SCORE 95 New 2-story office building cse, with 85,013 sf (to be 904 arastradero rd. U&o sent 6 12 14 Date: July 25, 2012 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 12000-01801 | |||||
SCORE 95 12000-01801: deferred submittal for plumbing seismic restraint Date: February 25, 2014 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 14rev-00116 | |||||
(ref permit #2-1801) revisions to vmware bldg cse: detail changes to the exterior light gauge steel framing. Date: June 17, 2013 Permit status: Permit issued | Permit id: 13rev-00384 | |||||
SCORE 95 12-1801: revisions to bldg cse, install accessible 2-way communication at elevator. Bulletin 22 Date: May 31, 2013 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 13rev-00358 | |||||
SCORE 95 (ref permit #12-1801) bldg cse deferred submittal for curtain wall construction Date: May 28, 2013 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 13rev-00354 | |||||
SCORE 95 (ref permit #12-1801) deferred submittal to bldg cse for metal stairs Date: May 23, 2013 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 13rev-00345 | |||||
SCORE 95 (ref permit #12-1801):structural revisions to bldg cse for bulletin 17 Date: April 5, 2013 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 13rev-00213 | |||||
SCORE 95 (ref permit #12-1801) bldg cse deferred submittal for roof trusses Date: April 8, 2013 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 13rev-00219 | |||||
SCORE 95 12000-01801: phase 3, bldg cse, bulletin 2, added drains and changed the size of the sanity sewer pipe within the campus from 4-inches to 6-inches. (p3-cse-rev6) Date: March 28, 2013 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 13rev-00197 | |||||
SCORE 95 (ref permit #12-1801) revisions to bldg cse: interior floor plan changes and the associated electrical, lighting and data changes. Bulletin #8 Date: February 28, 2013 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 13rev-00123 | |||||
SCORE 95 (ref permit #12-1801) bldg cse deferred submittal for structural brace frames Date: December 20, 2012 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 12rev-00707 | |||||
SCORE 95 (ref permit #12-1801) building cse changes: deletion of exterior sun shades, reduction of operable windows, misc changes to mechanical and electrical. Date: December 4, 2012 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 12rev-00666 | |||||
SCORE 95 (ref permit #12-1801) building cse revisions bulletin 6: revision to foundation. Change to all piers. Date: November 27, 2012 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 12rev-00654 | |||||
SCORE 95 (ref permit #12-1801) bldg cse revisions bulletin 3: structural changes to brace frame and misc concrete slab thickness info. Date: November 20, 2012 Contractor: Swinerton Builders Permit status: Permit issued | Permit id: 12rev-00642 |