Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Demolition permit Date: December 9, 2015 Client: Mohawk Community Investment | Permit status: Completed | Permit id: 654345 | |||||
Plumbing permit Date: November 24, 2015 Client: Mohawk Community Investment | Permit status: Completed | Permit id: 653228 | |||||
Zoning/use permit Date: December 9, 2015 Client: Mohawk Community Investment | Permit status: Completed | Permit id: 654343 | |||||
Demolition permit Date: December 9, 2015 Client: Mohawk Community Investment | Permit status: Completed | Permit id: 654345 | |||||
Plumbing permit Date: November 24, 2015 Client: Mohawk Community Investment | Permit status: Completed | Permit id: 653228 | |||||
Zoning use permit Date: December 9, 2015 Client: Mohawk Community Investment | Permit status: Completed | Permit id: 654343 | |||||
SCORE 100 For the complete demolition of an existing building. All construction must be in compliance with site safety plan. Full sidewalk closure required as reflected on approved site plan and in accordance with section 3306 of the ibc. Separate street closure permit required prior to start of work. Any deviation will require an amended building permit. Abatement of asbestos required prior to commencement of work Date: December 9, 2015 Contractor: Geppert Bros. Inc Client: Mohawk Community Investment | Permit type: Demolition permit | Permit status: Completed | Completion date: January 28, 2016 | Permit id: 654345 | |||||
SCORE 100 Close in place (1) one 2,000-gallon underground storage tank. The removal must comply with the regulations of the pennsylvania department of environmental protection. (padep) Date: November 20, 2017 Contractor: React Environmental Prof Servi Client: Mohawk Community Investment | Permit type: Demolition permit | Permit status: Active | Completion date: November 20, 2017 | Permit id: 833387 | |||||
SCORE 100 Seal sewer lateral pa one call #2015-3202207 Date: November 24, 2015 Contractor: Mr Ds Plumbing And Heating Client: Mohawk Community Investment | Permit type: Plumbing permit | Permit status: Completed | Completion date: February 20, 2016 | Permit id: 653228 | |||||
SCORE 100 Complete demolition of building Date: December 9, 2015 Contractor: Geppert Bros. Inc Client: Mohawk Community Investment | Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 29, 2017 | Permit id: 654343 |