Zoning/use permit Date: February 19, 2013 Permit status: Completed | Permit id: 453110 | |||||
Mechanical permit Date: March 13, 2014 Permit status: Completed | Permit id: 524056 | |||||
Administrative permit Date: August 29, 2014 Permit status: Completed | Permit id: 554631 | |||||
New construction permit Date: April 30, 2013 Permit status: Completed | Permit id: 464443 | |||||
Plumbing permit Date: June 23, 2014 Permit status: Completed | Permit id: 517971 | |||||
Electrical permit Date: February 26, 2014 Permit status: Completed | Permit id: 516719 | |||||
Suppression permit Date: September 18, 2014 Permit status: Completed | Permit id: 514448 | |||||
Alteration permit Date: April 21, 2014 Permit status: Completed | Permit id: 527034 | |||||
Zoning/use permit Date: April 21, 2014 Permit status: Completed | Permit id: 527177 | |||||
Mechanical permit Date: March 13, 2014 Client: C & M Student Housing Llc | Permit status: Completed | Permit id: 524056 | |||||
Alteration permit Date: April 21, 2014 Client: C & M Student Housing Llc | Permit status: Completed | Permit id: 527034 | |||||
Administrative permit Date: January 10, 2014 Client: C & M Student Housing Llc | Permit status: Completed | Permit id: 511103 | |||||
Suppression permit Date: September 18, 2014 Client: C & M Student Housing Llc | Permit status: Completed | Permit id: 514448 | |||||
Electrical permit Date: February 26, 2014 Client: C & M Student Housing Llc | Permit status: Completed | Permit id: 516719 | |||||
Zoning use permit Date: February 19, 2013 Client: C & M Student Housing Llc | Permit status: Completed | Permit id: 453110 | |||||
Plumbing permit Date: June 23, 2014 Client: C & M Student Housing Llc | Permit status: Completed | Permit id: 517971 | |||||
New construction permit Date: April 30, 2013 Client: C & M Student Housing Llc | Permit status: Completed | Permit id: 464443 | |||||
Zoning use permit Date: April 21, 2014 Client: C & M Student Housing Llc | Permit status: Completed | Permit id: 527177 | |||||
Ction of an attached structure(maximum height nte 38 feet) with cellar.(size and location a shown on the application). For use as five dwelling units. Date: February 26, 2013 Client: Wharton Realty Investment | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 29, 2014 | Permit id: 455262 | |||||
For the erection of an attached structure (height n. T. E. 38-0") with cellar and front bays. Size and location as shown in plans. For use as a multi-family residence (6 dwelling units). Date: February 19, 2013 Client: Wharton Realty Investment | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 29, 2014 | Permit id: 453110 | |||||
SCORE 100 Install a new 5" lateral,curb trap,fresh air inlet and (3)3 4" water services pa20140710670 Date: March 25, 2014 Contractor: Drain Masters Plumbing Llc Client: Wharton Realty Investment | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 9, 2014 | Permit id: 526460 | |||||
For alterations to interior layout, framing, exterior envelope and foundations as per approved plans. (see ap#464443 & ap#511103 for original plans and documentation). Date: April 21, 2014 Client: Wharton Realty Investment | Permit type: Alteration permit | Permit status: Completed | Completion date: October 3, 2014 | Permit id: 527034 | |||||
For reconfiguration of the proposed exterior dimensions of an attached structure. Size and location as per approved plans. (see ap#455262 for original size & location.). For a five (5) family dwelling as previously approved. Date: April 21, 2014 Client: Wharton Realty Investment | Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 17, 2014 | Permit id: 527177 | |||||
Amend building permit 464443 to remove and infill all windows located within 5 feet of the property line as per approved plans. Inspector to verify removal and infill of windows prior to issuance of certificate of occupancy. Nfpa 13 standard sprinkler system not required with window removal Date: August 29, 2014 Client: Wharton Realty Investment | Permit type: Administrative permit | Permit status: Completed | Completion date: October 3, 2014 | Permit id: 554631 | |||||
For the new construction of a (3) story,(5) family dwelling as per approved plans. Building to be sprinklered throughout in accordance with nfpa 13 separate permits required for mechanical, electrical, plumbing and fire suppression Date: April 30, 2013 Client: Wharton Realty Investment | Permit type: New construction permit | Permit status: Completed | Completion date: September 23, 2014 | Permit id: 464443 | |||||
To amend existing new construction permit 464443 to reflect additional bedrooms and bathrooms in cellar as per approved plans. Date: January 10, 2014 Client: Wharton Realty Investment | Permit type: Administrative permit | Permit status: Completed | Completion date: October 3, 2014 | Permit id: 511103 | |||||
SCORE 100 For resolution of dept. Of l&i case# 438888 for the installation of an automatic sprinkler system w. Two (2) inch fire service line & one & one-half (1 1 2) inch backflow prevention (bfp) assembly to serve a three (3) story above grade plane, w. Basement, mult-family building. Automatic sprinkler system installation in accordance with nfpa 13r. Date: September 18, 2014 Contractor: Oneida Fire Protection Client: Wharton Realty Investment | Permit type: Suppression permit | Permit status: Completed | Completion date: October 3, 2014 | Permit id: 514448 | |||||
SCORE 100 Install 400amp main ser vice, install 6 gang meter module, 5 meter for apts, 1 house all wiring throug out as per 2008 nec (west district) install fire alarm as per nfpa72 Date: February 26, 2014 Contractor: Baldwin Electrical Const Llc Client: Wharton Realty Investment | Permit type: Electrical permit | Permit status: Completed | Completion date: May 5, 2015 | Permit id: 516719 | |||||
SCORE 100 Install new house drain stack waste and water line and set fixtures wc, lav sinks,5 bath tubs,5 showers,2 stand pipe and 5 kitchen sinks Date: June 23, 2014 Contractor: Norman Cole Sr, Client: Wharton Realty Investment | Permit type: Plumbing permit | Permit status: Completed | Completion date: October 3, 2014 | Permit id: 517971 | |||||
SCORE 82 Install (5)1. 5 ton heat pumps with ductwork. Date: March 13, 2014 Contractor: Custom Air Flow Llc Client: Wharton Realty Investment | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 3, 2014 | Permit id: 524056 |