Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
SCORE 95 15-258: remove (2) lights to pantry Permit status: In plan check | Permit id: 17rev-00750 | |||||
SCORE 95 15-258: htg building clarification data and security associated architectural, mep work. Permit status: Completed | Permit id: 17rev-00089 | |||||
SCORE 95 15000-00258: deferred submittal 1 htg calculations and brb shops drawings Permit status: In plan check | Permit id: 17rev-00105 | |||||
SCORE 93 14-636 vmware: ht-a deferred submittal for glass wall. Permit status: Permit issued | Permit id: 14rev-00179 | |||||
SCORE 93 Vmware: ht-a offices located on 2nd and 3rd floors add (1) office and (1) boardroom including new walls, electrical fixtures, and hvac redistribution. Permit status: Permit issued | Permit id: 14000-00636 | |||||
SCORE 95 Revision includes steel stairs detail to boiler room. Permit status: Permit issued | Permit id: 13rev-00565 | |||||
SCORE 95 New city secondary electrical transformer, service entrance switchboard. Exiting upgrade for electric room. Permit status: Permit issued | Permit id: 12000-00248 | |||||
SCORE 95 (ref permit #12-431) revision to show accessible route to bus stop from bldg hta, civil details for accessible parking shown under main permit Permit status: Permit issued | Permit id: 12rev-00471 | |||||
Vmware htg new 2-story building core shell with office tenant improvement ~85,000sf. Includes large commercial kitchen for employees dining. Permit status: Lr - approved | Permit id: 15000-00258 | |||||
15-258: deferred plumbing bracing and seismic. Permit status: Completed | Permit id: 17rev-00601 | |||||
SCORE 95 15-258: bulletin #12, field clarification and restroom layout changes and av tv. Permit status: Completed | Permit id: 17rev-00176 | |||||
SCORE 95 15-258: revised office layouts and associated mep. Add new condensing unit on roof. Permit status: In plan check | Permit id: 17rev-00739 | |||||
SCORE 95 Vmware: building hta, new roof well for relocated chiller. Relocation of (2) boilers to (e)basement mechanical room. U&o sent 10 15 13 Permit status: Permit issued | Permit id: 12000-00431 | |||||
SCORE 95 15-258: revised electrical work and field clarification Permit status: Completed | Permit id: 17rev-00231 | |||||
SCORE 95 15-258: revised display details at various conference rooms and associated av. And dedicated ac units. Permit status: Completed | Permit id: 17rev-00551 | |||||
SCORE 95 15000-00258: deferred submittal for steel joists Permit status: Completed | Permit id: 17rev-00254 | |||||
SCORE 95 15-258: add ups system associated electrical . Permit status: Completed | Permit id: 17rev-00550 | |||||
15000-00258: deferred submittal for exterior guardrail. Permit status: Completed | Permit id: 17rev-00690 | |||||
SCORE 95 15-258:revised glass details conference rooms Permit status: Completed | Permit id: 17rev-00331 | |||||
SCORE 95 15-258: add scope to conduit run for future photovoltaic system and associated breaker. Permit status: Completed | Permit id: 17rev-00704 | |||||
14-258: deferred (3) stair designs Permit status: In plan check | Permit id: 17rev-00426 | |||||
15000-00258: seismic bracing for duct work for building htg Permit status: In plan check | Permit id: 17rev-00413 | |||||
SCORE 95 15-258: clarification egress coordination bulletin #17 Permit status: Completed | Permit id: 17rev-00491 | |||||
SCORE 95 15000-00258: vmware building htg deferred submittal for curtain wall system. Permit status: In plan check | Permit id: 17rev-00497 | |||||
SCORE 93 Vmware: ti to update electrical outlets and lighting (4536 sf) Permit status: Permit issued | Permit id: 17000-03033 | |||||
SCORE 95 15000-00258: revision to include deffered submittal for raised flooring system (dirtt access flooring system) Permit status: In plan check | Permit id: 17rev-00796 |