Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Zoning/use permit Date: April 24, 2015 Client: Taller Pr | Permit status: Completed | Permit id: 591297 | |||||
Electrical permit Date: November 6, 2015 Client: Taller Pr | Permit status: Expired | Permit id: 650103 | |||||
Demolition permit Date: February 12, 2016 Client: Taller Pr | Permit status: Completed | Permit id: 669633 | |||||
New construction permit Date: August 11, 2015 Client: Taller Pr | Permit status: Active | Permit id: 624587 | |||||
Zoning/use permit Date: October 15, 2014 Client: Taller Pr | Permit status: Completed | Permit id: 568240 | |||||
Mechanical permit Date: March 21, 2016 Client: Taller Pr | Permit status: Active | Permit id: 669256 | |||||
Operations permit Date: October 28, 2015 Client: Taller Pr | Permit status: Completed | Permit id: 23831 | |||||
Suppression permit Date: March 9, 2016 Client: Taller Pr | Permit status: Active | Permit id: 667372 | |||||
Operations permit Date: July 30, 2012 Client: Taller Pr | Permit status: Completed | Permit id: 21768 | |||||
Electrical permit Date: April 12, 2016 Client: Taller Pr | Permit status: Active | Permit id: 676345 | |||||
Plumbing permit Date: February 26, 2016 Client: Taller Pr | Permit status: Active | Permit id: 664975 | |||||
Zoning permit Date: August 22, 2014 Client: Taller Pr | Permit status: Completed | Permit id: 538397 | |||||
Administrative permit Date: September 30, 2016 Client: Taller Pr | Permit status: Active | Permit id: 716740 | |||||
Permit for the increase total number of off-street parking spaces from fifty-one(51) spaces including with five(5) accessible spaces with one(1) van accessible space to a eighty-six( 86) off-street parking spaces ; for a sit-down restaurant and retail consumer goods ( gift shop) on the same lot existing public, civic and institutional use ( library, cultural exhibits and educational facility ) with one(1) accessory flatwall sign as previously approved structure. Size and location as shown in the application. Date: March 13, 2015 Client: Taller Pr | Applicant: Peter Kelsen, Esq | Permit type: Appeal | Permit status: Granted | Completion date: April 22, 2015 | Permit id: 24787 | |||||
Demolition permit Date: February 12, 2016 Client: Taller Pr | Permit status: Completed | Permit id: 669633 | |||||
Plumbing permit Date: February 26, 2016 Client: Taller Pr | Permit status: Completed | Permit id: 664975 | |||||
Operations permit Date: July 30, 2012 Client: Taller Pr | Permit status: Completed | Permit id: 21768 | |||||
Electrical permit Date: March 15, 2016 Client: Taller Pr | Permit status: Completed | Permit id: 668749 | |||||
Zoning permit Date: August 22, 2014 Client: Taller Pr | Permit status: Completed | Permit id: 538397 | |||||
Mechanical permit Date: March 21, 2016 Client: Taller Pr | Permit status: Completed | Permit id: 669256 | |||||
Suppression permit Date: December 2, 2016 Client: Taller Pr | Permit status: Completed | Permit id: 738601 | |||||
Zoning use permit Date: October 16, 2014 Client: Taller Pr | Permit status: Completed | Permit id: 551878 | |||||
New construction permit Date: August 11, 2015 Client: Taller Pr | Permit status: Completed | Permit id: 624587 | |||||
Electrical permit Date: November 6, 2015 Client: Taller Pr | Permit status: Completed | Permit id: 650103 | |||||
Administrative permit Date: September 30, 2016 Client: Taller Pr | Permit status: Completed | Permit id: 716740 | |||||
Zoning use permit Date: April 24, 2015 Client: Taller Pr | Permit status: Completed | Permit id: 591297 | |||||
Operations permit Date: October 28, 2015 Client: Taller Pr | Permit status: Completed | Permit id: 23831 | |||||
Permit for the increase total number of off-street parking spaces from fifty-one(51) spaces including with five(5) accessible spaces with one(1) van accessible space to a eighty-six( 86) off-street parking spaces ; for a sit-down restaurant and retail consumer goods ( gift shop) on the same lot existing public, civic and institutional use ( library, cultural exhibits and educational facility ) with one(1) accessory flatwall sign as previously approved structure. Size and location as shown in the application. Date: March 13, 2015 Client: Taller Pr | Applicant: Peter Kelsen, Esq | Permit type: Appeal | Permit status: Granted | Completion date: April 22, 2015 | Permit id: 24787 | |||||
SCORE 100 Permit for the erection of one temporary tent x 60 Date: October 28, 2015 Contractor: Jefmar Party Rentals Client: Taller Pr | Permit type: Operations permit | Permit status: Completed | Permit id: 23831 | |||||
SCORE 100 07 27 2012 erect one (1) assembly use tent 40x40 Date: July 30, 2012 Contractor: Jefmar Party Rentals Client: Taller Pr | Permit type: Operations permit | Permit status: Completed | Permit id: 21768 | |||||
SCORE 100 For the installation of a (4) inch fire service line w. Backflow preventor (bfp) assembly and for installation of a fire suppression system as per nfpa 13. All work shall be in accordance with approved plans and hydraulic calculations. Date: March 9, 2016 Contractor: Fire Tech Automatic Client: Taller Pr | Permit type: Suppression permit | Permit status: Completed | Completion date: December 6, 2016 | Permit id: 667372 | |||||
SCORE 86 Interior plumbing construction for a (1)story latino community cultural center (taller puertorriqueno) - note: fuel gas, backflow prevention containment device, exterior and sewer water connections to the city mains require separate permit(s) - installation per the approved plans and the philadelphia plumbing code 2004 Date: February 26, 2016 Contractor: Rosati Mechanical Inc Client: Taller Pr | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 6, 2016 | Permit id: 664975 | |||||
SCORE 100 Install (1) one ansul r-102 3. 0-gallon (1) one ansul r-102 9. 0-gallon wet chemical comercial kitchen fire suppression system. Date: December 2, 2016 Contractor: Atlantic Fire Equipment Co Inc Client: Taller Pr | Permit type: Suppression permit | Permit status: Completed | Completion date: December 6, 2016 | Permit id: 738601 | |||||
SCORE 100 New hvac installation including mechanical equipment (rooftop units, vav boxes, etc) ductwork, exhaust fans and associated grilles, registers and diffusers. Separate permits required for all electrical and plumbing work and commercial kitchen hood exhaust fire suppression systems.. Boiler work excluded and separate requires approval from pennsylvania department of labor and industry Date: March 21, 2016 Contractor: Accord Mechanical And Mgmt Svs Client: Taller Pr | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 6, 2016 | Permit id: 669256 | |||||
SCORE 100 Closure via removal of three 5 gallon underground storage tanks containing #2 heating oil. Date: February 12, 2016 Contractor: React Environmental Prof Servi Client: Taller Pr | Permit type: Demolition permit | Permit status: Completed | Completion date: March 19, 2016 | Permit id: 669633 | |||||
SCORE 100 Provide & install complete fire alarm system with horns,strobes,pull stations as per nfpa 72 Date: April 12, 2016 Contractor: Emms Electric Inc Client: Taller Pr | Permit type: Electrical permit | Permit status: Completed | Completion date: December 6, 2016 | Permit id: 676345 | |||||
SCORE 100 Amending bldg permit #667372 to eliminate the dry type sprinkler system below the non-combustible canopy per section 8. 15. 7. 2 of nfpa 13. Date: September 30, 2016 Contractor: Fire Tech Automatic Client: Taller Pr | Permit type: Administrative permit | Permit status: Completed | Completion date: December 6, 2016 | Permit id: 716740 | |||||
Expand previously approves parking garage to 86 spaces Date: April 24, 2015 Client: Taller Pr | Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 24, 2015 | Permit id: 591297 | |||||
For the erection of one accessory flat sign, per plans. Date: October 15, 2014 Client: Taller Pr | Permit type: Zoning/use permit | Permit status: Completed | Completion date: October 15, 2014 | Permit id: 568240 | |||||
For the erection of a (1) story community center operated by non profit organization including accessory uses, (86) accessory parking spaces (including (5) accessible spaces), one accessory flat sign, per plans. Date: October 16, 2014 Client: Taller Pr | Permit type: Zoning/use permit | Permit status: Completed | Completion date: October 16, 2014 | Permit id: 551878 | |||||
SCORE 100 Install 200amp single phrase service for construction trailer in parking lot as per 2008 nec (north district) Date: November 6, 2015 Contractor: Emms Electric Inc Client: Taller Pr | Permit type: Electrical permit | Permit status: Completed | Completion date: December 6, 2016 | Permit id: 650103 | |||||
SCORE 99 New construction of one-story structure, parking lot construction. Signs included. Building fully sprinklered. No building demolition. Associated site civil work stormwater mgmt approved by others. Additional permits required:electrical, plumbing, hvac, sprinklers Date: August 11, 2015 Contractor: Allied Construction Services Client: Taller Pr | Permit type: New construction permit | Permit status: Completed | Completion date: December 6, 2016 | Permit id: 624587 | |||||
SCORE 100 Install new 12 amp service, provide & install site lighting, interior lighting, receptacles, switches and power conections to equipment including hvac. As per 2008 nec (north district) security by othes. Fire alarm permit to pulled separately no low voltage: phone, data Date: March 15, 2016 Contractor: Emms Electric Inc Client: Taller Pr | Permit type: Electrical permit | Permit status: Completed | Completion date: December 28, 2016 | Permit id: 668749 | |||||
SCORE 86 Pa20160341103 (community center) - (1)10", (1)12" & (1)18" storm lateral connection and a 6" sanitary lateral, house trap and partial house drain - note: sitework, stormwater management system and 2" domestic water distribution require separate permit(s) Date: February 16, 2016 Contractor: Rosati Mechanical Inc Client: Taller Pr | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 6, 2016 | Permit id: 668026 | |||||
For the lot adjustment to create one (1) lot from fifteen (15) deeded lots (2600, 2602, 2604, 2606, 2608, 2610, 2614, 2616, 2618, 2620, 2622, 2624 n 5th street, 2639 n reese street, 517 w huntingdon street, 521 w huntingdon street) and a portion of former reese street, and three (3) office of property assessment accounts (517-19 w huntingdon street, 521-25 w huntingdon street, and 2600-24 n 5th street). Size and location as shown on application. Date: August 22, 2014 Client: Taller Pr | Permit type: Zoning permit | Permit status: Completed | Completion date: August 22, 2014 | Permit id: 538397 | |||||
SCORE 100 Mechanical work, for installation of two type 1 kitchen hoods, fans and assoicated ductwork only, as per plans. See atttached mechanical permit #669256 for previous approved work Date: November 29, 2016 Contractor: Accord Mechanical And Mgmt Svs Client: Taller Pr | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 6, 2016 | Permit id: 737420 |