SCORE 100 Sewer connection for new sfd Engineer: N, A | Applicant: Production Plus Plumbing | Permit status: Finaled | Completion date: November 8, 2011 | Expiration date: June 26, 2012 | Permit id: 1106240010 | |||||
SCORE 99 Elect for roof-mount pv system - 1. 35 kw 6 panels 78. 78 sf Engineer: William Lou | Applicant: Sunpower Corp | Permit status: Finaled | Completion date: November 8, 2011 | Expiration date: September 8, 2012 | Permit id: 1109080040 | |||||
SCORE 100 Tpp for construction trailer Applicant: Power Plus | Permit status: Permisud | Expiration date: January 3, 2009 | Permit id: 807070034 | |||||
New sfd/gar/por plan 3 c 2,306/422/22 sf Engineer: Bassenian Logoni Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: November 8, 2011 | Expiration date: June 2, 2012 | Permit id: 1105170004 | |||||
New sfd/gar plan 2 cr 2906/606 sq ft Engineer: Bassenian Lagoni Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: November 15, 2006 | Expiration date: December 9, 2006 | Permit id: 605160017 | |||||
SCORE 99 Install roof-mount pv system - 1. 35 kw 6 panels 78. 78 sf Engineer: William Lou | Applicant: Sunpower Corp | Permit status: Finaled | Completion date: November 8, 2011 | Expiration date: September 8, 2012 | Permit id: 1109080064 | |||||
Workshop option @ tandem garage 136 sq ft Engineer: Bassenian Lagoni Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: November 15, 2006 | Expiration date: September 23, 2007 | Permit id: 609150051 | |||||
SCORE 100 Retaining wall 3h x 85l Engineer: Sikand Eng Associates | Applicant: Sikand Engineering - Frank Garcia | Permit status: Finaled | Completion date: November 15, 2006 | Expiration date: April 1, 2007 | Permit id: 603240063 | |||||
SCORE 100 Retaining wall 2. 7h x 90l Engineer: Sikand Eng Associates | Applicant: Sikand Engineering - Frank Garcia | Permit status: Finaled | Completion date: November 15, 2006 | Expiration date: April 1, 2007 | Permit id: 603240065 | |||||
SCORE 100 Connect new sfd to public sewer Applicant: Production Plus Plumbing | Permit status: Finaled | Completion date: November 15, 2006 | Expiration date: January 7, 2007 | Permit id: 607100008 | |||||
New sfd/gar plan 3 ar 3148/597 sq ft Engineer: Bassenian Lagoni Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: November 15, 2006 | Expiration date: December 9, 2006 | Permit id: 605160019 | |||||
New sfd gar plan 2 cr 2906 606 sq ft Engineer: Bassenian Lagoni Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: November 15, 2006 | Expiration date: December 9, 2006 | Permit id: 605160017 | |||||
New sfd gar plan 3 ar 3148 597 sq ft Engineer: Bassenian Lagoni Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: November 15, 2006 | Expiration date: December 9, 2006 | Permit id: 605160019 | |||||
New sfd gar por plan 3 c 2,306 422 22 sf Engineer: Bassenian Logoni Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: November 8, 2011 | Expiration date: June 2, 2012 | Permit id: 1105170004 |