Reviews Permit status: Closed | Completion date: February 28, 2006 | Permit id: 2006-112208-000 | |||||
Voice/data - voluntary seismic upgrade in conjuction with interior renovations of 1st and 2nd floors, remove some walls, doors, add back some for classrooms, work rooms, doors, flooring, ceiling, elec - voice;/data Permit type: Intake | Permit status: Closed | Completion date: November 18, 2014 | Permit id: 2014-239461-000 | |||||
Increasing the yemp rating for 2 sprinkler heads that are located above 2 kilns--3 sets of plans Permit type: Intake | Permit status: Closed | Completion date: November 25, 2014 | Permit id: 2014-242248-000 | |||||
Alarm-install duct detector units in mdf Permit type: Intake | Permit status: Closed | Completion date: December 16, 2014 | Permit id: 2014-250151-000 | |||||
Reconnect service at ht west Permit type: Electrical inspections | Permit status: Approved | Completion date: January 5, 2015 | Permit id: 2014-250627-000 | |||||
F13/ lower level - replace domstic hot water heat exchangers with condensing water heaters Permit type: Reviews | Permit status: Approved | Completion date: December 19, 2014 | Permit id: 2014-251500-000 | |||||
F13/ lower level - replace 3 domstic hot water heat exchangers & small boiler with 4 new condensing water heaters on existing pad plus 8 feet of new pad on either side of existing pad Permit type: Intake | Permit status: Closed | Completion date: December 19, 2014 | Permit id: 2014-251514-000 | |||||
Plumbing renovastion at pcc sylvania heat plant to replace 3 wh with 4 wh Permit type: Intake | Permit status: Closed | Completion date: December 22, 2014 | Permit id: 2014-252464-000 | |||||
Phase 2- alterations to the fire sprinklers as needed for t. I.- add, remove & relocate- 108 heads total Permit type: Intake | Permit status: Closed | Completion date: January 6, 2015 | Permit id: 2015-101614-000 | |||||
Fire alarm wiring - phase 2 level 2 office space renovation, open office area, conference rooms, computer lab and other spaces - fire alarm wiring Permit type: Intake | Permit status: Closed | Completion date: January 9, 2015 | Permit id: 2015-103298-000 | |||||
Pwr/controls - lower level - replace 3 domstic hot water heat exchangers & small boiler with 4 new condensing water heaters on existing pad - pwr/controls Permit type: Intake | Permit status: Closed | Completion date: January 13, 2015 | Permit id: 2015-104393-000 | |||||
B1/ csb document archives expansion, 21 x 14 chain link fence enclosure, relocate electrical receptacle, install hm door & frame Permit type: Reviews | Permit status: Approved | Completion date: January 16, 2015 | Permit id: 2015-106424-000 | |||||
Pwr - csb document archives expansion, 21 x 14 chain link fence enclosure, relocate electrical receptacle - pwr Permit type: Intake | Permit status: Closed | Completion date: January 23, 2015 | Permit id: 2015-109530-000 | |||||
Alterations to the fire alarm system as needed for t. I.- 42 devices total1- smoke detector9- strobes21- speaker/strobes11- pull stations Permit type: Intake | Permit status: Closed | Completion date: February 6, 2015 | Permit id: 2015-116016-000 | |||||
Construction of new learning garden canopy 12x16, open air structure, no walls, (4)wood posts, metal roof Permit type: Application | Permit status: Approved | Completion date: March 12, 2015 | Permit id: 2015-132717-000 | |||||
Voluntary construction of a stepped, storm water detention facility Permit type: Application | Permit status: Approved | Completion date: March 24, 2015 | Permit id: 2015-139222-000 | |||||
Adding sprinkler coverage below the theater stage. Permit type: Intake | Permit status: Closed | Completion date: April 7, 2015 | Permit id: 2015-146218-000 | |||||
Site lighting Permit type: Electrical inspections | Permit status: Approved | Completion date: June 26, 2015 | Permit id: 2015-150516-000 | |||||
F29/ phase 2; major renovations to the central east, ne, nw and upper mall areas of multipurpose student services building, concrete work, wall demo, flooring, ceilings, plbg, elec, etc Permit type: Reviews | Permit status: Approved | Completion date: April 20, 2015 | Permit id: 2015-153302-000 | |||||
F29/ new vavs, controls, hydronic piping, ductwork throughout Permit type: Intake | Permit status: Closed | Completion date: April 20, 2015 | Permit id: 2015-153304-000 | |||||
Le for camera install Permit type: Electrical inspections | Permit status: Approved | Completion date: May 4, 2015 | Permit id: 2015-161091-000 | |||||
Pwr - phase 2; major renovations to the central east, ne, nw and upper mall areas of multipurpose student services building, concrete work, wall demo, flooring, ceilings, plbg, elec - pwr Permit type: Intake | Permit status: Closed | Completion date: May 7, 2015 | Permit id: 2015-166876-000 | |||||
B2/ gas line to portable kiln Permit type: Reviews | Permit status: Approved | Completion date: May 18, 2015 | Permit id: 2015-172520-000 | |||||
B2/ gas line to existing portable kiln Permit type: Intake | Permit status: Closed | Completion date: May 18, 2015 | Permit id: 2015-172541-000 | |||||
Hazardous-install a 5 gallon well log and hooking up to greenhouse Permit type: Intake | Permit status: Approved | Completion date: May 28, 2015 | Permit id: 2015-176533-000 | |||||
Hazardous-installing a 5 gallon tank for vapor use. Permit type: Intake | Permit status: Approved | Completion date: May 28, 2015 | Permit id: 2015-176535-000 | |||||
Plumbing renovation at pcc sylvania cc building3 sinks, fs Permit type: Intake | Permit status: Closed | Completion date: May 28, 2015 | Permit id: 2015-177164-000 | |||||
B1/ bunker #2 & #3 re-roof project - remove rtus for re-roof and replace same equipment when roofing is complete Permit type: Reviews | Permit status: Approved | Completion date: June 12, 2015 | Permit id: 2015-185316-000 | |||||
F15/ kiln yard - seismic bracing (non-structural components) of brick kilns Permit type: Reviews | Permit status: Approved | Completion date: June 19, 2015 | Permit id: 2015-188677-000 | |||||
F15/ kiln yard - seismic bracing (non-structural components) of brick kilns Permit type: Intake | Permit status: Closed | Completion date: June 19, 2015 | Permit id: 2015-188682-000 | |||||
F18/ radiography/dental departments, 2nd & 3rd floors; remodel, new walls, ceiling, cabinets, counters, new equipment and anchoring, finishes, elec, plbg Permit type: Reviews | Permit status: Approved | Completion date: June 23, 2015 | Permit id: 2015-191084-000 | |||||
F18/ radiography/dental departments, 2nd & 3rd floors; remodel, new walls, ceiling, cabinets, counters, new equipment and anchoring, finishes, elec, plbg Permit type: Intake | Permit status: Closed | Completion date: June 23, 2015 | Permit id: 2015-191098-000 | |||||
F18/ new equipment, ductwork to existing systems, balance and relocate thermostats Permit type: Intake | Permit status: Closed | Completion date: June 23, 2015 | Permit id: 2015-191100-000 | |||||
B1/ bunker #2 & #3 re-roof project - new roof top mechanical units Permit type: Intake | Permit status: Closed | Completion date: July 1, 2015 | Permit id: 2015-195362-000 | |||||
B2/pr# pub saf/expansion of public safety office Permit type: Reviews | Permit status: Approved | Completion date: March 27, 2008 | Permit id: 2008-118372-000 | |||||
Intake Permit status: Closed | Completion date: November 19, 2009 | Permit id: 2009-172614-000 | |||||
B3/pr# sy1014-sylvania csb 314 ti/ sylvania csb fms office remodel Permit type: Reviews | Permit status: Approved | Completion date: May 27, 2010 | Permit id: 2010-141507-000 | |||||
Create project for mass notification device. Permit type: Reviews | Permit status: Approved | Completion date: September 13, 2010 | Permit id: 2010-175212-000 | |||||
Campus wide building energy and plumbing fixture water savings measures. Permit type: Reviews | Permit status: Approved | Completion date: September 24, 2010 | Permit id: 2010-179142-000 | |||||
F3/pr#sy1014-sylvaniacsb/hvac Permit type: Intake | Permit status: Closed | Completion date: May 18, 2011 | Permit id: 2011-140894-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Application | Permit status: Approved | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Issuance/intake | Permit status: Intake | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Process management | Permit status: Closed | Completion date: June 23, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Erosion control | Permit status: Approved | Completion date: July 5, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Site development | Permit status: Approved | Completion date: July 5, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Life safety | Permit status: Approved | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Structural | Permit status: Not reqd | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Commercial plumbing | Permit status: Not reqd | Completion date: July 1, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Fire bureau | Permit status: Not reqd | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Environmental services | Permit status: Approved | Completion date: July 11, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Transportation | Permit status: Not reqd | Completion date: July 7, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Transportation | Permit status: Approved | Completion date: July 8, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Transportation | Permit status: Closed | Completion date: July 8, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Water bureau review | Permit status: Not reqd | Completion date: June 22, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Parks bureau | Permit status: Approved | Completion date: July 1, 2011 | Permit id: 2011-150363-000 | |||||
One circuit for installation of pole lights for the roadway on propertyfaxed Permit type: Intake | Permit status: Closed | Completion date: February 24, 2012 | Permit id: 2012-115775-000 | |||||
New one story building for classrooms, office space and storage for automotive program Permit type: Application | Permit status: Approved | Completion date: March 13, 2012 | Permit id: 2012-119949-000 | |||||
4-tono packaged side wall heat pump, ductwork, plans w/12-119949 co Permit type: Intake | Permit status: Closed | Completion date: March 15, 2012 | Permit id: 2012-119952-000 | |||||
F12/ 1st floor library remodel, new offices & classroom for student success center, 2nd floor study room doors and new idf room, calcs for mechanical supports Permit type: Intake | Permit status: Closed | Completion date: May 14, 2012 | Permit id: 2012-140548-000 | |||||
F12/ 1st floor library remodel new mechanical equipment, air handler, chiller, pumps & vav units Permit type: Intake | Permit status: Closed | Completion date: May 14, 2012 | Permit id: 2012-140550-000 | |||||
Ew-data -:125,260, 3147684:health tech :sylvaniapr#20097087 healthplant Permit type: Intake | Permit status: Closed | Completion date: May 17, 2012 | Permit id: 2012-141954-000 | |||||
F12/ 1st floor library remodel, new offices & classroom for student success center, 2nd floor study room doors and new idf room, calcs for mechanical supportspr#20097070 Permit type: Intake | Permit status: Closed | Completion date: June 21, 2012 | Permit id: 2012-153795-000 | |||||
Reviews Permit status: Approved | Completion date: August 2, 2012 | Permit id: 2012-168375-000 | |||||
Pr-access:collegeserbg:sylvaniapr#csb 314 access Permit type: Reviews | Permit status: Approved | Completion date: September 4, 2012 | Permit id: 2012-178684-000 | |||||
New cabinet for battery back up equipment Permit type: Application | Permit status: Approved | Completion date: November 15, 2012 | Permit id: 2012-205864-000 | |||||
Install storm for new building Permit type: Intake | Permit status: Closed | Completion date: November 16, 2012 | Permit id: 2012-206117-000 | |||||
F10/ create 549 sq ft idf (telecom) and storage room on existing exterior covered deck located on the 2 level Permit type: Intake | Permit status: Closed | Completion date: April 9, 2013 | Permit id: 2013-137606-000 | |||||
F6/ complete renovation of the building including a new dynamometer pit, raised access platform, reconfigure classrooms and auto shop areas Permit type: Intake | Permit status: Closed | Completion date: April 23, 2013 | Permit id: 2013-142812-000 | |||||
F6/ complete renovation of the building including - replace existing new and controls, duct cleaning, balancing, fan coils units in classrooms and vfd on roof Permit type: Intake | Permit status: Closed | Completion date: April 23, 2013 | Permit id: 2013-142814-000 | |||||
F4/ voluntary seismic upgrade to structure Permit type: Intake | Permit status: Closed | Completion date: May 23, 2013 | Permit id: 2013-158815-000 | |||||
F16/ suite 123 lower level abe/ged office and classroom renovation Permit type: Intake | Permit status: Closed | Completion date: May 28, 2013 | Permit id: 2013-160567-000 | |||||
B2/ dfs for spray on fireproofing Permit type: Intake | Permit status: Closed | Completion date: September 25, 2013 | Permit id: 2013-161753-Dfs | |||||
B1/ cc building renovation - phase 1 - renovate the southeast portion of the bldg - dfs-02 mechanical equipment anchoring Permit type: Intake | Permit status: Closed | Completion date: April 1, 2014 | Permit id: 2013-161753-Dfs | |||||
Sprinkler - add (1) sprinkler and remove (1) sprinkler for new walls in t. I. Permit type: Intake | Permit status: Closed | Completion date: August 9, 2013 | Permit id: 2013-191206-000 | |||||
F7/ st bldg renovation phase 2 - 1st floor convert office space into classrooms, 2nd floor convert classrooms into office space and renovate portions of 2nd floor, 3rd floor renovate floor labs Permit type: Intake | Permit status: Closed | Completion date: September 24, 2013 | Permit id: 2013-209239-000 | |||||
F7/ st bldg renovation phase 2 modify existing hvac system, provide new exhauast snorkels at labs Permit type: Intake | Permit status: Closed | Completion date: September 24, 2013 | Permit id: 2013-209243-000 | |||||
F5/ 1st floor, classroom 111; rev-01 add classroom are replace part of the ceiling Permit type: Intake | Permit status: Closed | Completion date: December 24, 2013 | Permit id: 2013-225962-Rev | |||||
St bldg renovation phase 2 - 1st floor convert office space into classrooms, 2nd floor convert classrooms into office space and renovate portions of 2nd floor, 3rd floor renovate floor labspr# syvania bond-st phas Permit type: Intake | Permit status: Closed | Completion date: November 23, 2013 | Permit id: 2013-231760-000 | |||||
Sprinkler - relocate heads to maintain coverage around new walls and ceilings Permit type: Intake | Permit status: Closed | Completion date: December 27, 2013 | Permit id: 2013-242296-000 | |||||
Fire alarms-fire alarm improvements Permit type: Intake | Permit status: Closed | Completion date: February 4, 2014 | Permit id: 2014-113573-000 | |||||
F5/ voluntary seismic upgrade in conjuction with interior renovations of 1st and 2nd floors, remove some walls, doors, add back some for classrooms, work rooms, doors, flooring, ceiling, elec, plbg, finishes Permit type: Intake | Permit status: Closed | Completion date: February 6, 2014 | Permit id: 2014-114486-000 | |||||
B2/ dfs o1 for attachment of equipment Permit type: Intake | Permit status: Closed | Completion date: November 3, 2014 | Permit id: 2014-114486-Dfs | |||||
B2/ dfs 02 for buckling restrained brace welding Permit type: Intake | Permit status: Closed | Completion date: November 3, 2014 | Permit id: 2014-114486-Dfs | |||||
F5/ balancing, commissioning, equipment, layout modifications Permit type: Intake | Permit status: Closed | Completion date: February 6, 2014 | Permit id: 2014-114492-000 | |||||
New 16 sf open sided structure for kilns and pottery class; 68 high concrete wall at back wall and partial walls at sides; new stormwater planter at entrance, replace 6 fence at perimeter Permit type: Application | Permit status: Approved | Completion date: February 11, 2014 | Permit id: 2014-115082-000 | |||||
Gas piping, kiln exhaust fans, open shed for make up air, plans w/co Permit type: Intake | Permit status: Approved | Completion date: February 11, 2014 | Permit id: 2014-115083-000 | |||||
Plumbing renovation at pcc sylvania ct building Permit type: Intake | Permit status: Closed | Completion date: February 20, 2014 | Permit id: 2014-119132-000 | |||||
Pwr - voluntary seismic upgrade in conjuction with interior renovations of 1st and 2nd floors, remove some walls, doors, add back some for classrooms, work rooms, ceiling, elec, -pwr Permit type: Intake | Permit status: Closed | Completion date: March 4, 2014 | Permit id: 2014-123307-000 | |||||
F15/ cc building 2nd level office swing space remodel, new walls for private offices and remodel open office space Permit type: Intake | Permit status: Closed | Completion date: March 10, 2014 | Permit id: 2014-124992-000 | |||||
Pwr - cc building 2nd level office swing space remodel, new walls for private offices and remodel open office space - pwr Permit type: Intake | Permit status: Closed | Completion date: April 9, 2014 | Permit id: 2014-137904-000 | |||||
Electrical master permit - inspections Permit type: Intake | Permit status: Closed | Completion date: April 9, 2014 | Permit id: 2014-138507-000 | |||||
F4/ voluntary seismic separation of the exterior pedestrian bridge between the ss building and the st building Permit type: Intake | Permit status: Closed | Completion date: April 14, 2014 | Permit id: 2014-141109-000 | |||||
B2/ 1st floor mens restroom; mold and asbestos repair, remove one fixture, repair partitions and door, restore Permit type: Intake | Permit status: Closed | Completion date: April 18, 2014 | Permit id: 2014-144514-000 | |||||
Plumbing renovation at pcc sylvania ss building 1st floor mens restroom4 wc, 9 urinals, 8 lavs remove and replace Permit type: Intake | Permit status: Closed | Completion date: April 21, 2014 | Permit id: 2014-145271-000 | |||||
Enclose existing courtyard on east side with new roof and glazed exterior wall for a new entry in the pcc sylvania cc building Permit type: Application | Permit status: Approved | Completion date: May 15, 2014 | Permit id: 2014-157019-000 | |||||
Dfs for intumescent fireproofing Permit type: Application | Permit status: Approved | Completion date: October 21, 2014 | Permit id: 2014-157019-Dfs | |||||
Dfs for metal framed skylight Permit type: Application | Permit status: Approved | Completion date: October 21, 2014 | Permit id: 2014-157019-Dfs | |||||
Value added revision: structural steel members, details and calculations for skylight support, west wall stud framing and mechanical penetration Permit type: Application | Permit status: Approved | Completion date: March 24, 2015 | Permit id: 2014-157019-Rev | |||||
New ductwork connecting into an existing air handler unit for new enclosed entry, plans w/co Permit type: Intake | Permit status: Closed | Completion date: May 15, 2014 | Permit id: 2014-157023-000 | |||||
Sprinkler - relocate heads to maintain coverage around new walls & ceilings Permit type: Intake | Permit status: Closed | Completion date: May 16, 2014 | Permit id: 2014-157625-000 | |||||
F6/ ss-202 renovation to an existing classroom including removal and infill of a door and relite Permit type: Intake | Permit status: Closed | Completion date: May 19, 2014 | Permit id: 2014-158680-000 | |||||
B1/ cc - 1st floor mens restroom repair and renovation Permit type: Intake | Permit status: Closed | Completion date: May 30, 2014 | Permit id: 2014-163251-000 | |||||
Power - ss-202 renovation to an existing classroom including removal and infill of a door and relite Permit type: Intake | Permit status: Closed | Completion date: May 31, 2014 | Permit id: 2014-163592-000 | |||||
Plumbing renovation at pcc sylvania cc building mens rrr/r 4 wc, 8 lav, 8 urinals Permit type: Intake | Permit status: Closed | Completion date: June 2, 2014 | Permit id: 2014-163984-000 | |||||
Upgrade alarm system---2 sets of plans Permit type: Intake | Permit status: Closed | Completion date: June 5, 2014 | Permit id: 2014-165425-000 | |||||
Install catch basin and primer Permit type: Plumbing inspections | Permit status: Approved | Completion date: June 26, 2014 | Permit id: 2014-171532-000 | |||||
Adding new circuits from existing panels for lighting and receptacles Permit type: Electrical inspections | Permit status: Approved | Completion date: September 22, 2014 | Permit id: 2014-179904-000 | |||||
Relocate 2 strobes- no plans Permit type: Intake | Permit status: Closed | Completion date: July 23, 2014 | Permit id: 2014-188209-000 | |||||
Power - cc - 1st floor mens restroom repair and renovation Permit type: Intake | Permit status: Closed | Completion date: July 31, 2014 | Permit id: 2014-191577-000 | |||||
Alteration to the existing fire alarm system--2 sets of plans Permit type: Intake | Permit status: Closed | Completion date: July 31, 2014 | Permit id: 2014-191682-000 | |||||
F12/ ct building - little theater renovation including new stage floor and demo of small room Permit type: Reviews | Permit status: Approved | Completion date: July 31, 2014 | Permit id: 2014-191841-000 | |||||
F18/ phase 2 level 2 office space renovation, open office area, conference rooms, computer lab and other spaces Permit type: Reviews | Permit status: Approved | Completion date: August 26, 2014 | Permit id: 2014-204048-000 | |||||
F18/ phase 2 level 2 office space renovation - new ductwork, vavs and controls Permit type: Intake | Permit status: Closed | Completion date: August 26, 2014 | Permit id: 2014-204062-000 | |||||
Electrical for cc east entry Permit type: Electrical inspections | Permit status: Approved | Completion date: May 4, 2015 | Permit id: 2014-205464-000 | |||||
Plumbing renovation at pcc sylvania ss building level 200breakroom sink, df Permit type: Intake | Permit status: Closed | Completion date: September 16, 2014 | Permit id: 2014-213495-000 | |||||
Phase 2 level 2 office space renovation, open office area, conference rooms, computer lab and other spaces Permit type: Intake | Permit status: Closed | Completion date: September 16, 2014 | Permit id: 2014-213698-000 | |||||
Voice/data - phase 2 level 2 office space renovation, open office area, conference rooms, computer lab and other spaces - voice/data Permit type: Intake | Permit status: Closed | Completion date: September 18, 2014 | Permit id: 2014-214488-000 | |||||
Fire spirnkler - provide new sprinklers for new entry from existing fire sprinkler system Permit type: Intake | Permit status: Approved | Completion date: October 1, 2014 | Permit id: 2014-219912-000 | |||||
Replace existing mechanical equip Permit type: Electrical inspections | Permit status: Approved | Completion date: March 13, 2015 | Permit id: 2014-221245-000 | |||||
B1/ cc building/ mdf refrigeration upgrade Permit type: Reviews | Permit status: Approved | Completion date: October 17, 2014 | Permit id: 2014-226937-000 | |||||
Pwr - cc building/ mdf refrigeration upgrade - pwr Permit type: Intake | Permit status: Closed | Completion date: October 21, 2014 | Permit id: 2014-228228-000 | |||||
Replacement of 3/4 pipe and two ckts for out side lighting Permit type: Electrical inspections | Permit status: Approved | Completion date: November 7, 2014 | Permit id: 2014-234881-000 | |||||
Add a biodeisel fueling system to existing tanking area adjacent to auto shop Permit type: Application | Permit status: Approved | Completion date: September 17, 2007 | Permit id: 2007-162973-000 | |||||
Add a biodeisel fueling system to existing tanking area adjacent to auto shop Permit type: Planning and zoning | Permit status: Approved | Completion date: September 17, 2007 | Permit id: 2007-162973-000 | |||||
Add a biodeisel fueling system to existing tanking area adjacent to auto shop Permit type: Erosion control | Permit status: Not reqd | Completion date: September 17, 2007 | Permit id: 2007-162973-000 | |||||
Add a biodeisel fueling system to existing tanking area adjacent to auto shop Permit type: Environmental services | Permit status: Approved | Completion date: September 17, 2007 | Permit id: 2007-162973-000 | |||||
B2/ level 1, room 1 - divide office # 1 with new wall and door, relocate lighting, mech, electrical Permit type: Reviews | Permit status: Approved | Completion date: July 29, 2015 | Permit id: 2015-209045-000 | |||||
B2/ level 1, room 1 - relocate diffusers Permit type: Intake | Permit status: Closed | Completion date: July 29, 2015 | Permit id: 2015-209056-000 | |||||
Pwr - st2 bunker remodel, - pwr Permit type: Intake | Permit status: Closed | Completion date: August 1, 2015 | Permit id: 2015-210543-000 | |||||
Pwr - level 1, room 1 - divide office # 1 with new wall and door, relocate lighting, mech, electrical - pwr Permit type: Intake | Permit status: Closed | Completion date: August 12, 2015 | Permit id: 2015-217182-000 | |||||
Hvac controls - phase 2; major renovations to the central east, ne, nw and upper mall areas of multipurpose student services building, - hvac controls Permit type: Intake | Permit status: Closed | Completion date: August 28, 2015 | Permit id: 2015-227249-000 | |||||
Data/fire alarm wiring - phase 2; major renovations to the central east, ne, nw and upper mall areas of multipurpose student services building - data/fa wiring Permit type: Intake | Permit status: Closed | Completion date: August 31, 2015 | Permit id: 2015-228720-000 | |||||
Fire alarm system remodel to extend the mass notification system . Phase two of a 4 phased project. Permit type: Intake | Permit status: Closed | Completion date: September 8, 2015 | Permit id: 2015-233318-000 | |||||
Pwr - radiography/dental departments, 2nd & 3rd floors; remodel, new walls, ceiling, cabinets, counters, new equipment and anchoring, finishes, elec - pwr Permit type: Intake | Permit status: Closed | Completion date: September 9, 2015 | Permit id: 2015-233609-000 | |||||
Voice/data - radiography/dental departments, 2nd & 3rd floors; remodel - voice/data Permit type: Intake | Permit status: Closed | Completion date: September 11, 2015 | Permit id: 2015-235416-000 | |||||
F19/ room 112, replace vav with fan coil, install frequency drive and air balance machine shop Permit type: Reviews | Permit status: Approved | Completion date: October 6, 2015 | Permit id: 2015-246677-000 | |||||
Hazardous-switch out 5 gallon tank with a 5 gallon with wet leg. Permit type: Intake | Permit status: Approved | Completion date: October 8, 2015 | Permit id: 2015-247599-000 | |||||
Phase 2-sprinkler-adjust existing sprinkler system to accommodate remodel Permit type: Intake | Permit status: Closed | Completion date: October 21, 2015 | Permit id: 2015-254458-000 | |||||
Voice/data - phase 2; major renovations to the central east, ne, nw and upper mall areas of multipurpose student services building - voice/data Permit type: Intake | Permit status: Closed | Completion date: October 22, 2015 | Permit id: 2015-255215-000 | |||||
Control wiring - radiography/dental departments, 2nd & 3rd floors;imaging equipment - control wiring Permit type: Intake | Permit status: Closed | Completion date: October 27, 2015 | Permit id: 2015-257009-000 | |||||
Sprinkler - relocation of (2) sprinkler heads and raising of (1) sprinkler head Permit type: Intake | Permit status: Closed | Completion date: October 30, 2015 | Permit id: 2015-258497-000 | |||||
Pwr/controls - room 112, replace vav with fan coil, install frequency drive pwr Permit type: Intake | Permit status: Closed | Completion date: November 1, 2015 | Permit id: 2015-258922-000 | |||||
Alteration to at&t site to remove (1) gsm 850/19 antenna (3) one per sector (4)gsm 850/19 tmas (12)(4) per sector (1) lte 7 antenna per sector(3) totalreplace with(3)lte 700/19 (1)per sector lte 19 rrh total of 3 Permit type: Application | Permit status: Approved | Completion date: December 3, 2015 | Permit id: 2015-272396-000 | |||||
Private property tree removal permit Permit type: A - research | Permit status: Title 11 permit required | Completion date: December 15, 2015 | Permit id: 2015-277207-000 | |||||
B1/ server room - replace a/c mini split system and outdoor unit in mech room Permit type: Reviews | Permit status: Approved | Completion date: January 7, 2016 | Permit id: 2016-102111-000 | |||||
B1/ library server room - replace a/c min split and outdoor unit in mech room Permit type: Reviews | Permit status: Approved | Completion date: January 7, 2016 | Permit id: 2016-102120-000 | |||||
Plumbing renovation at pcc sylvania hp building Permit type: Reviews | Permit status: Approved | Completion date: February 9, 2016 | Permit id: 2016-118796-000 | |||||
Plumbing renovation at pcc sylvania hp buildingsewer Permit type: Intake | Permit status: Closed | Completion date: February 9, 2016 | Permit id: 2016-118803-000 | |||||
Plumbing renovationat pcc sylvania cc building phase 32-sinks,1-wall box Permit type: Intake | Permit status: Closed | Completion date: March 18, 2016 | Permit id: 2016-137431-000 | |||||
B2/install new split system heat pump and (2) indoor head units/outdoor unit to be mounted on wall with bracket. Permit type: Reviews | Permit status: Approved | Completion date: March 23, 2016 | Permit id: 2016-139880-000 | |||||
Elec - install new split system heat pump and (2) indoor head units - pwr Permit type: Intake | Permit status: Closed | Completion date: March 26, 2016 | Permit id: 2016-141065-000 | |||||
Stats-install new split system heat pump and (2) indoor head units - stats Permit type: Intake | Permit status: Closed | Completion date: March 26, 2016 | Permit id: 2016-141066-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Application | Permit status: Approved | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Issuance/intake | Permit status: Intake | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Process management | Permit status: Closed | Completion date: June 23, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Erosion control | Permit status: Approved | Completion date: July 5, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Site development | Permit status: Approved | Completion date: July 5, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Life safety | Permit status: Approved | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Structural | Permit status: Not reqd | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Commercial plumbing | Permit status: Not reqd | Completion date: July 1, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Fire bureau | Permit status: Not reqd | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Environmental services | Permit status: Approved | Completion date: July 11, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Transportation | Permit status: Not reqd | Completion date: July 7, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Transportation | Permit status: Approved | Completion date: July 8, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Transportation | Permit status: Closed | Completion date: July 8, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Water bureau review | Permit status: Not reqd | Completion date: June 22, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Parks bureau | Permit status: Approved | Completion date: July 1, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Permit expiration | Permit status: Extended | Completion date: December 30, 2015 | Permit id: 2011-150363-000 | |||||
Provide power and data to temporary work cubiclesfaxed Permit type: Electrical inspections | Permit status: Approved | Completion date: October 22, 2015 | Permit id: 2012-142710-000 | |||||
Relocate generator voip iifaxed Permit type: Electrical inspections | Permit status: Approved | Completion date: October 22, 2015 | Permit id: 2012-190102-000 | |||||
Install fire systemfaxed Permit type: Electrical inspections | Permit status: Approved | Completion date: October 22, 2015 | Permit id: 2013-172960-000 | |||||
Install fire alarmfaxed Permit type: Electrical inspections | Permit status: Approved | Completion date: March 3, 2016 | Permit id: 2013-225085-000 | |||||
Replace existing mechanical equipfaxed Permit type: Electrical inspections | Permit status: Approved | Completion date: March 13, 2015 | Permit id: 2014-221245-000 | |||||
F22/ dfs01 for skylight Permit type: Intake | Permit status: Closed | Completion date: September 30, 2015 | Permit id: 2015-153303-Dfs | |||||
F21/ rev 01 - additional steel support for the new skylight, change to framing Permit type: Intake | Permit status: Closed | Completion date: October 20, 2015 | Permit id: 2015-153303-Rev | |||||
F19/ phase 3 - revised office layout and associated electrical and mechanical Permit type: Intake | Permit status: Closed | Completion date: February 18, 2016 | Permit id: 2015-153303-Rev | |||||
F19/revised vav controls, hydronic piping and ductwork correlating with changes on main permit revision 02 (15-153303 rev 02 fa) Permit type: Intake | Permit status: Closed | Completion date: February 18, 2016 | Permit id: 2015-153304-Rev | |||||
Pwr - phase 2; major renovations to the central east, ne, nw and upper mall areas of multipurpose student services building, concrete work, wall demo, flooring, ceilings, plbg, elec - pwr Permit type: Intake | Permit status: Closed | Completion date: May 7, 2015 | Permit id: 2015-166876-000 | |||||
Plumbing renovation at pcc sylvania cc building3 sinks, fs Permit type: Intake | Permit status: Closed | Completion date: May 28, 2015 | Permit id: 2015-177164-000 | |||||
F18/ new equipment, ductwork to existing systems, balance and relocate thermostats Permit type: Intake | Permit status: Closed | Completion date: June 23, 2015 | Permit id: 2015-191100-000 | |||||
Pwr - bunker #2 & #3 re-roof project - remove rtus for re-roof and replace same equipment when roofing is complete - pwr Permit type: Intake | Permit status: Closed | Completion date: July 17, 2015 | Permit id: 2015-203263-000 | |||||
B1/ st2 bunker remodel, new entry doors and windows Permit type: Reviews | Permit status: Approved | Completion date: July 20, 2015 | Permit id: 2015-203812-000 | |||||
B1/ st2 bunker remodel, new entry door Permit type: Intake | Permit status: Closed | Completion date: July 20, 2015 | Permit id: 2015-203818-000 | |||||
Add a biodeisel fueling system to existing tanking area adjacent to auto shop Permit type: Application | Permit status: Approved | Completion date: September 17, 2007 | Permit id: 2007-162973-000 | |||||
Add a biodeisel fueling system to existing tanking area adjacent to auto shop Permit type: Planning and zoning | Permit status: Approved | Completion date: September 17, 2007 | Permit id: 2007-162973-000 | |||||
Add a biodeisel fueling system to existing tanking area adjacent to auto shop Permit type: Erosion control | Permit status: Not reqd | Completion date: September 17, 2007 | Permit id: 2007-162973-000 | |||||
Add a biodeisel fueling system to existing tanking area adjacent to auto shop Permit type: Environmental services | Permit status: Approved | Completion date: September 17, 2007 | Permit id: 2007-162973-000 | |||||
B2 level 1, room 1 - divide office # 1 with new wall and door, relocate lighting, mech, electrical Permit type: Reviews | Permit status: Approved | Completion date: July 29, 2015 | Permit id: 2015-209045-000 | |||||
B2 level 1, room 1 - relocate diffusers Permit type: Intake | Permit status: Closed | Completion date: July 29, 2015 | Permit id: 2015-209056-000 | |||||
Data fire alarm wiring - phase 2; major renovations to the central east, ne, nw and upper mall areas of multipurpose student services building - data fa wiring Permit type: Intake | Permit status: Closed | Completion date: August 31, 2015 | Permit id: 2015-228720-000 | |||||
Pwr - radiography dental departments, 2nd & 3rd floors; remodel, new walls, ceiling, cabinets, counters, new equipment and anchoring, finishes, elec - pwr Permit type: Intake | Permit status: Closed | Completion date: September 9, 2015 | Permit id: 2015-233609-000 | |||||
Voice data - radiography dental departments, 2nd & 3rd floors; remodel - voice data Permit type: Intake | Permit status: Closed | Completion date: September 11, 2015 | Permit id: 2015-235416-000 | |||||
F19 room 112, replace vav with fan coil, install frequency drive and air balance machine shop Permit type: Reviews | Permit status: Approved | Completion date: October 6, 2015 | Permit id: 2015-246677-000 | |||||
Voice data - phase 2; major renovations to the central east, ne, nw and upper mall areas of multipurpose student services building - voice data Permit type: Intake | Permit status: Closed | Completion date: October 22, 2015 | Permit id: 2015-255215-000 | |||||
Control wiring - radiography dental departments, 2nd & 3rd floors;imaging equipment - control wiring Permit type: Intake | Permit status: Closed | Completion date: October 27, 2015 | Permit id: 2015-257009-000 | |||||
Pwr controls - room 112, replace vav with fan coil, install frequency drive pwr Permit type: Intake | Permit status: Closed | Completion date: November 1, 2015 | Permit id: 2015-258922-000 | |||||
Alteration to at&t site to remove (1) gsm 850 19 antenna (3) one per sector (4)gsm 850 19 tmas (12)(4) per sector (1) lte 7 antenna per sector(3) totalreplace with(3)lte 700 19 (1)per sector lte 19 rrh total of 3 Permit type: Application | Permit status: Approved | Completion date: December 3, 2015 | Permit id: 2015-272396-000 | |||||
B1 server room - replace a c mini split system and outdoor unit in mech room Permit type: Reviews | Permit status: Approved | Completion date: January 7, 2016 | Permit id: 2016-102111-000 | |||||
B1 library server room - replace a c min split and outdoor unit in mech room Permit type: Reviews | Permit status: Approved | Completion date: January 7, 2016 | Permit id: 2016-102120-000 | |||||
B2 install new split system heat pump and (2) indoor head units outdoor unit to be mounted on wall with bracket. Permit type: Reviews | Permit status: Approved | Completion date: March 23, 2016 | Permit id: 2016-139880-000 | |||||
Elec - install new split system heat pump and (2) indoor head units - pwr Permit type: Intake | Permit status: Closed | Completion date: March 26, 2016 | Permit id: 2016-141065-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Application | Permit status: Approved | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Issuance/intake | Permit status: Intake | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Process management | Permit status: Closed | Completion date: June 23, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Erosion control | Permit status: Approved | Completion date: July 5, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Site development | Permit status: Approved | Completion date: July 5, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Life safety | Permit status: Approved | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Structural | Permit status: Not reqd | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Commercial plumbing | Permit status: Not reqd | Completion date: July 1, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Fire bureau | Permit status: Not reqd | Completion date: June 21, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Environmental services | Permit status: Approved | Completion date: July 11, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Transportation | Permit status: Not reqd | Completion date: July 7, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Transportation | Permit status: Approved | Completion date: July 8, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Transportation | Permit status: Closed | Completion date: July 8, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Water bureau review | Permit status: Not reqd | Completion date: June 22, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Parks bureau | Permit status: Approved | Completion date: July 1, 2011 | Permit id: 2011-150363-000 | |||||
Legalize temporary access road and paving - option 1 will approve the eventual removal and replanting of the areas within the environmental zones Permit type: Permit expiration | Permit status: Extended | Completion date: December 30, 2015 | Permit id: 2011-150363-000 | |||||
F7 st bldg renovation phase 2 - 1st floor convert office space into classrooms, 2nd floor convert classrooms into office space and renovate portions of 2nd floor, 3rd floor renovate floor labs Permit type: Intake | Permit status: Closed | Completion date: September 24, 2013 | Permit id: 2013-209239-000 | |||||
F7 st bldg renovation phase 2 modify existing hvac system, provide new exhauast snorkels at labs Permit type: Intake | Permit status: Closed | Completion date: September 24, 2013 | Permit id: 2013-209243-000 | |||||
New ductwork connecting into an existing air handler unit for new enclosed entry, plans w co Permit type: Intake | Permit status: Closed | Completion date: May 15, 2014 | Permit id: 2014-157023-000 | |||||
F12 ct building - little theater renovation including new stage floor and demo of small room Permit type: Intake | Permit status: Closed | Completion date: July 31, 2014 | Permit id: 2014-191843-000 | |||||
F18 phase 2 level 2 office space renovation, open office area, conference rooms, computer lab and other spaces Permit type: Intake | Permit status: Closed | Completion date: August 26, 2014 | Permit id: 2014-204049-000 | |||||
F18 phase 2 level 2 office space renovation - new ductwork, vavs and controls Permit type: Intake | Permit status: Closed | Completion date: August 26, 2014 | Permit id: 2014-204062-000 | |||||
Voice data - phase 2 level 2 office space renovation, open office area, conference rooms, computer lab and other spaces - voice data Permit type: Intake | Permit status: Closed | Completion date: September 18, 2014 | Permit id: 2014-214488-000 | |||||
F29 phase 2; major renovations to the central east, ne, nw and upper mall areas of multipurpose student services building, concrete work, wall demo, flooring, ceilings, plbg, elec, etc Permit type: Intake | Permit status: Closed | Completion date: April 20, 2015 | Permit id: 2015-153303-000 | |||||
F22 dfs01 for skylight Permit type: Intake | Permit status: Closed | Completion date: September 30, 2015 | Permit id: 2015-153303-Dfs | |||||
F21 rev 01 - additional steel support for the new skylight, change to framing Permit type: Intake | Permit status: Closed | Completion date: October 20, 2015 | Permit id: 2015-153303-Rev | |||||
F19 phase 3 - revised office layout and associated electrical and mechanical Permit type: Intake | Permit status: Closed | Completion date: February 18, 2016 | Permit id: 2015-153303-Rev | |||||
F29 new vavs, controls, hydronic piping, ductwork throughout Permit type: Intake | Permit status: Closed | Completion date: April 20, 2015 | Permit id: 2015-153304-000 | |||||
F19 revised vav controls, hydronic piping and ductwork correlating with changes on main permit revision 02 (15-153303 rev 02 fa) Permit type: Intake | Permit status: Closed | Completion date: February 18, 2016 | Permit id: 2015-153304-Rev | |||||
B2 gas line to portable kiln Permit type: Reviews | Permit status: Approved | Completion date: May 18, 2015 | Permit id: 2015-172520-000 | |||||
B2 gas line to existing portable kiln Permit type: Intake | Permit status: Closed | Completion date: May 18, 2015 | Permit id: 2015-172541-000 | |||||
B1 bunker #2 & #3 re-roof project - remove rtus for re-roof and replace same equipment when roofing is complete Permit type: Reviews | Permit status: Approved | Completion date: June 12, 2015 | Permit id: 2015-185316-000 | |||||
F15 kiln yard - seismic bracing (non-structural components) of brick kilns Permit type: Reviews | Permit status: Approved | Completion date: June 19, 2015 | Permit id: 2015-188677-000 | |||||
F18 radiography dental departments, 2nd & 3rd floors; remodel, new walls, ceiling, cabinets, counters, new equipment and anchoring, finishes, elec, plbg Permit type: Reviews | Permit status: Approved | Completion date: June 23, 2015 | Permit id: 2015-191084-000 | |||||
F18 new equipment, ductwork to existing systems, balance and relocate thermostats Permit type: Intake | Permit status: Closed | Completion date: June 23, 2015 | Permit id: 2015-191100-000 | |||||
Pwr - bunker #2 & #3 re-roof project - remove rtus for re-roof and replace same equipment when roofing is complete - pwr Permit type: Intake | Permit status: Closed | Completion date: July 17, 2015 | Permit id: 2015-203263-000 | |||||
B1 st2 bunker remodel, new entry doors and windows Permit type: Reviews | Permit status: Approved | Completion date: July 20, 2015 | Permit id: 2015-203812-000 | |||||
B1 st2 bunker remodel, new entry door Permit type: Intake | Permit status: Closed | Completion date: July 20, 2015 | Permit id: 2015-203818-000 | |||||
Build a new 6 sq ft accessory sculpture building for art department Client: Southwest Neighborhoods, Inc. | Permit type: New construction | Permit status: Final | Completion date: July 5, 2005 | Current use: Business | Permit id: 2002-152652-000 | |||||
Remove (3) existing anntenas and replace w 9 panel ant. Client: Southwest Neighborhoods, Inc. | Permit type: Alteration | Permit status: Final | Completion date: March 1, 2006 | Current use: Utility | Permit id: 2005-130902-000 | |||||
New three story college services building for maintenance shops and admin offices Client: Southwest Neighborhoods, Inc. | Permit type: New construction | Permit status: Final | Completion date: June 19, 2008 | Current use: Factory/industrial | Permit id: 2005-128108-000 | |||||
24 x 36 detached greenhouse for horticulture use Client: Southwest Neighborhoods, Inc. | Permit type: New construction | Permit status: Under inspection | Current use: Educational | Permit id: 2005-139020-000 | |||||
Demo gate house Client: Southwest Neighborhoods, Inc. | Permit type: Demolition | Permit status: Issued | Current use: Educational | Permit id: 2006-153373-000 | |||||
Public safety radio tower Client: Southwest Neighborhoods, Inc. | Permit type: New construction | Permit status: Final | Completion date: July 14, 2009 | Current use: Utility | Permit id: 2008-163780-000 | |||||
New 648 sf green house used primarily for horticultural or agricultural purposes and not human habitation. Client: Southwest Neighborhoods, Inc. | Permit type: New construction | Permit status: Final | Completion date: April 5, 2010 | Current use: Utility | Permit id: 2009-148274-000 | |||||
Alter pavement to add solar powered ticket station, reconfigure landscaping, add new bio swale Client: Southwest Neighborhoods, Inc. | Permit type: Alteration | Permit status: Final | Completion date: January 6, 2012 | Current use: Utility | Permit id: 2011-176286-000 | |||||
Install french drain at rear of health technology building at loading dock entrance and tie into existing manhole, pave over new line Client: Southwest Neighborhoods, Inc. | Permit type: Alteration | Permit status: Final | Completion date: June 21, 2012 | Current use: Educational | Permit id: 2012-109368-000 | |||||
Demolish four existing storage containers for future classroom storage Client: Southwest Neighborhoods, Inc. | Permit type: Demolition | Permit status: Final | Completion date: September 27, 2012 | Current use: Utility | Permit id: 2012-119943-000 | |||||
New exterior elevator to serve 2nd floor of cc building and roof level; associated site work and landscaping Client: Southwest Neighborhoods, Inc. | Permit type: Addition | Permit status: Final | Completion date: January 8, 2014 | Current use: Educational | Permit id: 2012-207263-000 | |||||
Relocate 3 antennas and adding 6 for total of 9 antennas Client: Southwest Neighborhoods, Inc. | Permit type: Alteration | Permit status: Final | Completion date: December 13, 2013 | Current use: Utility | Permit id: 2013-103661-000 | |||||
New 16 sf open sided structure for kilns and pottery class; 68" high concrete wall at back wall and partial walls at sides; new stormwater planter at entrance, replace 6 fence at perimeter Client: Southwest Neighborhoods, Inc. | Permit type: New construction | Permit status: Final | Completion date: September 26, 2014 | Current use: Business | Permit id: 2014-115082-000 | |||||
Demolish 5 sf existing open sided kiln shed, remove all debris Client: Southwest Neighborhoods, Inc. | Permit type: Demolition | Permit status: Final | Completion date: May 16, 2014 | Current use: Storage | Permit id: 2014-115073-000 | |||||
Alteration to at&t site to remove (1) gsm 850 19 antenna (3) one per sector (4)gsm 850 19 tmas (12)(4) per sector (1) lte 7 antenna per sector(3) total replace with(3)lte 700 19 (1)per sector lte 19 rrh total of 3 Client: Southwest Neighborhoods, Inc. | Permit type: Addition | Permit status: Final | Completion date: December 23, 2016 | Current use: Utility | Permit id: 2015-272396-000 |