Zoning permit Date: December 17, 2009 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 232737 | |||||
Zoning/use permit Date: January 8, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 253961 | |||||
New construction permit Date: January 21, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 248951 | |||||
Mechanical permit Date: July 16, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 288763 | |||||
Plumbing permit Date: April 21, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 270704 | |||||
Suppression permit Date: July 8, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 269772 | |||||
Electrical permit Date: September 22, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 273688 | |||||
Permit for the relocation of lot lines to create one (1) lot from two (2) lots, for the erection of a two (2) story detached structure max height not to exceed 35 ft for use as a two (2) family dwelling, for three (3) accessory open air parking spaces in the rear. Date: September 21, 2009 Client: Evelyn Sanders 2 Lp | Applicant: Kim Dolan, Esquire & Mark E. Levin, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: November 17, 2009 | Permit id: 10063 | |||||
Plumbing permit Date: April 21, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 270704 | |||||
Suppression permit Date: July 8, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 269772 | |||||
New construction permit Date: January 21, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 248951 | |||||
Zoning use permit Date: January 8, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 253961 | |||||
Zoning permit Date: December 17, 2009 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 232737 | |||||
Mechanical permit Date: July 16, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 288763 | |||||
Electrical permit Date: September 22, 2010 Client: Evelyn Sanders 2 Lp | Permit status: Completed | Permit id: 273688 | |||||
Permit for the relocation of lot lines to create one (1) lot from two (2) lots, for the erection of a two (2) story detached structure max height not to exceed 35 ft for use as a two (2) family dwelling, for three (3) accessory open air parking spaces in the rear. Date: September 21, 2009 Client: Evelyn Sanders 2 Lp | Applicant: Kim Dolan, Esquire & Mark E. Levin, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: November 17, 2009 | Permit id: 10063 | |||||
SCORE 100 New construction,2 family,14 fixtures with piping throughout Date: April 21, 2010 Contractor: Jr Mcgee Plumbing Llc Client: Evelyn Sanders 2 Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 25, 2011 | Permit id: 270704 | |||||
SCORE 100 Install fire suppression system as per plans. Date: July 8, 2010 Contractor: Angkor Contracting Services Client: Evelyn Sanders 2 Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: January 26, 2011 | Permit id: 269772 | |||||
SCORE 100 Install 2 heaters and air condition units Date: July 16, 2010 Contractor: City Mechanical Inc Client: Evelyn Sanders 2 Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: January 26, 2011 | Permit id: 288763 | |||||
Consol 2 lots into 1 lot. Construct 1 2 story duplex unit with 3 parking spaces. Unit is with flat roof system Date: January 8, 2010 Client: Evelyn Sanders 2 Lp | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 8, 2010 | Permit id: 253961 | |||||
Consol 2 lots into 1 lot. Construct 1 2 story duplex unit with 3 parking spaces. Unit is with flat roof system Date: December 17, 2009 Client: Evelyn Sanders 2 Lp | Permit type: Zoning permit | Permit status: Completed | Completion date: December 17, 2009 | Permit id: 232737 | |||||
SCORE 100 Wire duplex wire, install 200amp service, 100amp service for each apartments, 3 meters, ground rod, telephone and catv as per 2005 nec (north district) Date: September 22, 2010 Contractor: Derrick Townes Client: Evelyn Sanders 2 Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: February 23, 2011 | Permit id: 273688 | |||||
Erection of one duplex unit with accessible unit on the 1st fl as per plan. See a p 248946 for plans Date: January 21, 2010 Client: Evelyn Sanders 2 Lp | Permit type: New construction permit | Permit status: Completed | Completion date: January 26, 2011 | Permit id: 248951 |