SCORE 95 15-257: clarification door schedule. Permit status: In plan check | Permit id: 17rev-00749 | |||||
SCORE 95 15-257: deferred buckling restraint bracing design. Permit status: Completed | Permit id: 17rev-00124 | |||||
SCORE 95 15-257; csg building clarification data and security associated architectural and mep. Permit status: Completed | Permit id: 17rev-00090 | |||||
15000-00257: seismic bracing for ductwork for building csg Permit status: In plan check | Permit id: 17rev-00412 | |||||
15-257: deferred plumbing and seismic for c&sg Permit status: In plan check | Permit id: 17rev-00600 | |||||
SCORE 95 15ooo-oo257: revised interior perimeter office layout. Permit status: Completed | Permit id: 17rev-00269 | |||||
SCORE 95 15-257: bulletin #12, field clarification and restroom layout changes. Permit status: Completed | Permit id: 17rev-00175 | |||||
SCORE 95 Vmware csg building core shell and office tenant improvement ~100,000sf. Includes gym for employees. Scope also includes site improvements and landscaping. Permit status: Permit issued | Permit id: 15000-00257 | |||||
SCORE 95 16-257: revised plans include removal of an oak tree and also dimensional clarification. Permit status: Completed | Permit id: 17rev-00230 | |||||
SCORE 95 15000-00257: deferred submittal for steel joists Permit status: Completed | Permit id: 17rev-00255 | |||||
SCORE 95 15-257: revised office layouts on 1st and 2nd floor. Split large conference rooms into two. Permit status: Completed | Permit id: 17rev-00648 | |||||
SCORE 95 15-257: add scope to run conduit for future photovoltaic system and associated breaker. Permit status: Completed | Permit id: 17rev-00703 | |||||
15-257: deferred stair (3) design Permit status: In plan check | Permit id: 17rev-00427 | |||||
15000-00257: deferred submittal for exterior guardrail Permit status: Completed | Permit id: 17rev-00689 | |||||
SCORE 95 15000-00257: vmware building csg deferred submittal for curtain wall system Permit status: In plan check | Permit id: 17rev-00496 | |||||
SCORE 95 15-257: temporary power 200kw with diesel generator. Prparation for utilities infrastructure upgrades. Permit status: Permit issued | Permit id: 17rev-00763 | |||||
SCORE 95 15000-00257: revision includes revised electrical power feed to (e) ups rack from 30amp to 70amp Permit status: In plan check | Permit id: 17rev-00807 |