Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 93 Sprint-2-aaon rl-230-3-08boz-0 air cooled rtu 60975 cfm ea, 2-aaon lza-2 air cooled chillers 195. 3 ton ea Date: May 3, 2016 Contractor: Blaine Wilcoxson Permit type: Commercial air conditioning air distribution systems | Permit status: Issued | Permit id: Mec-16-02703 | |||||
SCORE 93 Sprint-pump house with (2) 145 gpm base mounted end suction pumps Date: May 3, 2016 Contractor: Blaine Wilcoxson Permit type: Hydronic/process/ammonia piping systems | Permit status: Issued | Permit id: Mec-16-02704 | |||||
SCORE 93 Sprint-4 fusible link safety shut off valves Date: November 25, 2013 Contractor: Blaine Wilcoxson Permit type: Hydronic/process/ammonia piping systems | Permit status: Issued | Permit id: Mec-13-10123 | |||||
SCORE 93 Sprint-2 ruskin fire dampers ruskin smoke dampers Date: November 25, 2013 Contractor: Blaine Wilcoxson Permit type: Commercial air conditioning air distribution systems | Permit status: Issued | Permit id: Mec-13-10063 | |||||
Sprint service repair Date: December 16, 2016 Permit type: Commercial electrical | Permit status: Issued | Permit id: Elc-16-11221 | |||||
Provide wiring to 2 new cooling towers that replaced existing. Date: August 11, 2016 Permit type: Commercial electrical | Permit status: Issued | Permit id: Elc-16-07137 | |||||
SCORE 56 Sprint - adding platform to roof (non sq ft addition), patching roof Permit type: Plans required - commercial building additions | Permit status: Pending | Permit id: Bld-16-03019 | |||||
We will be strictly performing maintenance testing and cleaning of the main breaker. The breaker is located on the line side of the utility, so a temporary utility disconnect is required to safely complete the work. There will be no upgrades changes to the equipment. Date: December 12, 2016 Permit type: Commercial electrical | Permit status: Issued | Permit id: Elc-16-11042 |