Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 97 New 2524 sf,2 story,sfr w/ 653 sf att garage,24 sf porch & 18 sf balcony. Applicant: Fan Daphne | Permit status: Finaled | Completion date: December 14, 2005 | Permit id: 0502140034 | |||||
SCORE 97 Demo exist residence 9 s. F. Applicant: Fan Daphne | Permit status: Finaled | Completion date: December 14, 2005 | Permit id: 0505250111 | |||||
SCORE 97 Temporary power pole Date: May 25, 2005 Contractor: Benchmark Construction Applicant: Fan Daphne | Permit status: Finaled | Completion date: December 14, 2005 | Permit id: 0505250047 | |||||
SCORE 91 Electrical for new sfr,upgrade panel to 2 amps. Date: August 12, 2005 Contractor: To The Lam Applicant: Lam To | Permit status: Finaled | Completion date: December 14, 2005 | Permit id: 0508120041 | |||||
SCORE 59 Plumbing for new sfr. Date: June 21, 2005 Contractor: Hydro Tech Plumbing Corp Applicant: Hydro - Tech Plumbing Corp Daphne | Permit status: Finaled | Completion date: December 14, 2005 | Permit id: 0506210005 | |||||
SCORE 97 Connect new sfr to public sewer Date: June 21, 2005 Contractor: Benchmark Construction Applicant: Fan Daphne | Permit status: Finaled | Completion date: December 14, 2005 | Permit id: 0506210005 |