Building Permits at 651 Huntington Av Boston MA


Estimated Price

Beds

Baths

Rooms

Sq.Ft.

Built:   Lot size:   Taxed:
RENOVATION HISTORY
Based on the information received from building department, associated with 651 Huntington Av Boston MA over the past .

If you are considering hiring for your home renovation project, we recommend using our bidding system to get competitive quotes.

ACTIVITY



PERMITS VALUATION



RENOVATIONS
Find out the best time of the year to complete your project on a minimal budget.
Get several free quotes from best contractors in your area.

REQUEST A QUOTE
Explore CheckPermit
Our dataset includes 30 milion building permits across 4 million addresses in US.

We analyzed and ranked over 1 million home remodeling contractors based on official government sources.

Every contractor's rank is calculated based on official government records.
RECENT PROJECTS


Content Date Cost Contractor Rank Address Contractor
SCORE
88
Add 5 devices to existing system 2 pull stations and 3 speaker strobes doc20111341
Date:  January 9, 2012

Permit type: Bfd fire alarm installations | Permit id: Bfdf110756
2012/01/09088651 Huntington Av Boston MaPaul Dunphy Harvard University
Welding of elevator equipment;in fxb-bldg (dpl) bfd paid detail required
Date:  August 30, 2012

Permit type: Bfd cutting-burning-welding | Permit id: Cbw170473
2012/08/30095651 Huntington Av Boston Ma
Harvard school of public health.; removal of duct insulation and glue daubs fromroom 433
Date:  October 22, 2015

Permit type: Bfd asbestos removal | Permit id: Asb532144
2015/10/22095651 Huntington Av Boston Ma
Harvard school of public health. ;removal of duct insulation and glue daubs from room 433
Date:  December 7, 2015

Permit type: Bfd asbestos removal | Permit id: Asb540081
2015/12/07095651 Huntington Av Boston Ma
SCORE
100
Miscellaneous renovations to the 6th floor and add (3) fire alarm strobe only devices to the existing system.
Date:  January 9, 2016
Contractor: Francis Averill

Client: Childrens Hosp | Permit type: Bfd fire alarm installations | Permit id: Bfdf549457 | Parcel: 0401880000
2016/01/090100651 Huntington Av Boston MaFrancis Averill
Burning &; welding to install new piping;(dpl) bfd paid detail required
Date:  January 22, 2010

Permit type: Bfd cutting-burning-welding | Permit id: Cbw11024
2010/01/22095651 Huntington Av Boston Ma
SCORE
100
Relocate elevator disconnect switches in machine room. Install cab light disconnects at harvard school of public health.
Date:  October 26, 2012
Value:   $7,500
Contractor: Dennis Mahoney

Client: Childrens Hosp | Permit type: Electrical permit | Expiration date: April 26, 2013 | Current use: Other | Permit id: E195378 | Parcel: 0401880000
2012/10/267500100651 Huntington Av Boston MaDennis Mahoney
SCORE
96
Remove and replace exterior facade sealants at the metal panels windows and masonry facade
Date:  May 22, 2012
Value:   $159,750
Contractor: Anthony Kelley

Permit type: Short form bldg permit | Expiration date: November 22, 2012 | Current use: Comm | Permit id: Sf142316
2012/05/2215975096651 Huntington Av Boston MaAnthony Kelley
Bfd chemist certificate proces
Date:  June 21, 2014

Permit id: Chm374903
2014/06/21095651 Huntington Av Boston Ma
Install tie back anchors and fall protection systems bfd paid detail required
Date:  May 11, 2012

Permit type: Bfd cutting-burning-welding | Permit id: Cbw137356
2012/05/11095651 Huntington Av Boston Ma
Cutting &; welding metal equipment skids and bracketing for equipment replacement bfd paid detail required
Date:  October 1, 2013

Permit type: Bfd cutting-burning-welding | Permit id: Cbw289151
2013/10/01095651 Huntington Av Boston Ma
Cutting / burning / welding of piping for relocation of a natural gas meter (dpl) for each separate location bfd paid detail required
Date:  November 26, 2013

Permit type: Bfd cutting-burning-welding | Permit id: Cbw307148
2013/11/26095651 Huntington Av Boston Ma
Cutting burning welding of piping for relocation of a natural gas meter (dpl) for each separate location bfd paid detail required
Date:  November 26, 2013

Permit type: Bfd cutting-burning-welding | Permit id: Cbw307148
2013/11/26095651 Huntington Av Boston Ma
SCORE
86
No other sprinkler zone shall be impaired during this scheduled impairment ; coordinate this impairment with the buildings nfpa 241 impairment coordinator. Installation shall be in-accordance with the requirements of 7 cmr nfpa 13 and isd approved shop drawings..
Date:  March 17, 2017
Contractor: Charles Pratt

Client: President & Fellows | Permit type: Bfd sprinkler system | Permit id: Sprk679832 | Parcel: 0401880000
2017/03/17086651 Huntington Av Boston MaCharles Pratt
SCORE
98
Burning and welding for the removal of existing elevator compensation cables and installation of new compensation cables (dpl 3 3 17) bfd paid detail required
Date:  February 27, 2017
Contractor: John Dalton

Client: President & Fellows | Permit type: Bfd cutting-burning-welding | Permit id: Cbw682233 | Parcel: 0401880000
2017/02/27098651 Huntington Av Boston MaJohn Dalton
BEST LOCAL CONTRACTORS




Contractor Rank Contractor Details Number of Projects Avg. Project Cost Years in Business Photos
Need a Contractor ?
Just fill out a form below and get several free quotes from best local contractors in your area.