Plumbing permit Date: May 13, 2016 Permit status: Completed | Permit id: 691798 | |||||
Use permit Date: March 2, 2016 Permit status: Completed | Permit id: 673058 | |||||
Electrical permit Date: May 9, 2016 Permit status: Active | Permit id: 690357 | |||||
Mechanical permit Date: May 10, 2016 Permit status: Active | Permit id: 690905 | |||||
Alteration permit Date: April 18, 2016 Permit status: Active | Permit id: 684894 | |||||
Permit for for the erection of a rear addition at the 2nd and 3rd floor levels and for the erection of rear decks on the 2nd and 3rd floor level with a spiral stair leading to a roof deck above the 3rd floor. Structure for use as Date: July 23, 2014 Applicant: Zhen H. Jin, Esq | Permit type: Appeal | Permit status: Granted/prov | Permit id: 23388 | |||||
Alteration permit Date: April 18, 2016 Client: Dl & Ys Llc | Permit status: Completed | Permit id: 684894 | |||||
Use permit Date: March 2, 2016 Client: Dl & Ys Llc | Permit status: Completed | Permit id: 673058 | |||||
Electrical permit Date: May 9, 2016 Client: Dl & Ys Llc | Permit status: Completed | Permit id: 690357 | |||||
Plumbing permit Date: April 27, 2016 Client: Dl & Ys Llc | Permit status: Completed | Permit id: 687533 | |||||
Mechanical permit Date: May 10, 2016 Client: Dl & Ys Llc | Permit status: Completed | Permit id: 690905 | |||||
Permit for for the erection of a rear addition at the 2nd and 3rd floor levels and for the erection of rear decks on the 2nd and 3rd floor level with a spiral stair leading to a roof deck above the 3rd floor. Structure for use as Date: July 23, 2014 Client: Dl & Ys Llc | Applicant: Zhen H. Jin, Esq | Permit type: Appeal | Permit status: Granted/prov | Permit id: 23388 | |||||
SCORE 92 Drywall kitchen tile floor ez permit standard alterations- for alterations to an existing one family dwelling as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: April 18, 2016 Contractor: Hui B Huang Client: L & Ys Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: December 15, 2016 | Permit id: 684894 | |||||
SCORE 100 Replace curb trap & fai pa20161333291 "self-certifications are no longer permitted" - "all excavations and plumbing trenches in excess of 5 feet in depth must have approved shoring in place at the time of inspection" Date: May 13, 2016 Contractor: Bartholomew Emanuel Client: L & Ys Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 6, 2016 | Permit id: 691798 | |||||
SCORE 89 Install 2 ton heatpump with duct work Date: May 10, 2016 Contractor: Tp Llc Client: L & Ys Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 15, 2016 | Permit id: 690905 | |||||
SCORE 100 Piping of installing 2 wc,2 lavs,2 bath tubs,1 kitchen sink,washing machine and water heater (sfd)the installation will comply with the philadelphia plumbing code 2004 Date: April 27, 2016 Contractor: Grand General Contractor Client: L & Ys Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 15, 2016 | Permit id: 687533 | |||||
SCORE 97 Rewire sfd as per 2008 nec and install 200amp service per 2008 nec (fishing)(sfd)south district Date: May 9, 2016 Contractor: Anthony Franklin Client: L & Ys Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: December 22, 2016 | Permit id: 690357 |