Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 99 Build new 2nd unit - 448 s. F. Applicant: Diaz Raul | Permit status: Finaled | Completion date: March 10, 2008 | Permit id: 0705250019 | |||||
SCORE 99 Electrical for 2nd unit Date: August 10, 2007 Contractor: L F Country Construction Applicant: Diaz Raul | Permit status: Finaled | Completion date: March 10, 2008 | Permit id: 0708100035 | |||||
SCORE 99 Install new wall heater Date: August 10, 2007 Contractor: L F Country Construction Applicant: Diaz Raul | Permit status: Finaled | Completion date: March 10, 2008 | Permit id: 0708100017 | |||||
SCORE 99 Plumbing for new 2nd unit Date: August 10, 2007 Contractor: L F Country Construction Applicant: Diaz Raul | Permit status: Finaled | Completion date: March 10, 2008 | Permit id: 0708100014 | |||||
SCORE 99 Install water line for 2nd unit. Date: January 28, 2008 Contractor: L F Country Construction Applicant: Diaz Raul | Permit status: Finaled | Completion date: January 29, 2008 | Permit id: 0801280024 | |||||
SCORE 99 Connect new 2nd unit to public sewer Date: August 10, 2007 Contractor: L F Country Construction Applicant: Diaz Raul | Permit status: Finaled | Completion date: January 28, 2008 | Permit id: 0708100005 |