Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Plumbing permit Date: October 20, 2008 Permit status: Completed | Permit id: 183364 | |||||
Fast form building permit Date: April 30, 2009 Permit status: Completed | Permit id: 213418 | |||||
Zoning/use permit Date: July 22, 2008 Permit status: Completed | Permit id: 164369 | |||||
New construction permit Date: September 16, 2008 Permit status: Completed | Permit id: 166275 | |||||
Electrical permit Date: February 23, 2009 Permit status: Expired | Permit id: 198496 | |||||
New construction permit Date: May 5, 2009 Permit status: Completed | Permit id: 174593 | |||||
Zoning/use permit Date: July 22, 2008 Permit status: Completed | Permit id: 164357 | |||||
Plumbing permit Date: October 20, 2008 Permit status: Completed | Permit id: 183376 | |||||
Fast form building permit Date: April 30, 2009 Permit status: Completed | Permit id: 213412 | |||||
Electrical permit Date: February 23, 2009 Permit status: Expired | Permit id: 198515 | |||||
Electrical permit Date: February 23, 2009 Client: Sharp James E & Sharp Leaann | Permit status: Expired | Permit id: 198496 | |||||
New construction permit Date: September 16, 2008 Client: Sharp James E & Sharp Leaann | Permit status: Completed | Permit id: 166275 | |||||
Fast form building permit Date: April 30, 2009 Client: Sharp James E & Sharp Leaann | Permit status: Completed | Permit id: 213418 | |||||
Plumbing permit Date: October 20, 2008 Client: Sharp James E & Sharp Leaann | Permit status: Completed | Permit id: 183364 | |||||
Zoning use permit Date: July 22, 2008 Client: Sharp James E & Sharp Leaann | Permit status: Completed | Permit id: 164369 | |||||
SCORE 89 Fast form building permit Date: April 30, 2009 Contractor: Talamge Stewart Permit status: Completed | Completion date: May 4, 2009 | Permit id: 213418 | |||||
Construct 1 semi detached sf house with related site improvements as shown on the approved plans. Date: September 16, 2008 Permit type: New construction permit | Permit status: Completed | Completion date: May 4, 2009 | Permit id: 166275 | |||||
SCORE 100 Install new plumbing system Date: October 20, 2008 Contractor: Joseph Rosati Permit type: Plumbing permit | Permit status: Completed | Completion date: February 20, 2009 | Permit id: 183364 | |||||
SCORE 86 200a service-120 240v single phase with circuit panel. Receptacles, gfi receptacles, single pole switches,4-3ways,1-4way switch,18 recessed lights,23 surface mounted lights,4 bathroom exhaust fans,2 heaters,2 a c condensor,6 -110v smoke carbon detectors with battery backup.. In accordance with 2005 nec Date: February 23, 2009 Contractor: Multiphase Technologies Permit type: Electrical permit | Permit status: Expired | Completion date: February 23, 2009 | Permit id: 198496 | |||||
Lots 1 and2. Semi detached sfd each with interior parking garage. Lot 3. Existing detached sfd hose to remain. Date: July 22, 2008 Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 22, 2008 | Permit id: 164369 | |||||
Electrical permit Date: February 23, 2009 Client: Sharp James E & Sharp Leaann | Permit status: Expired | Permit id: 198515 | |||||
Plumbing permit Date: October 20, 2008 Client: Sharp James E & Sharp Leaann | Permit status: Completed | Permit id: 183376 | |||||
Zoning use permit Date: July 22, 2008 Client: Sharp James E & Sharp Leaann | Permit status: Completed | Permit id: 164357 | |||||
New construction permit Date: May 5, 2009 Client: Sharp James E & Sharp Leaann | Permit status: Completed | Permit id: 174593 | |||||
Fast form building permit Date: April 30, 2009 Client: Sharp James E & Sharp Leaann | Permit status: Completed | Permit id: 213412 | |||||
Lots 1 and2. Semi detached sfd each with interior parking garage. Lot 3. Existing detached sfd hose to remain. Date: July 22, 2008 Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 22, 2008 | Permit id: 164357 | |||||
Construct (1) semi detached house with related site improvements. Plans are shared with tandem application #166275. All work shall comply with the approved plans. Date: May 5, 2009 Permit type: New construction permit | Permit status: Completed | Completion date: May 5, 2009 | Permit id: 174593 | |||||
SCORE 100 Install new plumbing system Date: October 20, 2008 Contractor: Joseph Rosati Permit type: Plumbing permit | Permit status: Completed | Completion date: May 4, 2009 | Permit id: 183376 | |||||
SCORE 89 Fast form building permit Date: April 30, 2009 Contractor: Talamge Stewart Permit status: Completed | Completion date: May 4, 2009 | Permit id: 213412 | |||||
SCORE 86 200a service-120 240v single phase with circuit panel. Receptacles, gfi receptacles, single pole switches,4-3ways,1-4way switch,18 recessed lights,23 surface mounted lights,4 bathroom exhaust fans,2 heaters,2 a c condensor,6 -110v smoke carbon detectors w battery backup.. In accordance with 2005 nec Date: February 23, 2009 Contractor: Multiphase Technologies Permit type: Electrical permit | Permit status: Expired | Completion date: February 23, 2009 | Permit id: 198515 |