Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 59 Re-stucco 3200sf canopy Applicant: Hellman Betzalel | Permit status: Finaled | Completion date: September 25, 2013 | Permit id: 1209280007 | |||||
SCORE 100 T. I. Of existing building for 7-eleven Applicant: Campagna Chris | Permit status: Finaled | Completion date: September 25, 2013 | Permit id: 1210040070 | |||||
SCORE 59 Restripe lot & accessible site improvements. Construct a 19 x 19 concrete curb for transformer pad. Applicant: Bryan Hellman | Permit status: Finaled | Completion date: September 25, 2013 | Permit id: 1211270022 | |||||
SCORE 95 Install (1) single face wall sign 2x22 (1) single face wall sign 2x1310". Reface double face pole sign 8x8 Applicant: Roy Courtney | Permit status: Finaled | Completion date: September 25, 2013 | Permit id: 1212110015 | |||||
SCORE 100 Ti for 7-eleven. Install 2 1 amp panels & 2 225 amp panels Date: June 24, 2013 Contractor: W C C S Inc Applicant: Campagna Chris | Permit status: Finaled | Completion date: September 25, 2013 | Permit id: 1210040065 | |||||
SCORE 95 Install new 12 amp panel electrical service Date: May 21, 2013 Contractor: Always On Applicant: Erel Studnik | Permit status: Finaled | Completion date: September 25, 2013 | Permit id: 1305130047 | |||||
SCORE 100 Ti for 7-eleven Date: June 24, 2013 Contractor: W C C S Inc Applicant: Campagna Chris | Permit status: Finaled | Completion date: September 25, 2013 | Permit id: 1210040034 | |||||
SCORE 93 Install new main water line w/regulator & backflow valve Date: March 22, 2013 Contractor: L K Plumbing And Heating Inc Applicant: Jim Forgey | Permit status: Finaled | Completion date: April 23, 2013 | Permit id: 1303220008 | |||||
SCORE 100 Plumbing for ti for 7-eleven Date: July 18, 2013 Contractor: W C C S Inc Applicant: Forgey Jim | Permit status: Finaled | Completion date: September 25, 2013 | Permit id: 1307180011 | |||||
SCORE 86 Plumbing for t. I on coin laundry Date: July 15, 2015 Contractor: Rafael 26 Construction Inc Engineer: Kevin Friedman | Applicant: Tonchev Mariyan | Permit status: Finaled | Completion date: October 8, 2015 | Expiration date: July 14, 2016 | Permit id: 1507150005 | |||||
SCORE 86 Pl for t. I. New water heater, upsize water & gas lines Date: May 6, 2015 Contractor: Rafael 26 Construction Inc Engineer: Kevin Friedman | Applicant: Tonchev Murray | Permit status: Finaled | Completion date: October 8, 2015 | Expiration date: May 5, 2016 | Permit id: 1504150019 | |||||
SCORE 97 Replace 4 evaporative coolers,and install 24 appliance vents Date: May 26, 2015 Contractor: Air Supply A C And Heating Applicant: Rosetti, Victor | Permit status: Finaled | Completion date: October 8, 2015 | Expiration date: May 25, 2016 | Permit id: 1505260041 | |||||
SCORE 86 T. I for coin laundry consisting of replacement of washer & dryers, new walls over dryers, repair t-bar ceiling and replace water heater. Engineer: Kevin Friedman | Applicant: Tonchev Murray | Permit status: Finaled | Completion date: October 8, 2015 | Expiration date: May 5, 2016 | Permit id: 1503250022 | |||||
SCORE 86 Electrical for t. I on coin laundry Date: July 15, 2015 Contractor: Rafael 26 Construction Inc Engineer: Kevin Friedman | Applicant: Tonchev Mariyan | Permit status: Finaled | Completion date: October 8, 2015 | Expiration date: July 14, 2016 | Permit id: 1507150012 | |||||
SCORE 61 Replace (2) existing a c units. (attachment shall be completed by an architect or engineer prior to permit final sign off) Date: April 17, 2013 Contractor: Aa Quick Cooling Applicant: Elbaz Yizhaq | Permit status: Finaled | Completion date: September 25, 2013 | Expiration date: April 17, 2014 | Permit id: 1304170014 | |||||
SCORE 59 Re-stucco 3200sf canopy Applicant: Hellman Betzalel | Permit status: Finaled | Completion date: September 25, 2013 | Expiration date: September 28, 2013 | Permit id: 1209280007 | |||||
SCORE 91 T. I. Of existing building for 7-eleven Engineer: Alexandre Sims | Applicant: Campagna Chris | Permit status: Finaled | Completion date: September 25, 2013 | Expiration date: June 24, 2014 | Permit id: 1210040070 | |||||
SCORE 59 Restripe lot & accessible site improvements. Construct a 19 x 19 concrete curb for transformer pad. Applicant: Bryan Hellman | Permit status: Finaled | Completion date: September 25, 2013 | Expiration date: December 12, 2013 | Permit id: 1211270022 | |||||
SCORE 91 Ti for 7-eleven. Install 2 1 amp panels & 2 225 amp panels Date: June 24, 2013 Contractor: W C C S, Inc Applicant: Campagna Chris | Permit status: Finaled | Completion date: September 25, 2013 | Expiration date: June 24, 2014 | Permit id: 1210040065 | |||||
SCORE 91 Ti for 7-eleven Date: June 24, 2013 Contractor: W C C S, Inc Applicant: Campagna Chris | Permit status: Finaled | Completion date: September 25, 2013 | Expiration date: June 24, 2014 | Permit id: 1210040034 | |||||
SCORE 93 Replace 4 evaporative coolers,and install 24 appliance vents Date: May 26, 2015 Contractor: Air Supply A, C And Heating Applicant: Rosetti, Victor | Permit status: Finaled | Completion date: October 8, 2015 | Expiration date: May 25, 2016 | Permit id: 1505260041 | |||||
SCORE 56 Install new main water line w regulator & backflow valve Date: March 22, 2013 Contractor: L K Plumbing And Heating, Inc Engineer: Alexandre Sims | Applicant: Jim Forgey | Permit status: Finaled | Completion date: April 23, 2013 | Expiration date: March 22, 2014 | Permit id: 1303220008 | |||||
SCORE 91 Plumbing for ti for 7-eleven Date: July 18, 2013 Contractor: W C C S, Inc Engineer: Alexandre Sims | Applicant: Forgey Jim | Permit status: Finaled | Completion date: September 25, 2013 | Expiration date: July 18, 2014 | Permit id: 1307180011 | |||||
SCORE 79 Install (1) 120v 20a circuit recepticle in (e) 7-eleven store. Date: February 22, 2016 Contractor: Rhino Electric Costa Mesa Applicant: Adams James | Permit status: Finaled | Completion date: March 1, 2016 | Expiration date: February 21, 2017 | Permit id: 1602220042 |