Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Seattle center and seattle opera are redeveloping the mercer arena to be the new operational home of the seattle opera. This application and work is to engage in demolition of existing mercer arena, as well as shoring and excavation in preparation for construction of the building to be reviewed under construction permit application, dci project number 6551526. Applicant: Battazzo, Angie | Permit type: Demolition | Permit status: Initial information colle | Current use: Institutional | Permit id: 6558612 | |||||
Seattle center and seattle opera are redeveloping the mercer arena to be the new operational home of the seattle opera. Work will include demolition of the mercer arena, new construction of a four-story, 103,0 sf new building for administrative offices, costume shop, studio, and rehearsal space. Applicant: Battazzo, Angie | Permit type: Construction | Permit status: Initial information colle | Current use: Institutional | Permit id: 6551526 | |||||
Land use application to adjust the boundary between two parcels of land. Proposed parcel sizes are: a) 349,136 sq. Ft.; b) 63,204 sq. Ft. Existing building (seattle center arena) to be demolished. Date: September 20, 2016 Applicant: Battazzo, Angie | Permit type: Lot boundary adjustment plat | Permit status: Application accepted | Current use: Institutional | Permit id: 3025581 | |||||
Land use application to allow a four-story, 103,0 sf new building containing administrative offices, costume shop, studio, and rehearsal space. Existing building (mercer arena) to be demolished. Addendum to environmental impact statement (eis) prepared by seattle center. Value: $1 Applicant: Battazzo, Angie | Permit type: Other land use actions | Permit status: Initial information colle | Current use: Institutional | Permit id: 3025131 | |||||
Demolition of an existing commercial building, (mercer arena) per plan. Date: November 10, 2016 Value: $900,000 Applicant: Battazzo, Angie | Permit type: Demolition | Permit status: Application accepted | Current use: Institutional | Permit id: 6558612 | |||||
Establish use as office, storage and entertainment and construct new commercial building (seattle opera at the center), occupy per plan. Mechanical included. Date: December 8, 2016 Value: $13,039,808 Applicant: Battazzo, Angie | Permit type: Construction | Permit status: Application accepted | Current use: Institutional | Permit id: 6551526 | |||||
Land use application to allow a four-story, 103,0 sf new building containing administrative offices, costume shop, studio, and rehearsal space. Existing building (mercer arena) to be demolished. Addendum to environmental impact statement (eis) prepared by seattle center. Value: $1 Applicant: Battazzo, Angie | Permit type: Other land use actions | Permit status: Initial information colle | Current use: Institutional | Permit id: 3025131 | |||||
SCORE 100 Temporary dewatering associated with 6551526. Discharge to combined main in 4th ave n. Associated bldg permit 6551526. Date: May 9, 2017 Contractor: Lease Crutcher Lewis Wa Llc Applicant: Lease Crutcher Lewis Wa Llc | Permit type: Side sewer | Permit status: Permit issued | Expiration date: November 9, 2018 | Current use: Institutional | Permit id: 6596132 | |||||
SCORE 99 New drain to combiend; new san ot ex. Associated building permit #6551526. Date: August 28, 2017 Contractor: Titan Earthwork Llc Applicant: Titan Earthwork Llc | Permit type: Side sewer | Permit status: Permit issued | Expiration date: February 28, 2019 | Current use: Single family / duplex | Permit id: 6615679 | |||||
SCORE 95 Electrical installation of power, lighting, switchgear, fire alarm, and low voltage systems for new seattle opera building. Job number: 216711. Permit type: Electrical | Permit status: Permit issued | Expiration date: August 25, 2018 | Current use: Commercial | Permit id: 6592300 | |||||
SCORE 95 Provide and install 2 amp 4 volt sup-panel to re-feed exisiting security gate, readerboard, etc. Scope includes re-work of exisiting network cable and raceway and circuit to security. Job: 216711. 3 20 17 paf change to plan review per inspector Permit type: Electrical | Permit status: Permit issued | Expiration date: February 13, 2018 | Current use: Commercial | Permit id: 6580931 | |||||
SCORE 95 Install fire alarm system at seattle opera at the center. Joint venture between simplexgrinnell and prime electric. Date: October 11, 2017 Contractor: Simplexgrinnell Lp Permit type: Electrical | Permit status: Permit issued | Expiration date: October 11, 2018 | Current use: Commercial | Permit id: 6607250 | |||||
Land use application to adjust the boundary between two parcels of land. Proposed parcel sizes are: a) 349,136 sq. Ft.; b) 63,204 sq. Ft. Existing building (seattle center arena) to be demolished. Date: January 27, 2017 Applicant: Johnsen, Ken | Permit type: Lot boundary adjustment plat | Permit status: Permit closed | Current use: Institutional | Permit id: 3025581 | |||||
SCORE 95 [temporary power. ] job number: 216711 Date: June 7, 2017 Contractor: Prime Electric Incorporated Permit type: Electrical | Permit status: Permit issued | Expiration date: June 7, 2018 | Current use: Commercial | Permit id: 6601425 | |||||
Demolition of an existing commercial building, (mercer arena) per plan. Date: February 15, 2017 Applicant: Chaney, Katy | Permit type: Demolition | Permit status: Permit closed | Completion date: June 30, 2017 | Expiration date: August 15, 2018 | Current use: Institutional | Permit id: 6558612 | |||||
Establish use as office, storage and entertainment and construct new commercial building (seattle opera at the center), occupy per plan. Mechanical included. Date: June 17, 2017 Value: $13,039,808 Applicant: Hegedus, Kerry | Permit type: Construction | Permit status: Permit issued | Expiration date: December 17, 2018 | Current use: Institutional | Permit id: 6551526 | |||||
Land use application to adjust the boundary between two parcels of land. Proposed parcel sizes are: a) 349197 sq. Ft.; b) 63,144 sq. Ft. Existing building on parcel a (mccaw hall) to remain. Date: September 6, 2017 Applicant: Hegedus, Kerry | Permit type: Lot boundary adjustment plat | Permit status: Permit closed | Current use: Commercial | Permit id: 3028485 | |||||
SCORE 95 Days get started for branch circuits only. Plan review done under permit #6592300 Date: July 17, 2017 Contractor: Prime Electric Incorporated Permit type: Electrical | Permit status: Permit issued | Expiration date: August 17, 2017 | Current use: Commercial | Permit id: 6608183 | |||||
Land use application to allow a four-story, 103,0 sf new building containing administrative offices, costume shop, studio, and rehearsal space. Existing building (mercer arena) to be demolished. Addendum to environmental impact statement (eis) prepared by seattle center. Value: $1 Applicant: Johnsen, Ken | Permit type: Other land use actions | Permit status: Initial information colle | Current use: Institutional | Permit id: 3025131 |