Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Mechanical permit Date: June 10, 2015 Client: Gutknecht Andrew Leiby Benjamin | Permit status: Completed | Permit id: 616232 | |||||
Electrical permit Date: June 10, 2015 Client: Gutknecht Andrew Leiby Benjamin | Permit status: Completed | Permit id: 615067 | |||||
Zoning permit Date: September 10, 2014 Client: Gutknecht Andrew Leiby Benjamin | Permit status: Completed | Permit id: 560485 | |||||
Demolition permit Date: May 7, 2015 Client: Gutknecht Andrew Leiby Benjamin | Permit status: Completed | Permit id: 605161 | |||||
Alteration permit Date: May 12, 2015 Client: Gutknecht Andrew Leiby Benjamin | Permit status: Completed | Permit id: 604434 | |||||
Demolition permit Date: May 7, 2015 Client: Gutknecht Andrew Leiby Benjamin | Permit status: Completed | Permit id: 605161 | |||||
Alteration permit Date: May 12, 2015 Client: Gutknecht Andrew Leiby Benjamin | Permit status: Completed | Permit id: 604434 | |||||
Zoning permit Date: September 10, 2014 Client: Gutknecht Andrew Leiby Benjamin | Permit status: Completed | Permit id: 560485 | |||||
Electrical permit Date: June 10, 2015 Client: Gutknecht Andrew Leiby Benjamin | Permit status: Completed | Permit id: 615067 | |||||
Mechanical permit Date: June 10, 2015 Client: Gutknecht Andrew Leiby Benjamin | Permit status: Completed | Permit id: 616232 | |||||
SCORE 99 Install one 3. 5 ton unit high velocity central a c system to cool the 2nd and 3rd floors and part of the 1st. Date: June 10, 2015 Contractor: Sila Heating And Ac Inc Client: Gutknecht Andrew Leiby Benjamin | Permit type: Mechanical permit | Permit status: Completed | Completion date: September 28, 2015 | Permit id: 616232 | |||||
For the relocation of lot lines to create (1) lot from (2) lots, and create breech wall between the two buildings Date: September 10, 2014 Client: Gutknecht Andrew Leiby Benjamin | Permit type: Zoning permit | Permit status: Completed | Completion date: September 25, 2015 | Permit id: 560485 | |||||
SCORE 65 Non structure demo 1st, 2nd and 3rd floor interior walls. Date: May 7, 2015 Contractor: Rittenhouse Builders Client: Gutknecht Andrew Leiby Benjamin | Permit type: Demolition permit | Permit status: Completed | Completion date: June 16, 2015 | Permit id: 605161 | |||||
SCORE 100 Partial re-wire, 20- switches, 25- receptacles, fixtures, 200a service, arc fault breakers.... In accordance with 2008 nec for a one family building Date: June 10, 2015 Contractor: Mbs Electric Client: Gutknecht Andrew Leiby Benjamin | Permit type: Electrical permit | Permit status: Completed | Completion date: November 4, 2015 | Permit id: 615067 | |||||
SCORE 65 Interior alteration to an existing detached single family dwelling per submitted plans. Separate permits required for electric; plumbing and mechanical. Date: May 12, 2015 Contractor: Rittenhouse Builders Client: Gutknecht Andrew Leiby Benjamin | Permit type: Alteration permit | Permit status: Completed | Completion date: October 14, 2015 | Permit id: 604434 |