Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Ti for offices Date: August 30, 2000 Value: $20,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: September 6, 2001 | Permit id: 0008300045 | |||||
SCORE 56 New industrial/office bldg 54 sq ft Applicant: Arcitex & Associates | Permit status: Finaled | Completion date: September 6, 2001 | Permit id: 9808280053 | |||||
SCORE 90 Elec for new com bldg 54 sq ft Date: July 6, 2001 Contractor: Rjs Electric Applicant: Rjs Electric | Permit status: Finaled | Completion date: September 6, 2001 | Permit id: 0006010029 | |||||
SCORE 90 Temporary power pole for new industrical/office bldg Date: December 11, 2000 Contractor: Rjs Electric Applicant: Rjs Electric Inc | Permit status: Finaled | Completion date: December 14, 2000 | Permit id: 0012110025 | |||||
SCORE 90 Elec for ti Date: July 6, 2001 Contractor: Rjs Electric Applicant: Rjs Electric | Permit status: Finaled | Completion date: September 6, 2001 | Permit id: 0107060008 | |||||
Elec for warehouse unit c Date: March 10, 2003 Applicant: Same As Owner | Permit status: Permisud | Permit id: 0303100037 | |||||
SCORE 99 Mech for new office bldg Date: September 4, 2001 Contractor: Summer Systems Inc Applicant: Summer Systems | Permit status: Finaled | Completion date: September 6, 2001 | Permit id: 0109040004 | |||||
SCORE 96 Plumbing for comm bldg Date: March 14, 2001 Contractor: Stevenson Plumbing And Fire Protect Applicant: Stevenson Plumbing And Fire Protect | Permit status: Finaled | Completion date: September 6, 2004 | Permit id: 0103140027 | |||||
SCORE 96 Gasline for fau for ti for offices Date: September 5, 2001 Contractor: Stevenson Plumbing And Fire Protect Applicant: Stevenson Plumb & Fire Protection | Permit status: Finaled | Completion date: September 6, 2001 | Permit id: 0109050015 |