Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Mechanical permit Date: February 9, 2007 Client: Deep Sea Gp Llc | Permit status: Expired | Permit id: 55681 | |||||
Electrical permit Date: October 11, 2007 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 99184 | |||||
Administrative permit Date: December 30, 2009 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 249491 | |||||
Use permit Date: May 22, 2007 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 77745 | |||||
Suppression permit Date: January 30, 2008 Client: Deep Sea Gp Llc | Permit status: Expired | Permit id: 107404 | |||||
Electrical permit Date: March 11, 2009 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 204633 | |||||
Alteration permit Date: July 10, 2007 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 81261 | |||||
Alteration permit Date: October 1, 2009 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 232754 | |||||
Zoning/use permit Date: January 20, 2012 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 378032 | |||||
Plumbing permit Date: February 18, 2010 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 262680 | |||||
Electrical permit Date: March 26, 2010 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 260223 | |||||
Electrical permit Date: November 16, 2012 Client: Deep Sea Gp Llc | Permit status: Expired | Permit id: 437500 | |||||
Alteration permit Date: November 20, 2012 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 431686 | |||||
Suppression permit Date: June 3, 2010 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 283011 | |||||
Mechanical permit Date: March 24, 2010 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 262665 | |||||
Plumbing permit Date: August 30, 2007 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 97069 | |||||
Administrative permit Date: January 15, 2008 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 124657 | |||||
Administrative permit Date: January 31, 2013 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 450928 | |||||
Sign permit Date: April 10, 2012 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 384325 | |||||
Use permit Date: February 20, 2009 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 201999 | |||||
Plumbing permit Date: November 26, 2012 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 437954 | |||||
Administrative permit Date: June 14, 2010 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 283094 | |||||
Alteration permit Date: July 10, 2007 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 81261 | |||||
Electrical permit Date: September 7, 2007 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 101051 | |||||
Zoning use permit Date: January 20, 2012 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 378032 | |||||
Electrical permit Date: March 11, 2009 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 204633 | |||||
Suppression permit Date: January 30, 2008 Client: Deep Sea Gp Llc | Permit status: Expired | Permit id: 107404 | |||||
Mechanical permit Date: March 24, 2010 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 262665 | |||||
Sign permit Date: April 10, 2012 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 384325 | |||||
Mechanical permit Date: February 9, 2007 Client: Deep Sea Gp Llc | Permit status: Expired | Permit id: 55676 | |||||
Use permit Date: May 22, 2007 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 77745 | |||||
Suppression permit Date: June 3, 2010 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 283011 | |||||
Administrative permit Date: January 15, 2008 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 124657 | |||||
Administrative permit Date: January 31, 2013 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 450928 | |||||
Use permit Date: February 20, 2009 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 201999 | |||||
Alteration permit Date: February 27, 2009 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 197077 | |||||
Electrical permit Date: November 16, 2012 Client: Deep Sea Gp Llc | Permit status: Expired | Permit id: 437500 | |||||
Administrative permit Date: December 30, 2009 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 249491 | |||||
Administrative permit Date: June 14, 2010 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 283094 | |||||
Plumbing permit Date: February 18, 2010 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 262680 | |||||
Alteration permit Date: November 20, 2012 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 431686 | |||||
Plumbing permit Date: August 30, 2007 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 97069 | |||||
Plumbing permit Date: November 26, 2012 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 437954 | |||||
Electrical permit Date: March 26, 2010 Client: Deep Sea Gp Llc | Permit status: Completed | Permit id: 260223 | |||||
SCORE 100 Installation of 1 - amp 220volt dedicated circuit to feed the existing air curtain (east district) Date: May 8, 2007 Contractor: Northstar Electrical Services Client: Eep Sea Gp Llc | Permit type: Electrical permit | Permit status: Expired | Completion date: May 8, 2007 | Permit id: 74567 | |||||
SCORE 100 Rewire lgt sw in patient care areas, install new recpt for dental chairs, new circuits for xray equipment & additional recpt to match new layout. Installation to comply with article 517. 13 of the 2008 nec. Date: November 16, 2012 Contractor: Robert O Brien Client: Eep Sea Gp Llc | Permit type: Electrical permit | Permit status: Expired | Completion date: April 20, 2013 | Permit id: 437500 | |||||
SCORE 100 Install 7-dental chair & 9-sinks (dental labs) Date: November 26, 2012 Contractor: Gregory F Rossi Plumbing And Htg Client: Eep Sea Gp Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 6, 2013 | Permit id: 437954 | |||||
SCORE 89 Install fire pump only Date: January 30, 2008 Contractor: Stephsin Fire Suppression Inc Client: Eep Sea Gp Llc | Permit type: Suppression permit | Permit status: Expired | Completion date: September 8, 2008 | Permit id: 107404 | |||||
SCORE 93 Service, feeders, power, light etc as per plans. No fire alarm or tele data. Date: September 7, 2007 Contractor: Donald Craig Electr Serv Client: Eep Sea Gp Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: February 21, 2008 | Permit id: 101051 | |||||
SCORE 100 Install three 3-ton heat pumps with acc. Ductwork (5th, 6th, & 7th floors) Date: October 3, 2007 Contractor: Jay Zawierucha Client: Eep Sea Gp Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 5, 2007 | Permit id: 106947 | |||||
Interior alterations at 9th floor only as per plans. Date: October 1, 2009 Client: Eep Sea Gp Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: June 28, 2010 | Permit id: 232754 | |||||
SCORE 100 Relocate 52 sprinkler heads (8th & 9th) Date: June 3, 2010 Contractor: Advance Management Corp Client: Eep Sea Gp Llc | Permit type: Suppression permit | Permit status: Completed | Completion date: June 28, 2010 | Permit id: 283011 | |||||
SCORE 100 Amending bldg permit#262665 to install stair pressurization fans at the 8th and 9th floors. Contractor to provide balance report to inspector. Install 3 heat pumps Date: June 14, 2010 Contractor: Fred Dinardo Jr Client: Eep Sea Gp Llc | Permit type: Administrative permit | Permit status: Completed | Completion date: June 28, 2010 | Permit id: 283094 | |||||
SCORE 100 Install 100a sub panel to 9th floor, all other electrical panels existing - install wiring as; per 2005 nec, all light fixtures supplied by owner, fire alarm by others (east dist) Date: March 26, 2010 Contractor: Baldwin Electrical Const Llc Client: Eep Sea Gp Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: August 2, 2010 | Permit id: 260223 | |||||
SCORE 88 Installation of (2) flat wall signs and an awning with no text Date: April 10, 2012 Contractor: Gran Client: Eep Sea Gp Llc | Permit type: Sign permit | Permit status: Completed | Completion date: May 8, 2012 | Permit id: 384325 | |||||
1 day temp. C. O. For 7th floor for 3 dental operatories. Date: January 31, 2013 Client: Eep Sea Gp Llc | Permit type: Administrative permit | Permit status: Completed | Completion date: February 4, 2013 | Permit id: 450928 | |||||
Revised layout to 9th floor amended to permit # 232754. Date: December 30, 2009 Client: Eep Sea Gp Llc | Permit type: Administrative permit | Permit status: Completed | Completion date: June 14, 2010 | Permit id: 249491 | |||||
Int alt for tenant fit out per attached plans Date: July 10, 2007 Client: Eep Sea Gp Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: November 30, 2007 | Permit id: 81261 | |||||
SCORE 100 Install ductwork (12 cfm) for 2 heaters covered under mp#55676- 2nd floor Date: February 9, 2007 Contractor: Jay Zawierucha Client: Eep Sea Gp Llc | Permit type: Mechanical permit | Permit status: Expired | Completion date: September 12, 2007 | Permit id: 55681 | |||||
Interior alterations to partial 7th floor area for existing dental tenant space to include general demo and renovations, upgrades to finishes, casework, millwork, new interior doors and interior office partitions, dental office furnishings and equipment and associated plumbing fixtures. No change in use or occupancy classification. Co attached as a matter of record. Building sprinklered. Additional permits req : electrical, plumbing, hvac , sprinklers if modified. Date: November 20, 2012 Client: Eep Sea Gp Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: March 6, 2013 | Permit id: 431686 | |||||
SCORE 99 Install new fire alarm system. (east dist) Date: October 11, 2007 Contractor: Hi Lite Electrical Contractors Client: Eep Sea Gp Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: February 11, 2008 | Permit id: 99184 | |||||
Renovations to the 8th fl. Of an existing 8 story (above grade) building with 9th fl. Pent house and basement. Proposed renovation is for the fit-out of medical offices and or exam rooms. Date: August 26, 2009 Client: Eep Sea Gp Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: November 23, 2010 | Permit id: 223281 | |||||
Interior alterations as per plans for 1st floor fit-out for mental health offices w retail sales of books. Date: February 27, 2009 Client: Eep Sea Gp Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: March 12, 2009 | Permit id: 197077 | |||||
1st floor use to offices retail Date: February 20, 2009 Client: Eep Sea Gp Llc | Permit type: Use permit | Permit status: Completed | Completion date: February 20, 2009 | Permit id: 201999 | |||||
SCORE 93 Relocate (20) receptacles (wall demod and relocated), as per 2005 nec (east dist) Date: March 11, 2009 Contractor: Donald Craig Electr Serv Client: Eep Sea Gp Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: January 12, 2010 | Permit id: 204633 | |||||
SCORE 100 Installing ductwork and registers for office areas on the 8th and 9th floors of a health care center as per plans. Date: March 24, 2010 Contractor: Fred Dinardo Jr Client: Eep Sea Gp Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 28, 2010 | Permit id: 262665 | |||||
SCORE 100 Install two gibson gas heaters (3 ton) with a c - 2nd floor Date: February 9, 2007 Contractor: Jay Zawierucha Client: Eep Sea Gp Llc | Permit type: Mechanical permit | Permit status: Expired | Completion date: September 12, 2007 | Permit id: 55676 | |||||
SCORE 72 Use: medical healthcare and related community services, including pharmacy services,no signs,no change in height or area. Date: May 22, 2007 Contractor: Henry Clausen Client: Eep Sea Gp Llc | Permit type: Use permit | Permit status: Completed | Completion date: May 24, 2007 | Permit id: 77745 | |||||
Installation of awnings and wall signs. Date: January 20, 2012 Client: Eep Sea Gp Llc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 30, 2012 | Permit id: 378032 | |||||
SCORE 100 Installing 8 exam room sinks, 1 kitchen sink, 3 water closet, 3 lavs, 1 mop receptor and 1 hot water heater Date: February 18, 2010 Contractor: John J Mulholland Client: Eep Sea Gp Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 21, 2010 | Permit id: 262680 | |||||
Tenant fit-out of 5th, 6th & 7th flrs. Date: September 28, 2007 Client: Eep Sea Gp Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: November 30, 2007 | Permit id: 92014 | |||||
SCORE 98 Replacement of drainage, waste and vent pipe system from basement to roof. Install new fxts. (6) 2 piece (12, wc, 12 lavs.) 6 mp recepts, 12 fl dr, sinks. Date: August 30, 2007 Contractor: Russell Brown Client: Eep Sea Gp Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 25, 2008 | Permit id: 97069 |