Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Pool/spa 512 sq ft laco std 26072 Date: January 17, 2006 Value: $19,500 Engineer: Miles Engineering | Applicant: Same As Owner | Permit status: Finaled | Completion date: February 8, 2007 | Expiration date: July 16, 2006 | Permit id: 601170005 | |||||
SCORE 99 Sewer for new sfd Date: March 28, 2003 Contractor: Tri Valley Mechanical Engineer: Bbg Architects | Applicant: Tri Valley Mechanical | Permit status: Finaled | Completion date: May 30, 2003 | Expiration date: September 24, 2003 | Permit id: 301150015 | |||||
Removing dirt from slope in back yard to make more useable pad area 6 cu yds Date: September 21, 2006 Applicant: Same As Owner | Permit status: Finaled | Completion date: August 5, 2011 | Expiration date: March 20, 2007 | Permit id: 607180001 | |||||
SCORE 68 Electrical for attached 3 sq. Ft. Patio cover Date: June 20, 2013 Contractor: Ekt Construction Applicant: Erick Twitchell | Permit status: Permisud | Expiration date: June 20, 2014 | Permit id: 1306200042 | |||||
SCORE 95 Electrical for new roof mount pv system 6. 5kw, 25 panels Date: July 1, 2013 Contractor: Solarcity Corporation Applicant: Leighton | Permit status: Finaled | Completion date: September 27, 2013 | Expiration date: July 1, 2014 | Permit id: 1306190017 | |||||
Elec for future bbq Date: January 17, 2006 Applicant: Same As Owner | Permit status: Finaled | Completion date: February 9, 2007 | Expiration date: July 16, 2006 | Permit id: 601170019 | |||||
SCORE 68 6 outlets and 2 lighting fixtures Date: May 26, 2011 Contractor: E K T Construction Applicant: Twitchell Erik K | Permit status: Finaled | Completion date: August 5, 2011 | Expiration date: May 25, 2012 | Permit id: 1105260006 | |||||
SCORE 68 Attached 3 sq. Ft. Solid roofed patio cover Applicant: Erick Twitchell | Permit status: Finaled | Completion date: August 6, 2013 | Expiration date: June 20, 2014 | Permit id: 1306200066 | |||||
SCORE 95 New roof mount pv system 6. 5 kw, 25 panels, 425 sqft Applicant: Leighton | Permit status: Finaled | Completion date: September 27, 2013 | Expiration date: July 1, 2014 | Permit id: 1306190035 | |||||
SCORE 95 Electrical to replace (e) 2 amp panel with new - same location Date: September 23, 2013 Contractor: Solarcity Corporation Applicant: Leighton | Permit status: Finaled | Completion date: September 27, 2013 | Expiration date: September 23, 2014 | Permit id: 1309230030 | |||||
SCORE 82 Ret. Wall 6h x 218l Engineer: Miles Engineering | Applicant: Hurrikane Pools | Permit status: Finaled | Completion date: January 5, 2007 | Expiration date: January 12, 2007 | Permit id: 601170069 | |||||
SCORE 68 Add solid-roof, tile patio cover 3 sq ft Applicant: Twitchell Erik K | Permit status: Finaled | Completion date: August 5, 2011 | Expiration date: May 25, 2012 | Permit id: 1105030014 | |||||
Pool spa 512 sq ft laco std 26072 Date: January 17, 2006 Value: $19,500 Engineer: Miles Engineering | Applicant: Same As Owner | Permit status: Finaled | Completion date: February 8, 2007 | Expiration date: July 16, 2006 | Permit id: 601170005 | |||||
SCORE 98 New sfd/gar plan 3xbr 3435/906 sq ft 4 car garage option Engineer: Bbg Architects | Applicant: Greystone Homes | Permit status: Finaled | Completion date: May 30, 2003 | Expiration date: June 17, 2003 | Permit id: 207240009 |