Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 69 Electrical for larics lasdncc. New 2 amp panel, 1 sub panel, 1 battery charger, 1 3hp motor. Date: March 30, 2015 Contractor: Echo Pacific Communications Engineer: Mitchell J Architecture | Applicant: Thomas Peelen | Permit status: Finaled | Completion date: July 8, 2015 | Expiration date: March 29, 2016 | Permit id: 1503300019 | |||||
SCORE 79 Install new equipment site. 4 equipment cabinets, 6 antennas 3 microwave antennas, 22kw back up generator Engineer: Mitchell J Architecture | Applicant: Jimenez Aurora | Permit status: Finaled | Completion date: July 8, 2015 | Expiration date: March 18, 2016 | Permit id: 1502020122 | |||||
SCORE 69 Install new equipment site. 4 equipment cabinets, 6 antennas 3 microwave antennas, 22kw back up generator Engineer: Mitchell J Architecture | Applicant: Thomas Peelen | Permit status: Finaled | Completion date: July 8, 2015 | Expiration date: March 23, 2016 | Permit id: 1503240021 |