Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Sewer connection for new sfd Date: September 25, 2014 Contractor: Wilcox And Wilcox U S A Corp Engineer: N, A | Applicant: Wilcox And Wilcox | Permit status: Finaled | Completion date: January 22, 2015 | Expiration date: September 25, 2015 | Permit id: 1409230006 | |||||
SCORE 99 Elect for roof-mounted pv sys 1. 38 kw, 6 panels, 78. 79 sf Date: November 4, 2014 Contractor: Unpower Corporation Systems Engineer: Peter Todd | Applicant: Streamline Permits | Permit status: Finaled | Completion date: January 22, 2015 | Expiration date: November 4, 2015 | Permit id: 1411040026 | |||||
New sfd/gar/porch 2167/427/111 sq ft plan 1ar Date: September 5, 2014 Value: $420,000 Engineer: Kevin Crook Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: January 22, 2015 | Expiration date: September 5, 2015 | Permit id: 1407080001 | |||||
SCORE 99 Install roof-mounted pv sys 1. 38 kw, 6 panels, 78. 79 sq ft Engineer: Peter Todd | Applicant: Streamline Permits | Permit status: Finaled | Completion date: January 22, 2015 | Expiration date: November 4, 2015 | Permit id: 1411040048 | |||||
New sfd gar porch 2167 427 111 sq ft plan 1ar Date: September 5, 2014 Value: $420,000 Engineer: Kevin Crook Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: January 22, 2015 | Expiration date: September 5, 2015 | Permit id: 1407080001 |