Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 98 Plumbing for comm. Shell building and mezzanine bldg 3 Date: August 16, 2005 Contractor: Andersen Commercial Plumbing Engineer: Poliquin-Kellogg Design Group | Applicant: Bb&g Consulting Alisa | Permit status: Finaled | Completion date: July 25, 2006 | Expiration date: February 12, 2006 | Permit id: 508040010 | |||||
SCORE 98 On site sewer for future use Date: July 14, 2005 Contractor: Andersen Commercial Plumbing Applicant: Andersen Commercial Plumbing | Permit status: Finaled | Completion date: July 25, 2006 | Expiration date: January 10, 2006 | Permit id: 507140006 | |||||
SCORE 99 Fire sprinklers for new comm bldg 565 heads 39,404 sq ft Engineer: Poliquin-Kellogg Design Group | Applicant: Guardian Fire Protection Inc | Permit status: Finaled | Completion date: July 25, 2006 | Expiration date: June 11, 2007 | Permit id: 603230012 | |||||
SCORE 87 Plum for t. I. 1st and 2nd floors Date: May 18, 2007 Contractor: Jim Mendoza General Contracting Engineer: C2g | Applicant: Bb&g Consulting | Permit status: Finaled | Completion date: August 2, 2007 | Expiration date: November 14, 2007 | Permit id: 705170018 | |||||
SCORE 87 Mech for t. I. 1st and 2nd floors Date: May 18, 2007 Contractor: Jim Mendoza General Contracting Engineer: C2g | Applicant: Bb&g Consulting | Permit status: Finaled | Completion date: August 2, 2007 | Expiration date: November 14, 2007 | Permit id: 705180009 | |||||
SCORE 86 Mech for commercial shell building and mezzanine bldg 3 44,846 sq ft Date: January 4, 2006 Contractor: Gold Coast Air Conditioning Co Engineer: Poliquin-Kellogg Design Group | Applicant: Enns Kevin | Permit status: Finaled | Completion date: July 25, 2006 | Expiration date: July 3, 2006 | Permit id: 510200012 | |||||
SCORE 87 Elec for t. I. 1st and 2nd floors Date: May 18, 2007 Contractor: Jim Mendoza General Contracting Engineer: C2g | Applicant: Bb&g Consulting | Permit status: Finaled | Completion date: August 2, 2007 | Expiration date: November 14, 2007 | Permit id: 705170039 | |||||
SCORE 98 Electrical for comm. Shell building and mezzanine bldg 3 Date: August 25, 2005 Contractor: Southern Power Inc Engineer: Poliquin-Kellogg Design Group | Applicant: Southern Power Inc | Permit status: Finaled | Completion date: July 25, 2006 | Expiration date: February 21, 2006 | Permit id: 508040022 | |||||
SCORE 90 Installation of storage racks10,0 sq ft Engineer: Sce | Applicant: Raymond Handling Solution | Permit status: Finaled | Completion date: November 20, 2007 | Expiration date: May 7, 2008 | Permit id: 710190002 | |||||
SCORE 100 Commercial shell building and mezzanine bldg 3 44,846 sq ft Engineer: Poliquin-Kellogg Design Group | Applicant: Bb&g Consulting Alisa | Permit status: Finaled | Completion date: July 25, 2006 | Expiration date: July 31, 2006 | Permit id: 501100035 | |||||
SCORE 98 Sewer connection for new commercial shell bldg bldg 3 Date: September 1, 2005 Contractor: Andersen Commercial Plumbing Applicant: Andersen Commercial Plumbing | Permit status: Finaled | Completion date: July 25, 2006 | Expiration date: February 28, 2006 | Permit id: 508310003 | |||||
SCORE 87 Ti - add lunch rm & extend restroom (1st fl), add offices & restr00m (2nd fl) 2,5 sq ft Engineer: C2g | Applicant: Bb&g Consulting | Permit status: Finaled | Completion date: August 2, 2007 | Expiration date: May 11, 2008 | Permit id: 703260043 | |||||
SCORE 65 Installation of storage racks10,0 sq ft Engineer: Sce | Applicant: Raymond Handling Solution | Permit status: Finaled | Completion date: November 20, 2007 | Expiration date: May 7, 2008 | Permit id: 710190002 |