Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Ret wall 1-8. 5 x long Date: March 2, 2000 Value: $27,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: May 1, 2002 | Permit id: 0003010061 | |||||
Add deck 68 sq ft Date: October 25, 2001 Value: $2,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: May 1, 2002 | Permit id: 0110250008 | |||||
SCORE 97 Add elevator shaft to residence Applicant: Libolt Design & Remodel | Permit status: Finaled | Completion date: February 21, 2003 | Permit id: 0208090050 | |||||
New sfd/garage 3339/911 sq ft Date: July 28, 2000 Value: $340,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: May 1, 2002 | Permit id: 9911150022 | |||||
SCORE 100 Pool and spa 7 sq ft standard plan 26077 Applicant: Nautical Pools | Permit status: Finaled | Completion date: March 4, 2003 | Permit id: 0208300001 | |||||
Elec for new sfd Date: February 1, 2001 Applicant: Same As Owner | Permit status: Finaled | Completion date: May 1, 2002 | Permit id: 0101310009 | |||||
SCORE 100 Temp power pole for new construction Date: April 11, 2001 Contractor: Andy Gump Inc Applicant: Andy Gump Temporary Site Services | Permit status: Finaled | Completion date: April 13, 2001 | Permit id: 0104110028 | |||||
SCORE 100 Elec for bbq Date: August 30, 2002 Contractor: Nautical Designs Inc Applicant: Nautical Pools | Permit status: Finaled | Completion date: February 25, 2003 | Permit id: 0208300006 | |||||
SCORE 97 Electrical for new elevator room Date: January 28, 2003 Contractor: Libolt Design And Remodel Applicant: Libolt Design & Remodel | Permit status: Finaled | Completion date: February 21, 2003 | Permit id: 0301280004 | |||||
SCORE 56 Grading for sfd 1618 cu yd Date: March 7, 2000 Contractor: Hamm Applicant: Land Design Consultants Larry Marr | Permit status: Permisud | Completion date: April 23, 2002 | Permit id: 9911010001 | |||||
Mech for new sfd Date: September 12, 2001 Applicant: Same As Owner | Permit status: Finaled | Completion date: May 1, 2002 | Permit id: 0109120013 | |||||
SCORE 82 A/c relocation 2 units Date: November 15, 2002 Contractor: Enertek Applicant: Enertek | Permit status: Finaled | Completion date: April 11, 2003 | Permit id: 0211150019 | |||||
Plumbing for new sfd Date: January 9, 2001 Applicant: Same As Owner | Permit status: Finaled | Completion date: May 1, 2002 | Permit id: 0101090013 | |||||
SCORE 100 Gasline for bbq Date: August 30, 2002 Contractor: Nautical Designs Inc Applicant: Nautical Pools | Permit status: Finaled | Completion date: February 25, 2003 | Permit id: 0208300005 |