Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 86 New sfr plan b1 /res 2811sf w/att garage 781sf & porch 44sf Applicant: Chiu Richard | Permit status: Finaled | Completion date: August 2, 2007 | Permit id: 0504060045 | |||||
SCORE 98 Temporary power pole w/4 subpoles Date: June 14, 2006 Contractor: S And S Rentafence Applicant: Parsell Chris | Permit status: Finaled | Completion date: June 15, 2006 | Permit id: 0606140032 | |||||
SCORE 86 Electrical work for new s f r Date: June 30, 2006 Contractor: Texton Construction Co Inc Applicant: Kuo Chin | Permit status: Finaled | Completion date: August 2, 2007 | Permit id: 0606300018 | |||||
SCORE 84 Hvac for new s f r Date: November 16, 2006 Contractor: K C A Air Inc Applicant: Srisan Charles | Permit status: Finaled | Completion date: August 2, 2007 | Permit id: 0611160011 | |||||
SCORE 79 Plumbing for new sfr Date: June 20, 2006 Contractor: Mauricios Plumbing Applicant: Ramirez Mauricio | Permit status: Finaled | Completion date: August 2, 2007 | Permit id: 0606190040 | |||||
SCORE 99 Connect house sewer to p/l Date: August 7, 2007 Contractor: Texton Construction Co. Inc Applicant: Shen | Permit status: Finaled | Completion date: August 7, 2007 | Permit id: 0708060022 |