Plumbing permit Date: September 23, 2009 Client: Jar Chocolate Works Lp | Permit status: Completed | Permit id: 238852 | |||||
Suppression permit Date: October 26, 2009 Client: Jar Chocolate Works Lp | Permit status: Completed | Permit id: 244578 | |||||
Alteration permit Date: November 9, 2009 Client: Jar Chocolate Works Lp | Permit status: Completed | Permit id: 241477 | |||||
Electrical permit Date: August 24, 2009 Client: Jar Chocolate Works Lp | Permit status: Completed | Permit id: 233523 | |||||
Alteration permit Date: June 21, 2012 Client: Jar Chocolate Works Lp | Permit status: Completed | Permit id: 409820 | |||||
Electrical permit Date: August 24, 2009 Client: Jar Chocolate Works Lp | Permit status: Completed | Permit id: 233523 | |||||
Alteration permit Date: June 21, 2012 Client: Jar Chocolate Works Lp | Permit status: Completed | Permit id: 409820 | |||||
Alteration permit Date: September 11, 2009 Client: Jar Chocolate Works Lp | Permit status: Completed | Permit id: 233627 | |||||
Plumbing permit Date: September 8, 2009 Client: Jar Chocolate Works Lp | Permit status: Completed | Permit id: 234685 | |||||
Suppression permit Date: October 26, 2009 Client: Jar Chocolate Works Lp | Permit status: Completed | Permit id: 244578 | |||||
SCORE 100 Install 1 mop sink, 1 water closet, 1 lav, water heater and 2 floor drains. The installation will comply with the philadephia plubming code 2004 Date: November 14, 2017 Contractor: Dominic Garofolo Client: Jar Chocolate Works Lp | Permit type: Plumbing permit | Permit status: Active | Completion date: November 14, 2017 | Permit id: 832059 | |||||
SCORE 86 For interior alterations to include new interior non-load bearing partitions to create a fitness center on first floor, accessed only by tenants (not for public use) Date: November 10, 2017 Contractor: Russ Kelly And Associates Inc Client: Jar Chocolate Works Lp | Permit type: Alteration permit | Permit status: Active | Completion date: November 20, 2017 | Permit id: 818779 | |||||
SCORE 85 Exterior facade repaires per historic approval Date: May 9, 2017 Contractor: Cri Restoration Inc Client: Jar Chocolate Works Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: October 20, 2017 | Permit id: 782244 | |||||
SCORE 82 Certification Date: December 12, 2008 Contractor: Genserve Inc Client: Jar Chocolate Works Lp | Permit status: Completed | Permit id: 15126 | |||||
SCORE 100 Alterations, for lobby renovation as per plans Date: September 11, 2009 Contractor: Revo Industries Inc Client: Jar Chocolate Works Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: December 7, 2009 | Permit id: 233627 | |||||
SCORE 99 Add 4 hi hats, 2 exit signs, 7 outlets, moving 5 data drops cat5 plenum as per 2005 nec (cc district) Date: August 24, 2009 Contractor: All Systems Electric And Mainten Client: Jar Chocolate Works Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: December 16, 2009 | Permit id: 233523 | |||||
SCORE 100 Installation of new pantry sink. Existing restroom to be renovated to meet ada standards. Re-locate drains and water lines and new fixtures: water closet, lavatory sink Date: September 8, 2009 Contractor: Lees Plumbing Inc Client: Jar Chocolate Works Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 7, 2009 | Permit id: 234685 | |||||
SCORE 100 Curb trap and new sewer for area drains Date: September 23, 2009 Contractor: Sam Wexler Plumbing Inc Client: Jar Chocolate Works Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: October 2, 2009 | Permit id: 238852 | |||||
SCORE 100 Remove built up roof & deck & replace with . 0 white tpo on an existing apt. Building Date: November 9, 2009 Contractor: Belcher Roofing Corporation Client: Jar Chocolate Works Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: May 11, 2010 | Permit id: 241477 | |||||
SCORE 100 Relocation of two heads in the lobby Date: October 26, 2009 Contractor: Oliver Sprinkler Co Inc Client: Jar Chocolate Works Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: December 7, 2009 | Permit id: 244578 | |||||
Remove existing decommissioned exterior fire escape as part of facade maintenance and repair program. Permit holder must ensure this fire escape is not part of a required means of egress, approval of this permit notwithstanding. Phc staff to review masonry repair sample in the field for final approval. Date: June 21, 2012 Client: Jar Chocolate Works Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: September 4, 2012 | Permit id: 409820 | |||||
SCORE 100 Relocate 18 existing sprinkler heads (multi-family) Date: December 4, 2017 Contractor: A And S Sprinkler Co Inc Client: Jar Chocolate Works Lp | Permit type: Suppression permit | Permit status: Active | Completion date: December 4, 2017 | Permit id: 832152 |