Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 New sfd/gar plan 3ar 3359/581 sq ft Applicant: Davidon Homes | Permit status: Finaled | Completion date: October 24, 2003 | Permit id: 0212310049 | |||||
Retaining wall 1 high x 75 long Date: February 21, 2003 Value: $2,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: October 24, 2003 | Permit id: 0302210006 | |||||
SCORE 95 Roof-mounted pv system 4. 3 kw panels 1,024 sq ft Applicant: Solarcity Corp | Permit status: Finaled | Completion date: March 6, 2012 | Permit id: 1108180033 | |||||
Electrical for new sfd Date: February 6, 2003 Applicant: Same As Owner | Permit status: Finaled | Completion date: October 24, 2003 | Permit id: 0302060020 | |||||
SCORE 95 Elect for roof-mounted pv system 4. 3 kw panels Date: August 25, 2011 Contractor: Solarcity Applicant: Solarcity Corp | Permit status: Finaled | Completion date: March 6, 2012 | Permit id: 1108180019 | |||||
Mechanical for new sfd Date: February 27, 2003 Applicant: Same As Owner | Permit status: Finaled | Completion date: October 24, 2003 | Permit id: 0302270035 | |||||
Plumbing for new sfd Date: February 10, 2003 Applicant: Same As Owner | Permit status: Finaled | Completion date: October 24, 2003 | Permit id: 0302100032 |