Alteration permit Date: April 4, 2007 Client: Sunoco Llc | Permit status: Completed | Permit id: 66449 | |||||
Sign permit Date: January 9, 2013 Client: Sunoco Llc | Permit status: Completed | Permit id: 443111 | |||||
Electrical permit Date: February 6, 2013 Client: Sunoco Llc | Permit status: Completed | Permit id: 451929 | |||||
Zoning/use permit Date: October 4, 2010 Client: Sunoco Llc | Permit status: Completed | Permit id: 301684 | |||||
Mechanical permit Date: April 1, 2010 Client: Sunoco Llc | Permit status: Completed | Permit id: 264620 | |||||
Zoning/use permit Date: November 15, 2012 Client: Sunoco Llc | Permit status: Completed | Permit id: 423252 | |||||
Electrical permit Date: March 17, 2010 Client: Sunoco Llc | Permit status: Expired | Permit id: 266369 | |||||
New construction permit Date: October 18, 2010 Client: Sunoco Llc | Permit status: Completed | Permit id: 304596 | |||||
New construction permit Date: October 18, 2010 Client: Sunoco Llc | Permit status: Completed | Permit id: 304596 | |||||
Mechanical permit Date: April 1, 2010 Client: Sunoco Llc | Permit status: Completed | Permit id: 264620 | |||||
Electrical permit Date: February 6, 2013 Client: Sunoco Llc | Permit status: Completed | Permit id: 451929 | |||||
Electrical permit Date: November 18, 2010 Client: Sunoco Llc | Permit status: Completed | Permit id: 306549 | |||||
Sign permit Date: January 9, 2013 Client: Sunoco Llc | Permit status: Completed | Permit id: 443111 | |||||
Zoning use permit Date: November 15, 2012 Client: Sunoco Llc | Permit status: Completed | Permit id: 423252 | |||||
Alteration permit Date: April 4, 2007 Client: Sunoco Llc | Permit status: Completed | Permit id: 66449 | |||||
Zoning use permit Date: October 4, 2010 Client: Sunoco Llc | Permit status: Completed | Permit id: 301684 | |||||
SCORE 100 Disconnect power to existing sign. Reconnect power to new sign as per 2008 nec(gas station) Date: February 6, 2013 Contractor: Fox Chase Electrical Inc Client: Sunoco Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: July 18, 2013 | Permit id: 451929 | |||||
SCORE 100 Disconnect (4) gas dispensers. Reconnect (4) new dispensers using same wires and seal offs. Disconnect (2)submercible pumps and reconnect (2) new pumps using same wires and seal offs. Remove existing dispenser manager and install new with new e-stop. In accordance with 2005 nec Date: March 17, 2010 Contractor: Pallanta, Anthony Client: Sunoco Llc | Permit type: Electrical permit | Permit status: Expired | Completion date: March 17, 2010 | Permit id: 266369 | |||||
SCORE 85 Application for the replacement of the undrground fuel storate tanks, replacement of (4) fuel dispenser islands , and the associated concretre mats for each. (2) economy fuel tanks and (1) ultra fuel tank shall be removed and (1) regular fuel tank and (1) diesel ultra fuel tank to be installed. Date: October 4, 2010 Contractor: Cornerstone Consulting Client: Sunoco Llc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: October 4, 2010 | Permit id: 301684 | |||||
SCORE 85 Remove 3 and install 2 new gasoline underground fuel storage tanks. All work to be in accordance with pa dep regulations, all applicable codes, including the philadelphia fire code (chapter 34),nfpa and nfpa 31. Applicant is required to subjmit a closure report to pa dep in accordance with state regulations. Call city bldg inspector 48 hours prior to starting work to schedule inspection. Plans also include details for installation of new gasoline dispensers and islands approved under permit #305066. Date: October 18, 2010 Contractor: Cornerstone Consulting Client: Sunoco Llc | Permit type: New construction permit | Permit status: Completed | Completion date: December 5, 2010 | Permit id: 304596 | |||||
SCORE 85 Remove existing and install four new fuel dispensers, pump islands, and mats in accordance with plans approved under ap #304596.. Date: October 18, 2010 Contractor: Cornerstone Consulting Client: Sunoco Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 5, 2010 | Permit id: 305066 | |||||
SCORE 100 Install power to fuel pumps, low voltage cable to fuel pumps & control wiring. Date: November 18, 2010 Contractor: Lai John Client: Sunoco Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: May 12, 2011 | Permit id: 306549 | |||||
Re-facing exisitng free-standing sign Date: November 15, 2012 Client: Sunoco Llc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: November 15, 2012 | Permit id: 423252 | |||||
Removal of existing price panel and installation of led price panel sign cabinet within two (2) separate existing free-standing signs per engineers plans. Separate electrical permit required. Date: January 9, 2013 Client: Sunoco Llc | Permit type: Sign permit | Permit status: Completed | Completion date: August 8, 2013 | Permit id: 443111 | |||||
SCORE 100 Replacement of four (4) fuel dispensers and dispenser piping below island as per plans. All work to be in accordance with pennsylvania d. E. P. Regulations, all applicable codes, nfpa and nfpa 31 and ifc. Date: April 1, 2010 Contractor: Ferguson And Mccann Inc Client: Sunoco Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: January 19, 2011 | Permit id: 264620 | |||||
SCORE 99 Remove and replace sales counter;patch acoustical ceiling Date: April 4, 2007 Contractor: A Yerger Inc Client: Sunoco Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: October 30, 2007 | Permit id: 66449 |