Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Install roof-mounted pv sys 2. 76 kw 12 panels 158. 25 sf Applicant: Streamline Permits | Permit status: Finaled | Completion date: October 28, 2013 | Permit id: 1306050067 | |||||
SCORE 99 New retaining wall 3h x 20l Applicant: E And J Construction J. Hernandez | Permit status: Finaled | Completion date: July 2, 2014 | Permit id: 1402100044 | |||||
New sfd/gar/por/outdoor rm/retreat plan 4xy a 2,920/508/79/259/118 sf 5 bdrm/3 bath Date: April 22, 2013 Value: $592,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: October 28, 2013 | Permit id: 1304090006 | |||||
SCORE 99 New spa only 1 sq ft laco std plan 26077-14 Applicant: E And J Construction J. Hernandez | Permit status: Finaled | Completion date: July 2, 2014 | Permit id: 1404140001 | |||||
SCORE 100 Elect for roof-mounted pv sys 2. 76 kw 12 panels 158. 25 sf Date: June 5, 2013 Contractor: Sunpower Corporation Systems Applicant: Streamline Permits | Permit status: Finaled | Completion date: October 28, 2013 | Permit id: 1306050048 | |||||
SCORE 99 Electrical for a/c relocation,bbq area,and future pool and spa reg plan apprvl r2014-00338 Date: February 10, 2014 Contractor: E And J Construction Applicant: E And J Construction J. Hernandez | Permit status: Finaled | Completion date: July 2, 2014 | Permit id: 1402100028 | |||||
SCORE 99 Mechanical for a/c relocation reg plan apprvl r2014-00338 Date: February 10, 2014 Contractor: E And J Construction Applicant: E And J Construction J. Hernandez | Permit status: Finaled | Completion date: July 2, 2014 | Permit id: 1402100016 | |||||
SCORE 99 Gasline for firepit,bbq and future pool and spa reg plan apprvl r2014-00338 Date: February 10, 2014 Contractor: E And J Construction Applicant: E And J Construction J. Hernandez | Permit status: Finaled | Completion date: July 2, 2014 | Permit id: 1402100021 |