Plumbing permit Date: November 6, 2009 Client: Ngunjiri Faith | Permit status: Completed | Permit id: 243371 | |||||
New construction permit Date: April 27, 2009 Client: Ngunjiri Faith | Permit status: Completed | Permit id: 209518 | |||||
Mechanical permit Date: August 5, 2010 Client: Ngunjiri Faith | Permit status: Completed | Permit id: 294053 | |||||
Zoning/use permit Date: March 10, 2009 Client: Ngunjiri Faith | Permit status: Completed | Permit id: 192032 | |||||
Zoning permit Date: January 12, 2009 Client: Ngunjiri Faith | Permit status: Completed | Permit id: 190386 | |||||
Electrical permit Date: June 17, 2009 Client: Ngunjiri Faith | Permit status: Expired | Permit id: 221381 | |||||
Plumbing permit Date: November 6, 2009 Client: Ngunjiri Faith | Permit status: Completed | Permit id: 243371 | |||||
Zoning permit Date: January 12, 2009 Client: Ngunjiri Faith | Permit status: Completed | Permit id: 190386 | |||||
New construction permit Date: April 27, 2009 Client: Ngunjiri Faith | Permit status: Completed | Permit id: 209518 | |||||
Mechanical permit Date: August 5, 2010 Client: Ngunjiri Faith | Permit status: Completed | Permit id: 294053 | |||||
Zoning use permit Date: March 10, 2009 Client: Ngunjiri Faith | Permit status: Completed | Permit id: 192032 | |||||
Electrical permit Date: June 17, 2009 Client: Ngunjiri Faith | Permit status: Expired | Permit id: 221381 | |||||
Erection of a three (3) story semi-detached structure inducing one (1) interior parking space for use as a single family dwelling. Date: March 10, 2009 Client: Ngunjiri Faith | Permit type: Zoning/use permit | Permit status: Completed | Completion date: March 10, 2009 | Permit id: 192032 | |||||
For the relocation of lot lines. Date: January 12, 2009 Client: Ngunjiri Faith | Permit type: Zoning permit | Permit status: Completed | Completion date: January 12, 2009 | Permit id: 190386 | |||||
SCORE 82 Erection of a 2 story semi detached structure as per plans. 33 total lots - see parent ap#208108 for plans. Separate permits required for mechanical, electrical and plumbing. Date: April 27, 2009 Contractor: Dale Contractors Inc Client: Ngunjiri Faith | Permit type: New construction permit | Permit status: Completed | Completion date: August 27, 2010 | Permit id: 209518 | |||||
SCORE 100 Installation of a 200amp service, 41 general recepts, light fixtures, 25 switches, 5 smoke detectors, and communication points as per 2005 nec (north district) Date: June 17, 2009 Contractor: Apex Electrical Svcs Llc Client: Ngunjiri Faith | Permit type: Electrical permit | Permit status: Expired | Completion date: September 16, 2010 | Permit id: 221381 | |||||
SCORE 100 Install house drain,trap rwc yd, and lateral w stormwater management Date: July 16, 2009 Contractor: Meco Constructors Inc Client: Ngunjiri Faith | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 20, 2013 | Permit id: 226798 | |||||
SCORE 96 Install one heat pump unit including fan coil unit (sfd) Date: August 5, 2010 Contractor: J Rihl Inc Client: Ngunjiri Faith | Permit type: Mechanical permit | Permit status: Completed | Completion date: July 25, 2013 | Permit id: 294053 | |||||
SCORE 96 Installation of: first floor- water closet, lavatory and kitchen sink. Second floor- water closet, lavatory and bathtub Date: November 6, 2009 Contractor: J Rihl Inc Client: Ngunjiri Faith | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 20, 2013 | Permit id: 243371 | |||||
SCORE 95 Replace house drain, curb trap & fai pa20171600567 "self-certifications are no longer permitted" - "all excavations and plumbing trenches in excess of 5 feet in depth must have approved shoring in place at the time of inspection" Date: June 9, 2017 Contractor: Roto Rooter Services Company Client: Ngunjiri Faith | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 6, 2017 | Permit id: 790688 |