Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Plumbing permit Date: November 7, 2014 Client: Agaf Holdings L P | Permit status: Completed | Permit id: 572975 | |||||
Suppression permit Date: November 21, 2014 Client: Agaf Holdings L P | Permit status: Completed | Permit id: 570342 | |||||
Electrical permit Date: November 4, 2014 Client: Agaf Holdings L P | Permit status: Completed | Permit id: 571951 | |||||
New construction permit Date: November 18, 2013 Client: Agaf Holdings L P | Permit status: Completed | Permit id: 497394 | |||||
Zoning/use permit Date: September 12, 2013 Client: Agaf Holdings L P | Permit status: Completed | Permit id: 483111 | |||||
Mechanical permit Date: November 13, 2014 Client: Agaf Holdings L P | Permit status: Completed | Permit id: 573826 | |||||
Zoning admin review Date: May 30, 2014 Client: Agaf Holdings L P | Permit status: Completed | Permit id: 525966 | |||||
Zoning use permit Date: September 12, 2013 Client: Agaf Holdings L P | Permit status: Completed | Permit id: 483111 | |||||
Administrative approval of previous permit number 444716 granted under zba cal. No. 19638 to convert a green roof above the four story portion of the single family dwelling to a roof deck with access via a stair from the previously approved roof deck above the front three story portion. Size and location as shown in application. See a p 525946 for plans Date: May 30, 2014 Permit type: Zoning admin review | Permit status: Completed | Completion date: May 30, 2014 | Permit id: 525966 | |||||
SCORE 100 200amp service,all proper grounding and bonding,smoke and c o detectors,complete wiring per 2008 nec (sfd) Date: November 4, 2014 Contractor: Bongiovanni Samuel M Permit type: Electrical permit | Permit status: Completed | Completion date: January 26, 2015 | Permit id: 571951 | |||||
SCORE 93 3 4 ws, 5" ct, fai, hd & 7-fixtures (sfd) pa20143110806 "self-certifications are no longer permitted" - "all excavations & plumbing trenches in excess of 5 in depth must have approved shoring in place at the time of inspection Date: November 7, 2014 Contractor: Lepore Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: February 18, 2015 | Permit id: 572975 | |||||
SCORE 100 Installtion of fire suppression system for residential space. 2" feed main. Nfpa 13r code compliancy certified by john fee pe Date: November 21, 2014 Contractor: Elite Fire Protection Permit type: Suppression permit | Permit status: Completed | Completion date: January 21, 2015 | Permit id: 570342 | |||||
SCORE 100 Install two 80,0 btu 95% gas furnace with air and related duct work one in basement and one on 3rd fl Date: November 13, 2014 Contractor: Anthony Casile Permit type: Mechanical permit | Permit status: Completed | Completion date: February 2, 2015 | Permit id: 573826 | |||||
Lots 1-7 to be used as a sfd with (1) parking stall each lot. See a p# 483099 for plans Date: September 12, 2013 Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 12, 2013 | Permit id: 483111 | |||||
For the construction of building foundation as per plans see ap# 494711 for plans and log notes Date: September 18, 2013 Permit type: New construction permit | Permit status: Expired | Completion date: August 4, 2014 | Permit id: 494716 | |||||
For the erection of a four story, sfd, on previously permitted foundation permit #494716 with basement, one off street parking stall, rear deck at second floor, as per plans. (see ap #497388 for plans and documents) Date: November 18, 2013 Permit type: New construction permit | Permit status: Completed | Completion date: January 21, 2015 | Permit id: 497394 |