Alteration permit Date: August 19, 2013 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 483160 | |||||
Electrical permit Date: August 31, 2010 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 291416 | |||||
Zoning admin review Date: November 21, 2008 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 185149 | |||||
Electrical permit Date: October 10, 2012 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 431864 | |||||
Zoning/use permit Date: January 20, 2016 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 650036 | |||||
Plumbing permit Date: October 30, 2008 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 185534 | |||||
Zoning/use permit Date: August 13, 2012 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 418536 | |||||
Alteration permit Date: January 3, 2012 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 374818 | |||||
Suppression permit Date: June 3, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 193179 | |||||
Electrical permit Date: October 31, 2013 Client: Friends Of Mast School Inc | Permit status: Expired | Permit id: 498808 | |||||
Suppression permit Date: June 10, 2010 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 268584 | |||||
New construction permit Date: January 14, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 186085 | |||||
Plumbing permit Date: March 15, 2010 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 266806 | |||||
Administrative permit Date: January 7, 2015 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 579207 | |||||
Zoning/use permit Date: November 27, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 180381 | |||||
Suppression permit Date: December 9, 2013 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 497338 | |||||
Electrical permit Date: September 10, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 231360 | |||||
Mechanical permit Date: March 14, 2011 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 329195 | |||||
Plumbing permit Date: April 1, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 207666 | |||||
Addition permit Date: December 9, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 241473 | |||||
Permit for the erection of a three(3) story addition to an existing structure as part of an existing charger school and for the erection of a two(2) story accessory parking garage with twenty-three(23) parking spaces (lower level) and twenty-six(26) parking spaces (upper level) for a total of forty-nine(49) parking spaces in garage and one hundred-ten(110) existing accessory open air parking spaces including six(6) accessible parking spaces. Size and location as shown in the application. Date: April 16, 2008 Client: Friends Of Mast School Inc | Applicant: Carrie B. Nase, Esq. | Permit type: Appeal | Permit status: Granted/prov | Completion date: May 14, 2008 | Permit id: 5302 | |||||
Permit for the erection of a two story addition to an existing one story /two story structure(maximum height nte 44 feet), for the erection of a three(3) story structure for (parking garage) for the reconfiguration of parking lot including nine(9) spaces with no access to drives and aisles, including six(6) handicapped accessible spaces for a new total of 202 spaces all accessory for use as an educational facility (size and location as shown on the application) Date: November 5, 2008 Client: Friends Of Mast School Inc | Applicant: Carrie B. Nase, Esquire | Permit type: Appeal | Permit status: Granted/prov | Completion date: January 27, 2009 | Permit id: 7653 | |||||
Addition permit Date: December 9, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 241473 | |||||
Electrical permit Date: August 31, 2010 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 291416 | |||||
Electrical permit Date: October 10, 2012 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 431864 | |||||
Suppression permit Date: June 3, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 193179 | |||||
Alteration permit Date: August 19, 2013 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 483160 | |||||
Plumbing permit Date: March 15, 2010 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 266806 | |||||
Zoning admin review Date: November 21, 2008 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 185149 | |||||
Plumbing permit Date: October 30, 2008 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 185534 | |||||
Mechanical permit Date: March 14, 2011 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 329195 | |||||
Electrical permit Date: September 10, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 231360 | |||||
Administrative permit Date: January 7, 2015 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 579207 | |||||
New construction permit Date: January 14, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 186085 | |||||
Zoning use permit Date: August 13, 2012 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 418536 | |||||
Electrical permit Date: October 31, 2013 Client: Friends Of Mast School Inc | Permit status: Expired | Permit id: 498808 | |||||
Alteration permit Date: January 3, 2012 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 374818 | |||||
Suppression permit Date: December 9, 2013 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 497338 | |||||
Zoning use permit Date: November 27, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 180381 | |||||
Zoning use permit Date: January 20, 2016 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 650036 | |||||
Suppression permit Date: June 10, 2010 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 268584 | |||||
Plumbing permit Date: April 1, 2009 Client: Friends Of Mast School Inc | Permit status: Completed | Permit id: 207666 | |||||
Permit for the erection of a two story addition to an existing one story two story structure(maximum height nte 44 feet), for the erection of a three(3) story structure for (parking garage) for the reconfiguration of parking lot including nine(9) spaces with no access to drives and aisles, including six(6) handicapped accessible spaces for a new total of 202 spaces all accessory for use as an educational facility (size and location as shown on the application) Date: November 5, 2008 Client: Friends Of Mast School Inc | Applicant: Carrie B. Nase, Esquire | Permit type: Appeal | Permit status: Granted/prov | Completion date: January 27, 2009 | Permit id: 7653 | |||||
Permit for the erection of a three(3) story addition to an existing structure as part of an existing charger school and for the erection of a two(2) story accessory parking garage with twenty-three(23) parking spaces (lower level) and twenty-six(26) parking spaces (upper level) for a total of forty-nine(49) parking spaces in garage and one hundred-ten(110) existing accessory open air parking spaces including six(6) accessible parking spaces. Size and location as shown in the application. Date: April 16, 2008 Client: Friends Of Mast School Inc | Applicant: Carrie B. Nase, Esq. | Permit type: Appeal | Permit status: Granted/prov | Completion date: May 14, 2008 | Permit id: 5302 | |||||
SCORE 99 Installation of mezzanine in an existing school cafeteria with elevator service and two (2) means of egress. Separate permits required for electrical, mechanical and fire suppression systems. Date: August 19, 2013 Contractor: Bsi Construction Llc Client: Saac Newton Foundation Inc. | Permit type: Alteration permit | Permit status: Completed | Completion date: January 29, 2015 | Permit id: 483160 | |||||
SCORE 95 Extend existing sprinkler system into new mezzanine. Relocate sprinklers for newly installed elevator and march rm. Date: December 9, 2013 Contractor: Preferred Fire Protection Inc Client: Saac Newton Foundation Inc. | Permit type: Suppression permit | Permit status: Completed | Completion date: February 2, 2015 | Permit id: 497338 | |||||
SCORE 59 Installation of new full color led signs on parking garage. Installation of 1 vinyl banner sign, back lit Date: August 13, 2012 Contractor: S And S Electrical Services Inc Client: Saac Newton Foundation Inc. | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 13, 2012 | Permit id: 418536 | |||||
SCORE 100 Install 2-20a ckts for video sign. All work done in accordance with 2008 nec(school))(east dist) Date: October 10, 2012 Contractor: Carr And Duff Co Client: Saac Newton Foundation Inc. | Permit type: Electrical permit | Permit status: Completed | Completion date: January 8, 2013 | Permit id: 431864 | |||||
SCORE 95 Provide relocation of existing ductile iron domestic water main to reroute around ramp for the new parking structure - provide connection for existing 18" rcp in parking lot and run 10" ductile iron storm drain to within 5-0" of the new parking structure - trench drain and all associated piping with the new structure to be done by others Date: October 30, 2008 Contractor: Krzyzanowski Adam Client: Saac Newton Foundation Inc. | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 16, 2009 | Permit id: 185534 | |||||
Construction of a parking garage. Date: January 14, 2009 Client: Saac Newton Foundation Inc. | Permit type: New construction permit | Permit status: Completed | Completion date: September 22, 2009 | Permit id: 186085 | |||||
SCORE 100 Relocate existing fire hydrant to new location as per plan. Date: June 3, 2009 Contractor: Patriot Sprinkler Company Client: Saac Newton Foundation Inc. | Permit type: Suppression permit | Permit status: Completed | Completion date: October 19, 2009 | Permit id: 193179 | |||||
SCORE 100 Fixture installation Date: April 1, 2009 Contractor: John Uebele Jr Client: Saac Newton Foundation Inc. | Permit type: Plumbing permit | Permit status: Completed | Completion date: August 5, 2009 | Permit id: 207666 | |||||
SCORE 100 Install 1 - 100amp feeder, 9 exit emergency lights, 28 lights as per 2005 nec (east district) Date: September 10, 2009 Contractor: Sunlight Electrical Client: Saac Newton Foundation Inc. | Permit type: Electrical permit | Permit status: Completed | Completion date: October 13, 2009 | Permit id: 231360 | |||||
SCORE 100 Install two manual dry standpipes in a new 3-level open parking garage as per plans Date: September 3, 2009 Contractor: Advance Management Corp Client: Saac Newton Foundation Inc. | Permit type: Suppression permit | Permit status: Completed | Completion date: October 19, 2009 | Permit id: 231843 | |||||
Partial demo, construct new 2nd & 3rd floors 2 story addition for extension of existing school with the associated alterations, civil site work, as per submitted plans. Date: December 9, 2009 Client: Saac Newton Foundation Inc. | Permit type: Addition permit | Permit status: Completed | Completion date: March 18, 2011 | Permit id: 241473 | |||||
SCORE 100 Demo of existing bathrooms - relocate bathroom, relocate roof drains (3), add new water closets (3),lavs (3), (1) shower, (2) sinks, (1) washer box, (3) floor drains Date: March 15, 2010 Contractor: Tandem Associates Inc Client: Saac Newton Foundation Inc. | Permit type: Plumbing permit | Permit status: Completed | Completion date: February 7, 2011 | Permit id: 266806 | |||||
SCORE 74 Construction of addition to existing educationaol facility to be built above existing 1st floor (2nd and 3rd floors proposed of approximately construction of open air parking structure for an additional 76 parking spaces for total of 202 spaces Date: November 27, 2009 Contractor: Fox Rothschild, Llp Client: Saac Newton Foundation Inc. | Permit type: Zoning/use permit | Permit status: Completed | Completion date: December 3, 2009 | Permit id: 180381 | |||||
SCORE 100 Install new sprinkler system and standpipes in new addition. Tie into existing riser in existing building Date: June 10, 2010 Contractor: Simplexgrinnell Client: Saac Newton Foundation Inc. | Permit type: Suppression permit | Permit status: Completed | Completion date: February 7, 2011 | Permit id: 268584 | |||||
SCORE 100 Complete electrical installation of 3 story addition,new service and fire alarm as per 2008 nec nfpa 72 Date: August 31, 2010 Contractor: Sunlight Elec. Contr. Co. Inc Client: Saac Newton Foundation Inc. | Permit type: Electrical permit | Permit status: Completed | Completion date: March 17, 2011 | Permit id: 291416 | |||||
Permit for already installed new hvac system, duct work, diffusers, accessory mechanicals, as per submitted plans, by licensed mechanical contractor, vif.. Date: March 14, 2011 Client: Saac Newton Foundation Inc. | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 1, 2011 | Permit id: 329195 | |||||
Install wheel chair lift in existing building Date: January 3, 2012 Client: Saac Newton Foundation Inc. | Permit type: Alteration permit | Permit status: Completed | Completion date: September 13, 2012 | Permit id: 374818 | |||||
Requesting administrative review to application #134568. To change the size of the proposed accessory parking structure and increase the number of parking spaces. Date: November 21, 2008 Client: Saac Newton Foundation Inc. | Permit type: Zoning admin review | Permit status: Completed | Completion date: November 21, 2008 | Permit id: 185149 | |||||
SCORE 100 Renovations existing multi purpose room - 1-new trans 100amp pnl feeder, 2-hvac equip lines, 1-lift line, lgt, sw, recpts, tele data outlets & 2-f a dev connect to exist sys as per nec 2008 & nfpa 72 (school) Date: October 31, 2013 Contractor: Sunlight Elec. Contr. Co. Inc Client: Saac Newton Foundation Inc. | Permit type: Electrical permit | Permit status: Expired | Completion date: October 31, 2013 | Permit id: 498808 | |||||
To amend permit #4831 to revise the fire-resistance rating of all building elements to type iib construction in accordance with table 601 of the 2009 ibc. Date: January 7, 2015 Client: Saac Newton Foundation Inc. | Permit type: Administrative permit | Permit status: Completed | Completion date: February 2, 2015 | Permit id: 579207 | |||||
For the erection of an addition to an existing detached structure. Size and location as shown on plans application. Structure for continued use as an educational facility. For the reconfiguration of parking spaces for a new total of one-hundred ninety-eight (198) spaces including seven (7) accessible spaces [minimum of two (2) spaces to be van accessible]. The eighteen (18) stacked parking spaces are to be used by employees only per proviso of a p no 180381. No signs on this application. Date: January 20, 2016 Client: Saac Newton Foundation Inc. | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 20, 2016 | Permit id: 650036 | |||||
Construction of four (4) story above grade plane, w. Open 1st story level, mixed-use education facility addition of structural steel & open web joist w. Shallow concrete foundation & cold-formed steel construction beside exist. Education facility per approved plans; addition to be fully sprinklered. Separate permits reqd for steel joist drawing & special inspector approvals (administrative) & any mech., elec., plumb., & firsupp work. Date: July 5, 2017 Client: Saac Newton Foundation Inc. | Permit type: Addition permit | Permit status: Active | Completion date: November 14, 2017 | Permit id: 774373 | |||||
SCORE 100 Addition: interior plumbing;mast charter school; 4 story building; -the installation will comply with the philadelphia plumbing code 2004 Date: September 1, 2017 Contractor: Lormar Mechanical Services Client: Saac Newton Foundation Inc. | Permit type: Plumbing permit | Permit status: Active | Completion date: November 14, 2017 | Permit id: 799379 | |||||
SCORE 100 Hvac installation including ductwork and mechanical equipment as per plans Date: July 24, 2017 Contractor: Lormar Mechanical Services Client: Saac Newton Foundation Inc. | Permit type: Mechanical permit | Permit status: Active | Completion date: November 14, 2017 | Permit id: 799384 | |||||
SCORE 100 Add to existing bldg - new electrical panel feeder, mechanical equipment feeds, lighting fixtures, exit emergency lighting, switches & occupancy sensors, recept 120v, tele data outlets as per nec 2008 & fire alarm as per nfpa 72 Date: September 25, 2017 Contractor: Sunlight Elec. Contr. Co. Inc Client: Saac Newton Foundation Inc. | Permit type: Electrical permit | Permit status: Active | Completion date: September 25, 2017 | Permit id: 811462 | |||||
SCORE 95 For the extension of fire suppression system to the four (4) story addition. For the installation of a fire suppression system per nfpa 13 and standpipe per nfpa 14 as per approved plans. Date: November 13, 2017 Contractor: Preferred Fire Protection Inc Client: Saac Newton Foundation Inc. | Permit type: Suppression permit | Permit status: Active | Completion date: November 14, 2017 | Permit id: 814358 |