New retaining wall 4h x 68l Date: April 22, 2010 Value: $8,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: March 28, 2011 | Permit id: 1004220055 | |||||
SCORE 100 Install roof-mounted pv system 2. 25 kw panels 131. 31 sf Applicant: Sunpower Corp | Permit status: Finaled | Completion date: October 21, 2011 | Permit id: 1108110048 | |||||
New sfd/gar/por plan 1 c 1,846/423/84 sq ft Date: May 20, 2011 Value: $355,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: October 21, 2011 | Permit id: 1104180005 | |||||
SCORE 100 Elect for roof-mounted pv sys 2. 25 kw panels 131. 31 sf Date: August 17, 2011 Contractor: Sunpower Corporation Systems Applicant: Sunpower Corp | Permit status: Finaled | Completion date: October 21, 2011 | Permit id: 1108110035 | |||||
SCORE 100 Sewer connection for new sfd Date: June 27, 2011 Contractor: Production Plus Plumbing Engineer: N, A | Applicant: Production Plus Plumbing | Permit status: Finaled | Completion date: October 21, 2011 | Expiration date: June 26, 2012 | Permit id: 1106240013 | |||||
SCORE 99 Install roof-mounted pv system 2. 25 kw panels 131. 31 sf Engineer: William Lou | Applicant: Sunpower Corp | Permit status: Finaled | Completion date: October 21, 2011 | Expiration date: August 16, 2012 | Permit id: 1108110048 | |||||
SCORE 99 Elect for roof-mounted pv sys 2. 25 kw panels 131. 31 sf Date: August 17, 2011 Contractor: Unpower Corporation Systems Engineer: William Lou | Applicant: Sunpower Corp | Permit status: Finaled | Completion date: October 21, 2011 | Expiration date: August 16, 2012 | Permit id: 1108110035 | |||||
New sfd gar por plan 1 c 1,846 423 84 sq ft Date: May 20, 2011 Value: $355,000 Engineer: Lgs Architects, Inc. | Applicant: Same As Owner | Permit status: Finaled | Completion date: October 21, 2011 | Expiration date: May 19, 2012 | Permit id: 1104180005 |