Suppression permit Date: June 24, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 285957 | |||||
Suppression permit Date: January 14, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 447944 | |||||
Demolition permit Date: March 31, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 269109 | |||||
Electrical permit Date: February 16, 2016 Client: Hub Properties Trust | Permit status: Completed | Permit id: 669934 | |||||
Fast form building permit Date: August 29, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 174243 | |||||
Electrical permit Date: April 24, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 461353 | |||||
Mechanical permit Date: November 19, 2012 Client: Hub Properties Trust | Permit status: Completed | Permit id: 438597 | |||||
Fast form building permit Date: January 5, 2009 Client: Hub Properties Trust | Permit status: Completed | Permit id: 195246 | |||||
Plumbing permit Date: May 1, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 149180 | |||||
Suppression permit Date: December 3, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 190922 | |||||
Mechanical permit Date: April 15, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 145399 | |||||
Suppression permit Date: August 3, 2016 Client: Hub Properties Trust | Permit status: Active | Permit id: 712139 | |||||
Alteration permit Date: November 29, 2012 Client: Hub Properties Trust | Permit status: Completed | Permit id: 438384 | |||||
Electrical permit Date: August 5, 2011 Client: Hub Properties Trust | Permit status: Completed | Permit id: 356854 | |||||
Use permit Date: January 26, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 258987 | |||||
Alteration permit Date: May 2, 2007 Client: Hub Properties Trust | Permit status: Completed | Permit id: 73034 | |||||
Alteration permit Date: December 4, 2014 Client: Hub Properties Trust | Permit status: Completed | Permit id: 575801 | |||||
Plumbing permit Date: July 13, 2016 Client: Hub Properties Trust | Permit status: Completed | Permit id: 705668 | |||||
Mechanical permit Date: September 13, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 492019 | |||||
Mechanical permit Date: May 6, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 276464 | |||||
Mechanical permit Date: July 1, 2014 Client: Hub Properties Trust | Permit status: Completed | Permit id: 539641 | |||||
Administrative permit Date: December 4, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 505348 | |||||
Alteration permit Date: January 7, 2016 Client: Hub Properties Trust | Permit status: Completed | Permit id: 657331 | |||||
Electrical permit Date: December 23, 2014 Client: Hub Properties Trust | Permit status: Completed | Permit id: 581295 | |||||
Electrical permit Date: May 15, 2015 Client: Hub Properties Trust | Permit status: Expired | Permit id: 610482 | |||||
Plumbing permit Date: February 20, 2015 Client: Hub Properties Trust | Permit status: Completed | Permit id: 589899 | |||||
Plumbing permit Date: June 12, 2014 Client: Hub Properties Trust | Permit status: Completed | Permit id: 542556 | |||||
Alteration permit Date: September 1, 2009 Client: Hub Properties Trust | Permit status: Completed | Permit id: 233623 | |||||
Electrical permit Date: November 24, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 310942 | |||||
Demolition permit Date: October 2, 2015 Client: Hub Properties Trust | Permit status: Completed | Permit id: 642545 | |||||
Suppression permit Date: April 22, 2015 Client: Hub Properties Trust | Permit status: Completed | Permit id: 604783 | |||||
Alteration permit Date: June 18, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 279451 | |||||
Mechanical permit Date: January 9, 2009 Client: Hub Properties Trust | Permit status: Completed | Permit id: 196049 | |||||
Zoning/use permit Date: August 17, 2009 Client: Hub Properties Trust | Permit status: Completed | Permit id: 229161 | |||||
Suppression permit Date: March 12, 2014 Client: Hub Properties Trust | Permit status: Completed | Permit id: 523977 | |||||
Operations permit Date: May 8, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 22309 | |||||
Demolition permit Date: August 14, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 171205 | |||||
Electrical permit Date: June 20, 2007 Client: Hub Properties Trust | Permit status: Completed | Permit id: 83394 | |||||
Alteration permit Date: August 6, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 485885 | |||||
Mechanical permit Date: December 1, 2011 Client: Hub Properties Trust | Permit status: Completed | Permit id: 371040 | |||||
Suppression permit Date: July 20, 2011 Client: Hub Properties Trust | Permit status: Completed | Permit id: 353903 | |||||
Plumbing permit Date: September 17, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 494943 | |||||
Mechanical permit Date: February 17, 2015 Client: Hub Properties Trust | Permit status: Completed | Permit id: 583816 | |||||
Alteration permit Date: September 10, 2015 Client: Hub Properties Trust | Permit status: Completed | Permit id: 634390 | |||||
Alteration permit Date: August 20, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 171208 | |||||
Plumbing permit Date: July 2, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 289081 | |||||
Electrical permit Date: June 18, 2009 Client: Hub Properties Trust | Permit status: Completed | Permit id: 222143 | |||||
Mechanical permit Date: May 19, 2016 Client: Hub Properties Trust | Permit status: Completed | Permit id: 693273 | |||||
Demolition permit Date: March 8, 2011 Client: Hub Properties Trust | Permit status: Completed | Permit id: 328677 | |||||
Fast form building permit Date: May 17, 2007 Client: Hub Properties Trust | Permit status: Active | Permit id: 76716 | |||||
Plumbing permit Date: December 6, 2011 Client: Hub Properties Trust | Permit status: Completed | Permit id: 377255 | |||||
Electrical permit Date: April 10, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 144582 | |||||
Suppression permit Date: October 2, 2007 Client: Hub Properties Trust | Permit status: Completed | Permit id: 106799 | |||||
Demolition permit Date: July 24, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 485078 | |||||
Suppression permit Date: December 12, 2012 Client: Hub Properties Trust | Permit status: Completed | Permit id: 443032 | |||||
Sign permit Date: August 6, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 150780 | |||||
Zoning/use permit Date: July 24, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 150779 | |||||
Alteration permit Date: November 22, 2011 Client: Hub Properties Trust | Permit status: Completed | Permit id: 374650 | |||||
Demolition permit Date: July 6, 2016 Client: Hub Properties Trust | Permit status: Active | Permit id: 705145 | |||||
Electrical permit Date: December 10, 2012 Client: Hub Properties Trust | Permit status: Completed | Permit id: 442623 | |||||
Mechanical permit Date: May 23, 2007 Client: Hub Properties Trust | Permit status: Completed | Permit id: 78117 | |||||
Alteration permit Date: April 21, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 270506 | |||||
Suppression permit Date: January 29, 2015 Client: Hub Properties Trust | Permit status: Completed | Permit id: 587434 | |||||
Electrical permit Date: October 22, 2015 Client: Hub Properties Trust | Permit status: Completed | Permit id: 646945 | |||||
Electrical permit Date: January 15, 2009 Client: Hub Properties Trust | Permit status: Completed | Permit id: 196903 | |||||
Electrical permit Date: September 24, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 302772 | |||||
Mechanical permit Date: September 13, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 492019 | |||||
Suppression permit Date: August 12, 2016 Client: Hub Properties Trust | Permit status: Completed | Permit id: 714566 | |||||
Plumbing permit Date: September 17, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 494943 | |||||
Mechanical permit Date: August 24, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 297737 | |||||
Suppression permit Date: November 15, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 311673 | |||||
Mechanical permit Date: June 17, 2009 Client: Hub Properties Trust | Permit status: Completed | Permit id: 221695 | |||||
Electrical permit Date: February 16, 2016 Client: Hub Properties Trust | Permit status: Completed | Permit id: 669934 | |||||
Mechanical permit Date: December 1, 2011 Client: Hub Properties Trust | Permit status: Completed | Permit id: 371040 | |||||
Electrical permit Date: November 18, 2011 Client: Hub Properties Trust | Permit status: Expired | Permit id: 374617 | |||||
Alteration permit Date: June 28, 2016 Client: Hub Properties Trust | Permit status: Active | Permit id: 687151 | |||||
Electrical permit Date: September 16, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 494797 | |||||
Mechanical permit Date: July 1, 2014 Client: Hub Properties Trust | Permit status: Completed | Permit id: 539641 | |||||
Electrical permit Date: December 10, 2012 Client: Hub Properties Trust | Permit status: Completed | Permit id: 442623 | |||||
Suppression permit Date: October 2, 2007 Client: Hub Properties Trust | Permit status: Completed | Permit id: 106799 | |||||
Fast form building permit Date: August 29, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 174243 | |||||
Zoning use permit Date: July 24, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 150779 | |||||
Mechanical permit Date: October 9, 2015 Client: Hub Properties Trust | Permit status: Completed | Permit id: 644184 | |||||
Plumbing permit Date: June 2, 2016 Client: Hub Properties Trust | Permit status: Completed | Permit id: 696477 | |||||
Electrical permit Date: July 2, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 162355 | |||||
Alteration permit Date: August 20, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 171208 | |||||
Electrical permit Date: February 18, 2014 Client: Hub Properties Trust | Permit status: Completed | Permit id: 519813 | |||||
Suppression permit Date: August 8, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 487832 | |||||
Alteration permit Date: September 1, 2009 Client: Hub Properties Trust | Permit status: Completed | Permit id: 233623 | |||||
Suppression permit Date: September 23, 2014 Client: Hub Properties Trust | Permit status: Completed | Permit id: 563411 | |||||
Alteration permit Date: February 6, 2015 Client: Hub Properties Trust | Permit status: Completed | Permit id: 586388 | |||||
Plumbing permit Date: July 21, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 290470 | |||||
Demolition permit Date: July 24, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 485078 | |||||
Alteration permit Date: November 29, 2012 Client: Hub Properties Trust | Permit status: Completed | Permit id: 438384 | |||||
Alteration permit Date: February 12, 2014 Client: Hub Properties Trust | Permit status: Completed | Permit id: 518165 | |||||
Demolition permit Date: June 28, 2016 Client: Hub Properties Trust | Permit status: Completed | Permit id: 703425 | |||||
Electrical permit Date: July 12, 2007 Client: Hub Properties Trust | Permit status: Completed | Permit id: 87590 | |||||
Plumbing permit Date: February 20, 2015 Client: Hub Properties Trust | Permit status: Completed | Permit id: 589899 | |||||
Electrical permit Date: January 12, 2017 Client: Hub Properties Trust | Permit status: Active | Permit id: 741357 | |||||
Alteration permit Date: March 11, 2011 Client: Hub Properties Trust | Permit status: Completed | Permit id: 323989 | |||||
Alteration permit Date: August 23, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 488795 | |||||
Demolition permit Date: March 31, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 269109 | |||||
Mechanical permit Date: May 23, 2007 Client: Hub Properties Trust | Permit status: Completed | Permit id: 78117 | |||||
Alteration permit Date: May 7, 2007 Client: Hub Properties Trust | Permit status: Completed | Permit id: 72488 | |||||
Demolition permit Date: January 28, 2015 Client: Hub Properties Trust | Permit status: Completed | Permit id: 586918 | |||||
Mechanical permit Date: June 29, 2012 Client: Hub Properties Trust | Permit status: Completed | Permit id: 413954 | |||||
Suppression permit Date: January 24, 2017 Client: Hub Properties Trust | Permit status: Active | Permit id: 754062 | |||||
Mechanical permit Date: January 19, 2017 Client: Hub Properties Trust | Permit status: Active | Permit id: 748236 | |||||
Plumbing permit Date: August 15, 2011 Client: Hub Properties Trust | Permit status: Completed | Permit id: 357819 | |||||
Administrative permit Date: December 4, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 505348 | |||||
Demolition permit Date: August 14, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 171205 | |||||
Use permit Date: January 26, 2010 Client: Hub Properties Trust | Permit status: Completed | Permit id: 258987 | |||||
Plumbing permit Date: April 25, 2014 Client: Hub Properties Trust | Permit status: Completed | Permit id: 532179 | |||||
Mechanical permit Date: May 19, 2016 Client: Hub Properties Trust | Permit status: Completed | Permit id: 693273 | |||||
Suppression permit Date: August 3, 2011 Client: Hub Properties Trust | Permit status: Completed | Permit id: 356272 | |||||
Plumbing permit Date: January 27, 2017 Client: Hub Properties Trust | Permit status: Active | Permit id: 754457 | |||||
Suppression permit Date: December 12, 2012 Client: Hub Properties Trust | Permit status: Completed | Permit id: 443032 | |||||
Demolition permit Date: March 8, 2011 Client: Hub Properties Trust | Permit status: Completed | Permit id: 328677 | |||||
Zoning use permit Date: August 17, 2009 Client: Hub Properties Trust | Permit status: Completed | Permit id: 229161 | |||||
Operations permit Date: May 22, 2013 Client: Hub Properties Trust | Permit status: Completed | Permit id: 22344 | |||||
Fast form building permit Date: May 17, 2007 Client: Hub Properties Trust | Permit status: Active | Permit id: 76716 | |||||
Fast form building permit Date: June 15, 2009 Client: Hub Properties Trust | Permit status: Active | Permit id: 221325 | |||||
Suppression permit Date: December 3, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 190922 | |||||
Alteration permit Date: January 19, 2017 Client: Hub Properties Trust | Permit status: Active | Permit id: 744611 | |||||
Plumbing permit Date: May 1, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 149180 | |||||
Sign permit Date: August 6, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 150780 | |||||
Mechanical permit Date: April 15, 2008 Client: Hub Properties Trust | Permit status: Completed | Permit id: 145399 | |||||
SCORE 100 Install 9-switches, 22-power outlets, & relocate 26-lights utilize existing electrical service as is as per nec 2008 cc district Date: August 12, 2016 Contractor: Mcgoldrick Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: September 12, 2016 | Permit id: 697066 | |||||
SCORE 100 Relocate 16 sprinklers on the 13th floor ez permit sprinkler relocation (nfpa 13)- for the relocation of sprinkler heads as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: May 25, 2016 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: July 6, 2016 | Permit id: 694841 | |||||
SCORE 98 For level 2 alterations: office fit-out of tennant space, all non-structural work as shown on plans application, space used as previously approved business & professional offices. Date: May 12, 2016 Contractor: Patriot Construction Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: September 14, 2016 | Permit id: 688180 | |||||
SCORE 100 Installation of water closet, lavatory, 2- sinks; connect to existing sanitary, vent and domestic water Date: August 11, 2015 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 9, 2015 | Permit id: 630009 | |||||
SCORE 100 Interior demolition non load bearing partitions only(39th floor) Date: July 31, 2015 Contractor: Lakash Constructors Inc Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: September 3, 2015 | Permit id: 628763 | |||||
SCORE 100 Demo & relocate existing circuits, re lamp and re ballast all exisitng fixtures(39) add, (10) down lights, (4) switches. Add (13) new duplex an dconnect to existing circuits from demo. Add (2) exits, as per 2008 nec. Date: March 1, 2017 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: March 14, 2017 | Permit id: 751154 | |||||
SCORE 100 Ez interior demolition - for the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: June 28, 2016 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: July 23, 2016 | Permit id: 703425 | |||||
SCORE 100 Install kitchen sink, point of use water heater; connect to existing sanitary, vent and domestic water Date: June 2, 2016 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 6, 2016 | Permit id: 696477 | |||||
SCORE 100 Relocation of (16) sprinkler head to accomodate new ceilings Date: July 21, 2010 Contractor: Independence Fire Sprinkler Co Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: September 14, 2010 | Permit id: 292302 | |||||
SCORE 100 Relocate 8 existing fxts and add 4 new to existing ctrs, add 2 new sws, relocate 2 exits, add 5 new recepts and (1) furn feed. Reuse existing 110v circuits from old furniture systems (cc dist) Date: August 28, 2008 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: October 29, 2008 | Permit id: 173785 | |||||
SCORE 100 Renovation of existing office space as per plans. Date: October 18, 2011 Contractor: Commercial Construction Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: December 19, 2011 | Permit id: 368817 | |||||
SCORE 100 Relocate 2x4 fixtures, recepts, 3 switches, and 3 existing power feeds as per 2008 nec (cc district) Date: October 4, 2011 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: October 4, 2011 | Permit id: 366606 | |||||
SCORE 100 Relocation of (17) sprinkler heads Date: August 3, 2011 Contractor: Independence Fire Sprinkler Co Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 356272 | |||||
SCORE 100 Installation of (1) pantry sink and open site drain (indirect waste)... Connect to existing sanitary, vent and domestic water Date: February 20, 2015 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: April 18, 2015 | Permit id: 589899 | |||||
SCORE 100 Relocating 24 sprinklers on the 20th & 26th floor bathrooms and common areas. Date: September 20, 2013 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: October 24, 2013 | Permit id: 495904 | |||||
SCORE 100 Install lavatory, toilet with sanitary, water and vent Date: December 23, 2015 Contractor: Nagellavin Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: February 13, 2016 | Permit id: 660190 | |||||
SCORE 100 Interior fit-out of copy printer and pantry space on the 17th floor of an existing office building as per plans. Separate electrical permit required. Date: January 7, 2016 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: March 1, 2016 | Permit id: 657331 | |||||
SCORE 100 Install kitchen sink, connect to sanitary, vent and domestic water Date: December 29, 2015 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 1, 2016 | Permit id: 660328 | |||||
SCORE 100 Relocate 2 diffusers, to comply with ezs permit standards for ductwork ez permit ductwork & warm-air appliances- for the installation of new ductwork, registers grilles diffusers, and warm-air appliances as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: December 29, 2015 Contractor: Ramm Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 13, 2016 | Permit id: 660672 | |||||
SCORE 99 Interior demolition of ductwork and for the installation of ductwork, registers diffusers, vav boxes, and fans as per approved plans. Date: September 13, 2013 Contractor: Hunter Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 29, 2013 | Permit id: 492019 | |||||
SCORE 100 Installation of catgeory 5e low voltage non plenum cabling longest run 3 as per 2008 nec (cc district) Date: October 22, 2015 Contractor: Eagle Industrial Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: January 9, 2016 | Permit id: 646945 | |||||
SCORE 100 Relocate 5 sprinkler heads Date: December 30, 2014 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: January 14, 2015 | Permit id: 582061 | |||||
SCORE 100 Disconnect temp light & pwr,reuse exst distrib,add new buss duct sws,xfmr pnl. Load ctrs,light fixs,meters,feeders,cirts breakers,security,tele data,hvac,sws,devices and recepts as per 2008 nec (cc district) - add to existing fire alarm system as per nfpa72 --bldg permit 572401 Date: March 2, 2015 Contractor: Anmar Electrical Contractor In Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: March 2, 2015 | Permit id: 583036 | |||||
SCORE 99 Furnish labor and material to relocate 17 air devices Date: August 8, 2013 Contractor: Hunter Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: March 19, 2014 | Permit id: 487968 | |||||
SCORE 100 Relocate 18 existing sprinkler heads(commercial) Date: August 8, 2013 Contractor: Precision Sprinkler Services Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: September 30, 2013 | Permit id: 487832 | |||||
SCORE 100 Level ii interior alterations to re-finish existing furnishings, walls & doors and for the creation of a new accessible toilet room in an existing high-rise office building. Separate permits for mechanical, plumbing, electrical and fire suppression systems. Date: August 23, 2013 Contractor: Ernest Bock And Sons Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: November 29, 2013 | Permit id: 488795 | |||||
SCORE 100 1 new transformer, 1 new panel, lights relocate, 17 new lights, 13 new wall sewers, 6 new ceiling senors, 38 new receptacles 3 furniture feeds, 6 existing fire devices relocate and re certify as per 2008 nec, commercial office Date: December 13, 2011 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: December 13, 2011 | Permit id: 369565 | |||||
SCORE 99 Installation of ductwork and mechanicals Date: December 1, 2011 Contractor: Hunter Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 19, 2011 | Permit id: 371040 | |||||
SCORE 100 Category 5e cable runs logest cable 1 ft as per 2008 nec(cc dist)(commercial space) Date: November 18, 2011 Contractor: H B Frazer Co Penna Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: November 18, 2011 | Permit id: 374617 | |||||
SCORE 100 Relocate 24 sprinkler heads (14th floor) Date: November 9, 2011 Contractor: Fire Protection Industries Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: December 19, 2011 | Permit id: 373119 | |||||
SCORE 100 Interior alterations as per plans Date: November 22, 2011 Contractor: Dlauro And Rodgers Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: June 18, 2012 | Permit id: 374650 | |||||
SCORE 96 Office bldg-demo 2 existing sinks & drains, relocate drains & waters to new location & replace the sinks. Date: December 6, 2011 Contractor: D P Ellinger Plumbing Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 19, 2011 | Permit id: 377255 | |||||
SCORE 100 Relocate 5 diffusers Date: June 29, 2012 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 28, 2012 | Permit id: 413954 | |||||
SCORE 100 Tenant fit out as per approved plans. Date: November 29, 2012 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: April 1, 2013 | Permit id: 438384 | |||||
Interior alterations as per approved plans. Date: November 20, 2012 Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Expired | Completion date: July 20, 2015 | Permit id: 438013 | |||||
SCORE 100 Relocate diffusers Date: November 19, 2012 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 22, 2013 | Permit id: 438597 | |||||
SCORE 100 Relocate 4 diffusers Date: December 7, 2012 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: March 4, 2013 | Permit id: 442267 | |||||
SCORE 95 Relocate 22 existing sprinkler heads(commercial) Date: June 23, 2014 Contractor: Preferred Fire Protection Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: July 25, 2014 | Permit id: 544908 | |||||
SCORE 100 Replacement only: 7- water closets, 6- lavatories, 2- urinal onto existing piping- no other fixtures or piping on this permit Date: October 26, 2017 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Active | Completion date: November 17, 2017 | Permit id: 826564 | |||||
SCORE 99 For the installation if new ductwork, registers grilles diffusers, and warm-air appliances as per attached standards. Deviations from these standards require submission of construction and site plans. Date: November 16, 2017 Contractor: Hunter Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Active | Completion date: November 16, 2017 | Permit id: 832673 | |||||
SCORE 100 Relocate 6 diffusers Date: September 12, 2014 Contractor: Ramm Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 13, 2014 | Permit id: 561296 | |||||
SCORE 100 Install sanitary and water lines for a pantry sink Date: August 24, 2017 Contractor: Nagellavin Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 1, 2017 | Permit id: 810545 | |||||
For the relocation of two (2) fire department connections (fdc) from the courtyard to the exterior of an existing high-rise structure, to be reinstalled as freestanding fdcs, as per plans; no other work on this permit; no other changes to existing fire suppression system within existing building. Date: September 21, 2017 Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Active | Completion date: October 13, 2017 | Permit id: 812654 | |||||
SCORE 100 Install 40new fixtures, switches,2 exit lights,25 new receptacles and relocate existing panel and branch circuits per 2008 nec (office space) Date: July 15, 2014 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: February 2, 2016 | Permit id: 540397 | |||||
SCORE 100 Furnish and install cat 6 plemum cables for voice and data per 2008 nec (office space) Date: June 18, 2014 Contractor: Gt Telecom Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: June 18, 2014 | Permit id: 543822 | |||||
SCORE 100 Install kitchen sink for coffee station tie into existing stack and water Date: June 12, 2014 Contractor: E J Raith Mechanical Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: August 4, 2014 | Permit id: 542556 | |||||
SCORE 100 Interior alterations Date: May 7, 2007 Contractor: Dlauro And Rodgers Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: December 4, 2008 | Permit id: 72488 | |||||
SCORE 100 Install a pedestrian protection scaffold 28 long on 16th st per engineers drawings Date: May 2, 2007 Contractor: Safway Services Llc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: December 4, 2008 | Permit id: 73034 | |||||
SCORE 100 Install 7-new lights using existing lighting circuits, 3-new lights switches using existing lighting circuits, 13-new recpts using the existing circuits as per nec 2008 (comm) Date: April 24, 2013 Contractor: Henkels And Mc Coy Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: September 30, 2013 | Permit id: 461353 | |||||
SCORE 100 Relocate 2 spriknlers on the 18th floor-condo Date: April 3, 2013 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: October 24, 2013 | Permit id: 462728 | |||||
SCORE 100 Furnish and install 1 kitchen sink and 1 point of use water heater, extend from existing sanitary vent and domestic water.- the installation will compy with the philadelphia plumbing code 2004 Date: January 27, 2017 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: February 27, 2017 | Permit id: 754457 | |||||
SCORE 100 Install: 21- cat 6 plenum cables- longest 110ft, 2 wireless access points, new wall mounted cabinet to support data cabling, 58- new patch cables, terminate, test and label new cable, support and ground new cable... Work per 2008 nec (hi-rise office building) Date: March 9, 2017 Contractor: Bluestone Communications Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: March 9, 2017 | Permit id: 765052 | |||||
SCORE 89 Furnish and install 12 switches,2 ceiling 0s, new fixtures,2 exit signs and 45 outlets per 2008 nec & nfpa 72(office space ) Date: October 25, 2013 Contractor: Kd Electric Llc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: April 10, 2014 | Permit id: 496499 | |||||
SCORE 100 Furnish and install aprox new data and 23 new voice lines cat5e for new offiace lay out longest run 125 Date: January 16, 2007 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: May 18, 2007 | Permit id: 50059 | |||||
SCORE 100 Replace existing mens and ladies room lav sinks Date: April 21, 2010 Contractor: Lees Plumbing Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 27, 2010 | Permit id: 273907 | |||||
SCORE 100 Installation of (4)pantry sinks with drain, vent and domestic water supply Date: April 21, 2010 Contractor: Lees Plumbing Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 27, 2010 | Permit id: 273911 | |||||
SCORE 100 Remove fixtures, relocate aprox fixtures. Add energy efficent fixtures, change 7 exits and add recetpacles and change 35 switches to wall motion sensors as per 2008 nec (cc district) Date: June 2, 2010 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: March 15, 2011 | Permit id: 273922 | |||||
SCORE 100 Installation of cat 5e tele data as per plans. Date: June 8, 2010 Contractor: Charles H Macdonald Electric I Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: January 9, 2016 | Permit id: 274594 | |||||
SCORE 100 Relocate 27 sprinkler heads(office space)(27th floor) Date: April 27, 2010 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: June 27, 2010 | Permit id: 275315 | |||||
SCORE 100 Construction of a new office within existing tenant space Date: May 14, 2010 Contractor: Commercial Construction Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: June 16, 2010 | Permit id: 276102 | |||||
SCORE 100 Relocate 2 4 fixtures,8 duplex receptacles,2 exits, 4 switches,3 sconces,add 6 new receptacles,2 swiyches, no lead increase as per 2008 nec Date: November 24, 2010 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: January 3, 2011 | Permit id: 313404 | |||||
SCORE 86 Interior alteration as per plans Date: June 11, 2009 Contractor: Agoos Lovera Architects Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: December 14, 2009 | Permit id: 219705 | |||||
SCORE 100 Relocate 28 sprinkler heads. Date: October 2, 2007 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: November 27, 2007 | Permit id: 106799 | |||||
SCORE 100 Install 63 plenum cat 5e cables to 1 telecom room. Date: November 1, 2007 Contractor: New Line Communications Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: September 3, 2013 | Permit id: 101954 | |||||
SCORE 100 Rebuild in place failed 2500kva transformer (13. 2kv primary & 480 277v secondary). Date: June 28, 2011 Contractor: H B Frazer Co Penna Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: December 4, 2015 | Permit id: 350041 | |||||
SCORE 100 Furnish and install cat 5e cables,plenum rated avg cable pull 1 feet as per 2008 nec Date: June 13, 2011 Contractor: Belles Electrical Contractors Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: June 13, 2011 | Permit id: 333922 | |||||
SCORE 100 Relocate (10) diffusers Date: June 17, 2009 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: January 19, 2010 | Permit id: 221695 | |||||
SCORE 100 Fast form building permit Date: June 15, 2009 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit status: Active | Completion date: June 15, 2009 | Permit id: 221325 | |||||
SCORE 100 Furnish and install 39 cat6 voice and 39 cat6 data cables, both plenum rated and install voice data equipment in lan room, longest drop 125, as per 2005 nec artticle 399. 21 + 8 (cc dist) Date: January 15, 2009 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: December 7, 2009 | Permit id: 196903 | |||||
SCORE 100 Relocate fire alarm strobes and install new fire alarm strobes connected to existing circuitry per 2008 nec & nfpa 72 (office bldg) Date: May 28, 2014 Contractor: Metro Electric Co Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: June 25, 2014 | Permit id: 536722 | |||||
SCORE 100 Interior demo & alterations, upgrades to finishes, as per plans. Existing office building no change in use -occupancy. Date: September 10, 2015 Contractor: Lakash Constructors Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: December 17, 2015 | Permit id: 634390 | |||||
SCORE 100 No change in use and occupancy classification. Interior alterations as per approved plans. Separate permit required for mechanical, electrical, plumbing, and fire suppression work. Date: August 24, 2015 Contractor: Lakash Constructors Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: December 7, 2015 | Permit id: 630204 | |||||
SCORE 100 Install 14 recpts, 4-exits, 15-2x2 fixtures, 28-2x4 fixtures, 6-downlights, & 14-motions, demo as per nec 2008 & nfpa 72 (office bldg) Date: August 27, 2013 Contractor: Shoreline Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: August 27, 2013 | Permit id: 489708 | |||||
SCORE 100 Alteration of mechanical system on 57th floor of existing building as per approved plans. Date: January 5, 2016 Contractor: Tracey Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 19, 2016 | Permit id: 645837 | |||||
SCORE 100 Level ii interior alterations (no change of occupancy) to existing business office suite 5 on the 5th floor of an existing high rise building as per approved plans. Existing building fully sprinklered. Separate permits required for any mep or fire suppression work Date: October 15, 2015 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: November 30, 2015 | Permit id: 642548 | |||||
SCORE 96 For selective interior demolition of non load-bearing elements, level 2 interior alterations to update existing dwelling units and and for the creation of eight (8) new units on floors 48-56 of an existing high-rise structure. Upgrades are also to be performed at level 37 ammenities space to create new offices & entertainment areas. Building is fully sprinklered. Separate permits required for mechanical, electrical, plumbing, and fire suppress systems. Date: December 23, 2014 Contractor: Intech Construction Llc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: February 2, 2016 | Permit id: 572401 | |||||
SCORE 100 Installation of sink, sanitary and water lines Date: September 22, 2014 Contractor: Nagellavin Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 13, 2014 | Permit id: 562907 | |||||
SCORE 100 Relocating sprinklers Date: September 23, 2014 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: November 13, 2014 | Permit id: 563411 | |||||
SCORE 100 Ez permit sprinkler relocation (nfpa 13)- for the relocation of sprinkler heads as per attached standards. Deviations from these standards require submission of construction and site plans. Date: August 16, 2017 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: October 20, 2017 | Permit id: 808836 | |||||
SCORE 95 Install 1 speaker strobe & 1 siga-led remote alarm led. Date: May 16, 2011 Contractor: Hatzel And Buehler Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: August 1, 2012 | Permit id: 335188 | |||||
SCORE 100 Relocate (6) diffusers Date: March 30, 2011 Contractor: Cms Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 25, 2011 | Permit id: 332534 | |||||
SCORE 100 Relocate (12) existing sprinkler heads in order to accommodate tenant wall and ceiling layout as per all nfpa no. 13 and local code. Date: September 10, 2013 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: November 29, 2013 | Permit id: 493914 | |||||
SCORE 99 1 kitchen sink and indirect waste Date: July 21, 2010 Contractor: Hunter Mechanical Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 14, 2010 | Permit id: 290470 | |||||
SCORE 92 Furnish and install 175 category 5e plenum cables to various locations per the prints. Ave cable pull 1 feet as per 2008 nec Date: August 4, 2010 Contractor: Donald Belles Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: May 31, 2011 | Permit id: 290225 | |||||
SCORE 100 Install (1) toilet and (1) lavatory, tie into existing sanitary and vent Date: July 2, 2010 Contractor: Nagellavin Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 14, 2010 | Permit id: 289081 | |||||
SCORE 100 Add 26 smk dets,46 ht dets control relays in elev mach rms for shunt trip,add total (6)120v cirs in mach rms from existing panels to pwr shunt trip bkrs in existing panels located in mach rms as per 2008 nec(cc dist) Date: November 18, 2010 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: November 18, 2010 | Permit id: 304896 | |||||
SCORE 100 Furnish and install (86) work area outlets classrooms consisting of (178) plenum rated cat6 telecommunication and telecommunication fit out with a longest run of about 1 as per 2008 nec (cc district) Date: September 16, 2015 Contractor: Charles H Macdonald Electric I Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: March 9, 2016 | Permit id: 632670 | |||||
SCORE 100 For level ii alteration to existing mechanical system in the lobby area to include the installation of registers diffusers and mechanical equipment with associated duct work. All work to be done per approved plans. If field conditions vary contact design engineer prior to the start of any work. Separate permits required for all other work. Date: November 12, 2015 Contractor: Tracey Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Expired | Completion date: June 3, 2016 | Permit id: 632107 | |||||
SCORE 96 Non bearing interior demolition, new drywall partition partitions, acoustic ceiling, doors and frames, finishes. Date: May 23, 2014 Contractor: Intech Construction Llc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: July 25, 2014 | Permit id: 536325 | |||||
SCORE 100 For the installation of hvac equipment to include the demolition of existing hvac equipment with the erection of registers diffuser with associated ductwork. Proposed system to be connected to existing system. All work to be done per approved plans. Separate permits required for all other work. Date: September 11, 2013 Contractor: Cms Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: September 30, 2013 | Permit id: 489863 | |||||
SCORE 100 Level ii interior alterations as per plan. Date: August 26, 2013 Contractor: Murphy Quigley Company Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: September 22, 2014 | Permit id: 483720 | |||||
SCORE 99 Furnish labor and material to relocate diffusers Date: October 9, 2015 Contractor: Hunter Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 30, 2015 | Permit id: 644184 | |||||
SCORE 100 Relocate 2x4s furnish and install new 2x4,5 wall motion switches,2 exit lights, 15 duplex and 4 furniture power per 2008 nec (office space)cc district Date: November 13, 2015 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: December 30, 2015 | Permit id: 645042 | |||||
SCORE 100 For level ii alterations to an existing office building on the fifth floor level. Alteration to include the removal erection of partition walls, provide finishes and furnishing throughout. Building is fully sprinklered. All work to be done per approved plans. Separate permits required of mechanical, electrical, plumbing and fire supression work. Date: September 18, 2014 Contractor: Commercial Construction Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: November 5, 2014 | Permit id: 559018 | |||||
SCORE 100 Demo sys furniture powers,relocate circuits to above ceiling, rewire 25-2x4 fixtures add 6 wall motion sws, new duplex connect to old furniture power.. 2 exit lites & 2-110v ded circuits & devices per 2008 nec (cc district) relocated 1 strobe with no additional wiring as per nfpa72 Date: September 15, 2014 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: February 2, 2016 | Permit id: 561597 | |||||
SCORE 100 Relocate (29) existing sprinkler heads in order to accommodate tenant layouts as per nfpa no. 13 and all local codes. Date: April 28, 2017 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: May 30, 2017 | Permit id: 779038 | |||||
SCORE 100 Relocation replacement of lighting fixtures & relocations of furniture workstations as per nec 2008 (office space) Date: January 15, 2014 Contractor: Metro Electric Co Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: June 25, 2014 | Permit id: 506048 | |||||
Relocate (14) diffusers Date: November 21, 2013 Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: August 14, 2014 | Permit id: 507411 | |||||
SCORE 100 Remove and reinstall (2)sinks. Date: December 1, 2010 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 24, 2010 | Permit id: 313715 | |||||
SCORE 100 Provide 45 voice data cables drops consisting of plenum rated cats5e cable,lable,test,terminate as per 2008 nec Date: January 11, 2011 Contractor: M Gitlin Co Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: January 11, 2011 | Permit id: 315481 | |||||
SCORE 100 Tenant fit-out for offices Date: March 11, 2011 Contractor: Mj Settelen Construction Llc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: April 25, 2011 | Permit id: 323989 | |||||
SCORE 100 Interior alterations per plan - 28th floor Date: March 2, 2011 Contractor: Builders Incorporated Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 326710 | |||||
SCORE 100 Relocate 3 existing strobes to new wall layout. Reinstall 2 speaker, test and certify in working order no additional wiring needed per nfpa 72 (office space)cc district Date: August 12, 2016 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: September 2, 2016 | Permit id: 714428 | |||||
SCORE 100 We will relocating 71 sprinklers on the 8th, 9th, 11th, 22nd, 28th, 30th & 31st floors at pnc. Date: November 12, 2013 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: March 31, 2014 | Permit id: 505423 | |||||
SCORE 100 Install 8 new 2x4 flourscent light fixtures, relocate 2 recepts and 2 switches, demo 6 recepts, 1 pole thru, light fixtures and 2 switches as per 2008 nec (cc district) no change in use Date: April 22, 2014 Contractor: J F Hierholzer Mech And Electric Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: April 22, 2014 | Permit id: 531967 | |||||
SCORE 100 Replacement only of (8)lavatories and (2)water closets Date: April 25, 2014 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 14, 2014 | Permit id: 532179 | |||||
SCORE 95 6 new duplex receptacles, 6 new quads, 1 furniture feed, rework existing lighting in end offices and reception per 2008 (office space) Date: May 23, 2013 Contractor: Hatzel And Buehler Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: November 6, 2013 | Permit id: 473431 | |||||
SCORE 100 Interior demo and alterations, renovations, partitions, ceilings, flooring, furnishings, upgrades to finsihes for office area 10th floor, as per plans. Separate permtis reqd for meps. Date: March 23, 2015 Contractor: Dlauro And Rodgers Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: July 13, 2015 | Permit id: 594617 | |||||
SCORE 100 Remove and replace only: 12 area drains at plaza. No other work on this permit, no new piping on this permit Date: August 18, 2016 Contractor: Bofinger And Breslin Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 17, 2017 | Permit id: 712088 | |||||
SCORE 100 Supply and install sink complete with waste, vent and water lines using existing stack and water lines Date: November 15, 2010 Contractor: Nagellavin Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 21, 2011 | Permit id: 311660 | |||||
SCORE 100 Relocate 18 sprinkler heads, 16th floor Date: November 15, 2010 Contractor: Fire Protection Industries Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: January 21, 2011 | Permit id: 311673 | |||||
SCORE 89 Furnish and install (30)communication points only... In accordance with 2008 nec Date: December 3, 2010 Contractor: Crystal Ball Contracting Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: March 3, 2011 | Permit id: 311829 | |||||
SCORE 100 Remove old corrider lighting & f & i 21-new 2x2 fixtures & 3-wall fixtures as per nec 2008 (office bldg) Date: February 18, 2014 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: May 21, 2014 | Permit id: 519813 | |||||
SCORE 100 Installation of new office partitions, doors, frames and ceilings-office space Date: March 18, 2013 Contractor: Henkels And Mc Coy Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: November 6, 2013 | Permit id: 451491 | |||||
SCORE 100 Interior alterations as per plan. Date: April 1, 2013 Contractor: Dlauro And Rodgers Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: March 5, 2014 | Permit id: 460564 | |||||
SCORE 100 Relocate (8) existing sprinkler heads in order to accommodate new tenant fitout as per all nfpa no. 13 and local codes. Date: January 14, 2013 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: October 24, 2013 | Permit id: 447944 | |||||
SCORE 100 Relocate recepts, exit signs, furniture feeds and instalkl energy efficient lights, down lights, 2x4 lights and a pendant. All work done in accordance with 2008 nec(commercial)(cc dist) Date: December 10, 2012 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: May 4, 2013 | Permit id: 442623 | |||||
SCORE 100 Level ii alterations include moving of partitions and doors for office space. Date: April 7, 2014 Contractor: Henkels And Mc Coy Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: May 14, 2014 | Permit id: 525767 | |||||
SCORE 100 Fast form building permit Date: September 4, 2008 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit status: Completed | Completion date: October 28, 2008 | Permit id: 175063 | |||||
SCORE 95 Relocate existing telecommunications points (44) and install new cabling for telecommunications points (23) longest 3 per 2008 nec. Installation to comply with articles 300. 21 & 8 of the 2008 nec. Date: April 4, 2014 Contractor: Tangent Cable Systems Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: January 6, 2015 | Permit id: 520686 | |||||
SCORE 100 Relocate 7 diffusers - office bldg Date: February 28, 2014 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 16, 2015 | Permit id: 521796 | |||||
SCORE 100 Relocate (32) existing sprinkler heads in order to accommodate tenant fitout as per all nfpa no. 13 and local codes. Date: March 12, 2014 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: May 1, 2014 | Permit id: 523977 | |||||
SCORE 100 12- 2x4 fixtures, 2-switches, 2-exit sts, 7-duplex recpt & 2-120v circuits connect to existing 2 amp panel as per nec 2008 (comm) Date: January 22, 2013 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: May 4, 2013 | Permit id: 449349 | |||||
SCORE 99 Hotworks: welding cutting soldering torch work - permit expires 5 08 2014. Frank bldg engineer 267-515-3130 Date: May 8, 2013 Contractor: Herman Goldner Co. Inc Client: Hub Properties Trust | Permit type: Operations permit | Permit status: Completed | Permit id: 22309 | |||||
SCORE 100 Add 1-new fire panel & 6-stobe & 3-speaker as per nec 2008 & nfpa 72 cc district Date: April 15, 2015 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: April 15, 2015 | Permit id: 594607 | |||||
SCORE 100 Relocate existing sprinkler heads (commercial) Date: October 11, 2017 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Active | Completion date: November 1, 2017 | Permit id: 823279 | |||||
SCORE 100 Erection of a sidewalk shelter platform as per engineered plans. Streets department permit is required for sidewalk closure prior to the start work. Date: October 24, 2017 Contractor: Superior Scaffold Services Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Active | Completion date: November 14, 2017 | Permit id: 826322 | |||||
SCORE 100 Replacement only of 8- lavatories in existing locations Date: November 23, 2015 Contractor: Nagellavin Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: February 13, 2016 | Permit id: 653573 | |||||
SCORE 100 Relocate (8) sprinkler heads to accommodate tenant layout as per all nfpa no. 13 and local codes. Date: December 2, 2015 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: March 24, 2016 | Permit id: 655442 | |||||
SCORE 100 Install 25 new 2 x 2 fixtures in place of old install (2) exits (replace old) (1) new switch (2) exhaust fan, power furnish (8) 2 x 2 fixtures for building stock in kind with no additional wiring as per 2008 nec (cc district) Date: December 3, 2015 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: December 3, 2015 | Permit id: 655686 | |||||
SCORE 100 Relocate 2 fixtures,1 switch,furnish and install 4 new duplex and 4 data voice 125ft per 2008 nec (office space) Date: December 23, 2014 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: February 1, 2016 | Permit id: 581295 | |||||
SCORE 100 Level ii interior alterations (no change in occupancy) to existing office space on the 16th floor of an existing high-rise office building as per approved plans. Separate permits required for any mep or fire suppression work Date: December 4, 2014 Contractor: Commercial Construction Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: January 14, 2015 | Permit id: 575801 | |||||
SCORE 100 Relocate (6) sprinkler heads in order to accommodate tenant fitout as per all nfpa no. 13 and local codes. Date: June 20, 2013 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 478704 | |||||
SCORE 100 For mechanical alterations including new registers diffuers, air handling units and associated ductwork as per approved plans. Date: February 17, 2015 Contractor: Tracey Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 13, 2016 | Permit id: 583816 | |||||
SCORE 100 Interior demo of non load bearing walls. Date: January 28, 2015 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: March 10, 2015 | Permit id: 586918 | |||||
SCORE 96 Level ii interior alterations (no change of occupancy) for renovations to existing 4th, 6th, 7th & 8th floor offices within an existing high-rise building as per approved plans. Existing building fully sprinklered. Separate permits required for any mep or fire suppression work Date: August 24, 2017 Contractor: Intech Construction Llc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Active | Completion date: October 24, 2017 | Permit id: 797208 | |||||
SCORE 95 Installation and termination of new voice and data cabling for new furniture configuration cabling to be plenum rated Date: April 5, 2017 Contractor: Tangent Cable Systems Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: April 5, 2017 | Permit id: 772522 | |||||
SCORE 100 Relocate 19 sprinkler heads Date: August 24, 2010 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 295935 | |||||
SCORE 95 1 a v signal power supply, 1 addressable control module, 4 addressable relay modules, 13 speaker strobes & 3 strobes. Date: August 26, 2010 Contractor: Hatzel And Buehler Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: March 17, 2011 | Permit id: 292506 | |||||
SCORE 100 32 relocate lighting, 2 - 2x2 lay in fixtures, 8 duplex recepts, 29 quad recepts, 7 furniture system feeds as per 2005 nec (cc district) relocate 2 fire alarm devices Date: September 1, 2010 Contractor: Metro Electric Co Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: January 19, 2011 | Permit id: 295005 | |||||
SCORE 99 Hotworks: welding cutting soldering torch work - permit expires 05 22 2014. Date: May 22, 2013 Contractor: Herman Goldner Co. Inc Client: Hub Properties Trust | Permit type: Operations permit | Permit status: Completed | Permit id: 22344 | |||||
SCORE 96 Alterations to existing hvac system to accomodate new office layouts on the 4th, 6th, 7th & 8th floors of an existing high-rise building as per approved plans. Date: August 24, 2017 Contractor: Intech Construction Llc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Active | Completion date: September 11, 2017 | Permit id: 801050 | |||||
SCORE 95 Furnish and install power and lighting throughout as per 2008 nec Date: July 15, 2010 Contractor: Hatzel And Buehler Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: March 17, 2011 | Permit id: 285052 | |||||
SCORE 99 Furnish and install vav boxes, heat pumps, duct and air devices for new office layout. Date: August 2, 2010 Contractor: Hunter Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: September 14, 2010 | Permit id: 285461 | |||||
SCORE 100 Furnish and install 2 new ups systems 2 panels 12 power strips @ traders desk. Install (200)2x2s and 15 downlights and ceiling wall motion sensors per 2008 nec (office space)cc district Date: May 10, 2017 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: July 5, 2017 | Permit id: 769351 | |||||
SCORE 100 Interior fit out to office bldg including demolition of existing office space and application of new finishes. Date: November 5, 2010 Contractor: Commercial Construction Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: January 21, 2011 | Permit id: 309309 | |||||
SCORE 100 Interior demo of an existing office space Date: November 16, 2010 Contractor: Lakash Constructors Inc Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: December 6, 2010 | Permit id: 311859 | |||||
SCORE 100 Install lighting,switching,power and electric service,relocate existing,fire alarm devices per attached plans, no tel data,as per 2008 nec Date: November 24, 2010 Contractor: Mcgoldrick Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: February 25, 2011 | Permit id: 310942 | |||||
SCORE 100 Install new lighting, switches, power outlets, 39 teledata drops with cat6 cable. Utilize existing electrical service as is as per nec 2008 cc district & fire alarm as per nfpa 72 Date: January 12, 2017 Contractor: Mcgoldrick Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: January 12, 2017 | Permit id: 741357 | |||||
SCORE 100 Interior renovations as per plans Date: April 11, 2008 Contractor: Lakash Constructors Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: November 5, 2008 | Permit id: 143032 | |||||
SCORE 100 Install cat 5e plenum wire to phone data outlets as per 2005 nec (cc district) Date: December 19, 2007 Contractor: New Line Communications Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: September 3, 2013 | Permit id: 112838 | |||||
SCORE 86 Relocate 22 existing 2x4 fixtures, relocate 1 existing panel within 25 ft, relocate old system furniture power 4 circuits, add 15 new duplex recepts, and connect to old furniture power, add 6 new light switches, as per 2005 nec (cc dist) Date: April 10, 2008 Contractor: Timothy Moran Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: August 29, 2008 | Permit id: 144582 | |||||
SCORE 86 Install new and reuse existing tele data circuits in 8th floor tenet fit out area (cc dist) Date: July 19, 2007 Contractor: Lee Burkey Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: January 27, 2009 | Permit id: 85443 | |||||
SCORE 100 Relocate existing grds. Reprogram bldg automatic system Date: January 18, 2017 Contractor: Herman Goldner Co Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: January 24, 2017 | Permit id: 752467 | |||||
SCORE 100 Relocate 2x4s,2 exit lights, receptacles,2 switches,install 2 ceilinging motion sensors,4 waal motion sensors change existing recptacles and wall plates as per 2008 nec Date: March 16, 2011 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: April 27, 2011 | Permit id: 330011 | |||||
SCORE 100 Int demo of non bearing walls and carpet only. Date: March 8, 2011 Contractor: Mj Settelen Construction Llc Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: May 7, 2014 | Permit id: 328677 | |||||
SCORE 100 Relocate 9 existing sprinkler heads(commercial) Date: March 22, 2011 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: April 25, 2011 | Permit id: 331041 | |||||
SCORE 100 For interior alterations to a partial area, suite 501 of an existing highrise building. All work shall comply with the approved plans. Date: December 1, 2010 Contractor: Lakash Constructors Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: December 20, 2010 | Permit id: 312354 | |||||
SCORE 100 Interior alteration as per plans Date: June 11, 2009 Contractor: Dlauro And Rodgers Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: December 14, 2009 | Permit id: 219705 | |||||
SCORE 100 Fast form building permit Date: January 5, 2009 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit status: Completed | Completion date: March 31, 2009 | Permit id: 195246 | |||||
SCORE 100 Relocate 3 diffusers Date: January 9, 2009 Contractor: Elliott Lewis Corporation Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 22, 2009 | Permit id: 196049 | |||||
SCORE 100 1 new floor recepts, 4 new exit lights, 6 - 2x2 relocate and re wire, 4 duplex recept, re-activate 5 existing floor power feeds and 1 new switch as per 2005 nec (cc district) Date: January 8, 2009 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: December 7, 2009 | Permit id: 195830 | |||||
SCORE 100 Hvac including ductwork and mechanical equipment as per plans. 85 diffusers Date: August 24, 2015 Contractor: Terrell Enterprises Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 9, 2015 | Permit id: 630754 | |||||
SCORE 99 For level ii alterations to existing hvac system on the 14th floor of an existing building, alterations to include replacement of registers, diffusers, and mechanical equipment with associated duct work. All work to be done per approved plans. Separate permits required for electrical work. Date: July 1, 2014 Contractor: Hunter Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: July 25, 2014 | Permit id: 539641 | |||||
SCORE 100 Furnish & install (51) category 6 plenum cables, longest run 85. Installation to comply with articles 300. 21 & 8 of the 2008 nec. Date: September 24, 2013 Contractor: Gt Telecom Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: October 30, 2013 | Permit id: 490712 | |||||
SCORE 100 Relocate 15 existing sprinkler heads (commercial) Date: October 8, 2015 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: November 30, 2015 | Permit id: 644024 | |||||
SCORE 100 Level ii alterations to 15th floor common area as per plan. Date: November 24, 2015 Contractor: Commercial Construction Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: April 14, 2016 | Permit id: 650512 | |||||
SCORE 100 Relocating 22 sprinklers in the common areas on the 15th floor-ez permit sprinkler relocation (nfpa 13)- for the relocation of sprinkler heads as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: November 18, 2015 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: April 14, 2016 | Permit id: 652992 | |||||
SCORE 100 Remove & replace 14-lighting, 4-3-way switches, 2-tv power recepts & 1-floor recept as per nec 2008 (office bldg) Date: September 16, 2014 Contractor: Metro Electric Co Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: October 30, 2014 | Permit id: 562067 | |||||
SCORE 100 Furnish & install 43-cat5e plenum cables for voice & data as per nec 2008 cc district Date: August 3, 2016 Contractor: Gt Telecom Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: August 3, 2016 | Permit id: 698501 | |||||
SCORE 100 Installation of a kitchen sink Date: September 17, 2013 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 16, 2013 | Permit id: 494112 | |||||
SCORE 100 No change in use and occupancy classification. Interior alterations as per approved plans. Date: October 28, 2013 Contractor: Dlauro And Rodgers Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: August 14, 2014 | Permit id: 494182 | |||||
SCORE 100 Remove and replace (12) lavs and (4)urinals with new fixtures.. No additional piping Date: September 17, 2013 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 5, 2013 | Permit id: 494421 | |||||
SCORE 100 Add 1 switch,1 light fixture for new handicap bath change 26 fixtures to new energy efficient 2x2s per 2008 nec (office space) Date: September 16, 2013 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: April 30, 2014 | Permit id: 494797 | |||||
SCORE 100 Relocate (20) diffusers. Date: August 24, 2010 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 297737 | |||||
SCORE 100 39- 2 x 4 lighting to relamp, 1 - 2 x 2 to relocate, 28 - duplex receps.,4 furniture feeds (wall), 42 - tel data (box & string), 68-2 x 4 to relocate, 1 - 2 x 2 to relocate, 29 - quad receps, 01-furniture feed (floor), 10-new 2 x 4 layin, 18-switches, 20-ne downlights, 3-exit lights, 1-poke thru floor recep. (cc dist) Date: June 20, 2007 Contractor: Metro Electric Co Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: November 27, 2007 | Permit id: 83394 | |||||
SCORE 100 Relocate (75) existing sprinkler heads in order to accommodate tenant layouts as per nfpa no. 13 and all local codes. Date: January 3, 2017 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: July 28, 2017 | Permit id: 747444 | |||||
SCORE 100 Furnish and install temporary wire and lights north side only per 2008 nec(office space)cc district Date: December 16, 2016 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: December 16, 2016 | Permit id: 744104 | |||||
For the installation of a mechanical system to include ductwork, registers diffusers, and vavs as per approved plans. Separate permit required for any plumbing and electrical work. Date: January 19, 2017 Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: July 5, 2017 | Permit id: 748236 | |||||
SCORE 77 Interior alterations (no change in use and occupancy classification) to fit-out office space on the 26th floor of an existing high-rise office building as per approved plans. Existing building fully sprinklered separate permits required for any mep or fire suppression work Date: December 20, 2016 Contractor: Sci Construction Group Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: August 19, 2017 | Permit id: 743572 | |||||
SCORE 100 For level ii alterations: office fit-out of tenant space on the 33rd floor, all non-structural work as shown on plans application, space used as previously approved business & professional offices. Separate permit is required for electrical, plumbing and mechanical work Date: November 9, 2016 Contractor: Commercial Construction Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: January 24, 2017 | Permit id: 732608 | |||||
SCORE 100 Relocate (3) diffusers Date: November 18, 2010 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 20, 2010 | Permit id: 312400 | |||||
SCORE 100 Shelter platform permit- erection of a sidewalk shelter platform as per engineered plans. Streets department permit required for sidewalk closure prior to the start of work. Date: June 27, 2016 Contractor: Superior Scaffold Services Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: July 23, 2016 | Permit id: 703020 | |||||
SCORE 100 Demo of non-bearing walls, ceilings and floor finishes. No structural changes. Must maintain all code required fire rating on wall and floor ceiling assemblies. Contractor with a valid conractors license to perform work in the city of philadelphia is required to be listed on this permit. Subject to job being stopped if no contractor information is provided prior to next inspection. No exceptions Date: July 24, 2013 Contractor: Sullivan Company The Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: August 30, 2013 | Permit id: 485078 | |||||
SCORE 100 Install 24-cat 5e utp cables for voice & data applications. All cables will be supported w j kook assemblies, installation to comply with articles 300. 21, 300. 22 & 8 of the 2008 nec. (office bldg) Date: August 14, 2014 Contractor: Gordon Group Electric Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: August 19, 2016 | Permit id: 555839 | |||||
SCORE 100 Level ii altaretaions for tenant fit out as per plans. Separate permit is required for electrical, plumbing and mechanical work Date: July 12, 2016 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: September 2, 2016 | Permit id: 700918 | |||||
SCORE 95 Furnish & install lighting, receptacles and occupancy sensors as per plans & spec & per 2008 nec (office space) Date: October 2, 2015 Contractor: Hatzel And Buehler Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: December 29, 2015 | Permit id: 634957 | |||||
SCORE 100 Add 6-fire alarm devices, 4-wall mounted strobe lights & 2-ceiling mounted speakers as per nfpa 72 (office space)cc district Date: June 4, 2015 Contractor: Metro Electric Co Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: June 4, 2015 | Permit id: 611560 | |||||
SCORE 100 Relocate 2 fixtures furnish and install 2 fixtures furnish and install 2 switchs 4 receptacles 2 rough in voice datas Date: May 27, 2015 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: September 5, 2015 | Permit id: 612911 | |||||
Level ii interior alterations (no change of occupancy) to existing business office suite 9 on the 9th floor of an existing high rise building as per approved plans. Existing building fully sprinklered. Separate permits required for any mep or fire suppression work Date: July 1, 2015 Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: September 29, 2015 | Permit id: 618580 | |||||
SCORE 99 For level ii alterations to existing mechanical system to include the demolition installation of registers, diffusers and mechanical equipment with associated ductwork. All work to be done on the 26th floor of an existing building. All work to be done per approved plans. If field conditions vary contact design engineer prior to the start of any work. Separate permits required for all other work. Date: February 24, 2015 Contractor: Hunter Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 14, 2015 | Permit id: 590369 | |||||
SCORE 100 Furnish and install 3panels,1transformer,110new fixtures,9exit lights,49duplex recepts,14occupancy sensors,22switches and 7furniture feeds as per 2008 nec (cc district) Date: February 19, 2015 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: October 24, 2015 | Permit id: 586830 | |||||
SCORE 100 Relocate 31 sprinkler heads. (commerical) Date: January 29, 2015 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: April 14, 2015 | Permit id: 587434 | |||||
SCORE 100 Demo of existing recept wiring at 14 locations,re-use wiring from demo install recepts at 5 locations,relocate sws at 7 locations, relocate existing ltg at 14 locations,install new exit lt at 2 locations as per 2005 nec,relocate fa device at 1 location, per nfpa-72(cc dist) Date: June 18, 2009 Contractor: Metro Electric Co Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: December 17, 2009 | Permit id: 222143 | |||||
SCORE 100 Construction of new partitions, patching acoustical ceilings, new glass wall, install new doors and frames. Date: January 8, 2009 Contractor: Sullivan Company The Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: June 22, 2009 | Permit id: 195051 | |||||
SCORE 100 Relocation of existing sprinkler heads. Fit-out-33rd floor drucker & scaccetti Date: June 25, 2010 Contractor: Independence Fire Sprinkler Co Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: January 21, 2011 | Permit id: 287562 | |||||
SCORE 100 Install new double inteior preaction system to accomodate sever data room as per nfpa 13. Date: June 24, 2010 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: June 27, 2010 | Permit id: 285957 | |||||
SCORE 100 Relocate (12) sprinkler heads. Date: April 22, 2015 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: July 15, 2015 | Permit id: 604783 | |||||
SCORE 100 Relocate 19 diffusers ez permit ductwork & warm-air appliances- for the installation of new ductwork, registers grilles diffusers, and warm-air appliances as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: April 23, 2015 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: July 15, 2015 | Permit id: 604947 | |||||
SCORE 100 Relocate 7 down lights,remove and replace 162x4 lighting, 4 switches, relocate 1 exit light, 1 f and i exit light, 1 poke thru floor recap, receptacles, 5 wiremold plugmold raceways, 1 tv receptacle all work to comply with 2008 nec Date: April 30, 2015 Contractor: Metro Electric Co Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: November 3, 2015 | Permit id: 606925 | |||||
SCORE 95 7 relocated 2by2 fixture 2 occuppancy sensors 2 duplex recetacles Date: September 24, 2010 Contractor: Hatzel And Buehler Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: August 1, 2012 | Permit id: 302772 | |||||
SCORE 100 Relocate (3) sprinklers on 25th fl of bldg. Date: September 14, 2010 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: March 29, 2011 | Permit id: 301120 | |||||
Interior alterations (no change in use and occupancy classification) to fit-out office space on the 21st floor of an existing high-rise office building as per approved plans. Existing building fully sprinklered separate permits required for any mep or fire suppression work Date: January 19, 2017 Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: July 1, 2017 | Permit id: 744611 | |||||
SCORE 100 Demolition,relocate 30-2x4s,8-wall mounts,1-exit,add 27-duplex and 2-furniture power connects all new to existing 225 amp panel as per 2008 nec (cc district) Date: August 16, 2016 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: September 2, 2016 | Permit id: 707339 | |||||
SCORE 100 Remove and replace 3-exterior wall mounted light fixtures, supply and install 1-exterior wall mounted light fixtures provide power connecto to new motorized door as per nec 2008 cc district Date: August 1, 2016 Contractor: Lyndee Corporation Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: June 27, 2017 | Permit id: 711322 | |||||
SCORE 100 Install 35- cat 6 plenum data cable to existing data rock, longest run 305 ft. Terminate cabling in data rack in closet. Test and label all new station cabling to match existing. Support all new cabling per code. Work in accordance with 2008 nec Date: August 5, 2016 Contractor: Bluestone Communications Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: August 22, 2017 | Permit id: 711847 | |||||
SCORE 100 Fast form building permit Date: May 17, 2007 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit status: Active | Completion date: May 17, 2007 | Permit id: 76716 | |||||
SCORE 100 Relocation of (30) diffusers for office bldg. Date: November 9, 2010 Contractor: Ramm Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: January 21, 2011 | Permit id: 310689 | |||||
SCORE 99 Install (1) sink waste line at new proposed location, connection to existing piping below. Install (1) new sink and faucet Date: November 8, 2010 Contractor: Stanley Rajauski Jr Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 6, 2011 | Permit id: 310517 | |||||
SCORE 100 Relocating 2 sprinklers on the 28th floor of pnc bank. Date: February 12, 2015 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: February 24, 2015 | Permit id: 590332 | |||||
SCORE 100 Partial demolition and level ii interior alterations including new non-load bearing partitions and finishes throughout an existing tenant space in the southeast portion of the 15th floor. Separate permits required for any mechanical, electrical, plumbing and fire suppression work. Date: September 5, 2013 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: November 29, 2013 | Permit id: 491483 | |||||
SCORE 100 Relocation of 1 sprinkler on 39th floor ez permit sprinkler relocation (nfpa 13)- for the relocation of sprinkler heads as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans Date: September 4, 2015 Contractor: Independence Fire Sprinkler Co Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: December 9, 2015 | Permit id: 636949 | |||||
SCORE 100 Relocate 9 existing sprinkler heads (commercial) Date: August 12, 2016 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: September 14, 2016 | Permit id: 714566 | |||||
SCORE 100 Install (4) temporary light fixture in lower level vacant space power from existing 277v power supply (project date 8 15 16-11 15 16) per 2008 nec (commercial) Date: August 12, 2016 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: August 12, 2016 | Permit id: 714431 | |||||
SCORE 100 Furnish and install (1)sink - connect to existing services Date: August 15, 2011 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: August 10, 2013 | Permit id: 357819 | |||||
SCORE 100 Relocate 6 sprinkler heads (ground floor - wanamaker tickets) Date: September 16, 2011 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: December 13, 2011 | Permit id: 363688 | |||||
SCORE 100 Relocate existing sprinkler heads to conform with new floor and ceiling layout on floors 4,6,7 and 8. Date: October 5, 2017 Contractor: Precision Sprinkler Services Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Active | Completion date: October 26, 2017 | Permit id: 818080 | |||||
SCORE 100 Install 2- kitchen sinks for coffee stations. All sanitary and domestic water connections to existing stacks and riser Date: October 10, 2017 Contractor: E J Raith Mechanical Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Active | Completion date: October 31, 2017 | Permit id: 820039 | |||||
SCORE 100 Relocate (25) diffusers, to comply with ez permit standards for ductwork Date: September 29, 2017 Contractor: Ramm Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 20, 2017 | Permit id: 820168 | |||||
SCORE 100 Install horizontial plenum rated cat5 telcom cabling from (8) wall outlets to closets for a longest run of 80ft. As per 2008 nec (cc district) Date: September 29, 2017 Contractor: E J Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Active | Completion date: September 29, 2017 | Permit id: 820234 | |||||
SCORE 95 Install receptacles poke thrus furniture feeds lights and lighting controls nec 2008 telcom average cable length 225 total cable 475 plenum rated cat 5e cable total coax cables 25 rg-6 plenum rated all cables will terminate in on existing existing termination points existing tr on each floor all cable will be tested with dsx fluke Date: November 10, 2017 Contractor: Hatzel And Buehler Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Active | Completion date: November 10, 2017 | Permit id: 822928 | |||||
SCORE 100 Fast form building permit Date: April 24, 2008 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit status: Active | Completion date: April 24, 2008 | Permit id: 147789 | |||||
SCORE 100 Relocate 5 diffusers registers - 15th floor (frank crystal office) Date: April 15, 2008 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 2, 2014 | Permit id: 145399 | |||||
SCORE 100 Fixture installation Date: May 1, 2008 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 1, 2009 | Permit id: 149180 | |||||
SCORE 100 Installation of (5) logo signs including 2 building logo signs at sky line of high rise as per sealed drawings Date: August 6, 2008 Contractor: Philadelphia Sign Company Client: Hub Properties Trust | Permit type: Sign permit | Permit status: Completed | Completion date: May 22, 2009 | Permit id: 150780 | |||||
SCORE 100 Installation of signs Date: July 24, 2008 Contractor: Philadelphia Sign Company Client: Hub Properties Trust | Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 24, 2008 | Permit id: 150779 | |||||
SCORE 100 Install 31 triplex cat6 plenum communication outlets. Longest run 1 (cc dist) Date: May 16, 2008 Contractor: New Line Communications Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: August 29, 2008 | Permit id: 151338 | |||||
SCORE 76 Add high hats and kitchen under cabinet lighting - install owner supplied lighting fixtures - mc cable, as per 2005 nec (cc dist) Date: July 2, 2008 Contractor: Harris David J Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: March 23, 2010 | Permit id: 162355 | |||||
SCORE 100 Interior demolition of non bearing partitions Date: August 14, 2008 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: February 5, 2009 | Permit id: 171205 | |||||
SCORE 100 Expansion of existing office space as per plan. Date: August 20, 2008 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: November 5, 2008 | Permit id: 171208 | |||||
SCORE 100 Interior alterations fit-out of existing office space. Date: July 18, 2011 Contractor: Lakash Constructors Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: March 13, 2012 | Permit id: 351544 | |||||
SCORE 100 Relocate 6 sprinkler heads (28th floor) Date: July 20, 2011 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 353903 | |||||
SCORE 100 Relocate and relamp 45 fixtures,1 new exit, 13 new motion switches, wall,3 floor recptacles, 2 wall furniture feeds, 6 quad receptacles, duplex receptacles, 4 fire devices relocate existing. No anticapted load change as per 2008 nec Date: August 17, 2011 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: October 7, 2011 | Permit id: 354313 | |||||
SCORE 100 Ez permit ductwork & warm-air appliances - for the installation of new ductwork, registers grilles diffusers, and warm-air appliances as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: July 6, 2016 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: September 14, 2016 | Permit id: 704971 | |||||
SCORE 100 43 lights, 29 duplexes, 2 quardruplexes, 4 exit signs as per 2005 nec (cc dist) Date: November 17, 2008 Contractor: Henkels And Mc Coy Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: November 17, 2008 | Permit id: 183110 | |||||
SCORE 100 Interior renovations. Tenant fit-out. Permit to include the installation of non combustible partitions to create additional office space in an existing b use. Additional permits required for; plumbing,electrical, hvac, and fire suppression. Date: October 29, 2008 Contractor: Henkels And Mc Coy Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: January 8, 2009 | Permit id: 183090 | |||||
SCORE 99 Fast form building permit Date: August 29, 2008 Contractor: Hunter Mechanical Inc Client: Hub Properties Trust | Permit status: Completed | Completion date: October 28, 2008 | Permit id: 174243 | |||||
SCORE 100 Interior alterations to the 9th and 21st floors as per plans. Date: May 19, 2010 Contractor: Dlauro And Rodgers Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 278007 | |||||
Interior fit-out Date: June 18, 2010 Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: September 14, 2010 | Permit id: 279451 | |||||
SCORE 100 Install 8 locations consisting of 2 catse plenum cables - install 3 card readers locations conisting of composite cable - all locations to be fire stopped - per 2008 nec Date: August 5, 2011 Contractor: Lanconnect Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: November 30, 2011 | Permit id: 356854 | |||||
SCORE 100 Relocate (39) diffusers registers tenant (pnc bank) Date: May 23, 2007 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 78117 | |||||
SCORE 100 Relocate (12) existing sprinkler heads in order to accommodate tenant layouts as per nfpa no. 13 and all local codes. Date: January 24, 2017 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: July 5, 2017 | Permit id: 754062 | |||||
SCORE 100 Ez permit ductwork & warm-air appliances- for the installation of new ductwork, registers grilles diffusers, and warm-air appliances as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: January 25, 2017 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 27, 2017 | Permit id: 754185 | |||||
SCORE 100 Add 2 gfi devices in kitchen, 2 copier receptacles and2 general receptacles per 2008 nec (office space)cc district Date: February 16, 2016 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: March 15, 2016 | Permit id: 669934 | |||||
SCORE 100 Exterior alterations, renovations, upgrades of existing plaza area, drains, concrete work, planters, etc facade door upgrades, as per specs and plans. Within lot lines. Date: June 28, 2016 Contractor: Clemens Construction Co Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: November 27, 2017 | Permit id: 687151 | |||||
SCORE 100 Ez interior demolition- for the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Interior demolition work of non bearing walls on lower level 1 Date: July 6, 2016 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: April 17, 2017 | Permit id: 705145 | |||||
SCORE 95 Furnish & install (1) nac panel power supply, (2) smoke detectors, ( relay modules for door release, (18) speaker strobes & (8) strobes as per nfpa 72 Date: October 27, 2015 Contractor: Hatzel And Buehler Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: February 24, 2016 | Permit id: 640565 | |||||
SCORE 100 Remove old incandescent down lgts & install energy eff 25-2x2 fixtures & replace 6-wall fixtures, reuse existing circuits as per nec 2008 (office bldg) Date: February 18, 2014 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: May 21, 2014 | Permit id: 519812 | |||||
SCORE 100 Relocate 8 existing sprinkler heads (commercial) Date: August 3, 2016 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: February 23, 2017 | Permit id: 712139 | |||||
SCORE 100 Ez interior demolition- for the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: October 2, 2015 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: May 4, 2016 | Permit id: 642545 | |||||
SCORE 100 Renovation to existing corridor and restrooms including new finishes and new ada restroom as per plans. Date: June 11, 2010 Contractor: Commercial Construction Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: September 14, 2010 | Permit id: 283185 | |||||
SCORE 100 Hvac included ductwork as per plans Date: May 6, 2010 Contractor: Cms Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 27, 2010 | Permit id: 276464 | |||||
SCORE 100 Relocate (2) receptacles, (4) fixtures, add (1) exit light, re-circuit (1) room and add (2) switches as per 2008 nec (cc dist) Date: May 4, 2010 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: August 3, 2010 | Permit id: 276852 | |||||
SCORE 100 Ez interior demolition- for the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: November 30, 2016 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: January 24, 2017 | Permit id: 740028 | |||||
SCORE 100 Install new lavatory, water and sanitary lines Date: November 2, 2016 Contractor: Nagellavin Inc Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 24, 2017 | Permit id: 733154 | |||||
SCORE 100 Relocate (31) existing sprinkler heads in order to accommodate tenant layouts as per nfpa no. 13 and all local codes. Date: November 8, 2016 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: January 24, 2017 | Permit id: 735222 | |||||
SCORE 100 Ez permit sprinkler relocation (nfpa 13)- for the relocation of sprinkler heads as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: January 25, 2017 Contractor: Oliver Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: February 27, 2017 | Permit id: 754268 | |||||
SCORE 100 Install kitchen sink and 1- point of use water heater- connect to existing sanitary and domestic water Date: July 13, 2016 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 16, 2016 | Permit id: 705668 | |||||
SCORE 100 Interior renovations to the conference room, to include demo of non-bearing partition and millwork and repair concrete floor and install new gwb on existing partition as per plans. Separate permits required for mechanical, electrical and fire suppression. Date: July 16, 2014 Contractor: Dlauro And Rodgers Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: March 10, 2015 | Permit id: 548053 | |||||
For interior renovation of common area on the 25th floor of an existing office building as per plans, separate permits required for mechanical, electrical, plumbing, and fire suppression systems. Date: October 4, 2017 Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Active | Completion date: November 17, 2017 | Permit id: 802280 | |||||
SCORE 100 Level ii alteration as per plans. Date: February 12, 2014 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: May 14, 2014 | Permit id: 518165 | |||||
SCORE 95 New & relocated voice data cabling for offices, furniture cubicles & 1-conference room as per nec 2008. Installation to comply with articles 300. 21, 300. 22 & 8 of the 2008 nec. Date: June 11, 2014 Contractor: Tangent Cable Systems Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: June 11, 2014 | Permit id: 531617 | |||||
SCORE 100 Relocate (10) diffusers, to comply with ez permit standards for ductwork ez permit ductwork & warm-air appliances- for the installation of new ductwork, registers grilles diffusers, and warm-air appliances as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: May 19, 2016 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: July 6, 2016 | Permit id: 693273 | |||||
SCORE 100 8 ceiling mounted fire alarm speakers, 7 wall mounted fire alarm strobe lights, 1 system test and certification by wfi delmarva (cc dist) Date: July 12, 2007 Contractor: Metro Electric Co Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: November 27, 2007 | Permit id: 87590 | |||||
Interior demolition of non load bearing walls, miscellaneous interior renovations of existing office space, new interior walls and finishes as per plans. Additional permits are required for electrical, plumbing, hvac and supression. Date: August 6, 2013 Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: September 30, 2013 | Permit id: 485885 | |||||
SCORE 100 For level ii alterations to the 26th floor of an existing building for use as a business occupancy. Alterations to include the erection of partition walls, provide finishes and furnishings. All work to be done per approved plans. Building to be fully sprinklered. If field conditions vary contact design professional prior to the start of any work. Separate permits required for mechanical, electrical, and fire suppression work. Date: May 21, 2015 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: July 1, 2015 | Permit id: 608766 | |||||
SCORE 100 Level ii interior alterations (no change of occupancy) for fitout to existing unoccupied suite within an existing high-rise building as per approved plans. Existing building fully sprinklered. Separate permits required for any mep or fire suppression work Date: August 11, 2017 Contractor: Commercial Construction Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: October 20, 2017 | Permit id: 804889 | |||||
SCORE 99 Install duct,1 fan and relocate 19 diffusers as per plans. Date: December 23, 2008 Contractor: Hunter Mechanical Inc Client: Hub Properties Trust | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 22, 2009 | Permit id: 189090 | |||||
Use as a cafeteria for pnc. Bank Date: January 26, 2010 Client: Hub Properties Trust | Permit type: Use permit | Permit status: Completed | Completion date: January 26, 2010 | Permit id: 258987 | |||||
SCORE 98 Interior alterations on 27th floor as per plans. Date: April 21, 2010 Contractor: Patriot Construction Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: June 27, 2010 | Permit id: 270506 | |||||
SCORE 100 Interior non-bearing demolition - 27th floor Date: March 31, 2010 Contractor: Cippco Contracting Inc Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: June 27, 2010 | Permit id: 269109 | |||||
SCORE 100 Level ii interior alterations (no change in occupancy) to fit-out office space on the 26th floor of an existing high-rise office building as per approved plans. Existing building fully sprinklered separate permits required for any mep or fire suppression work Date: February 6, 2015 Contractor: Haas Peters Construction Group Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: April 18, 2015 | Permit id: 586388 | |||||
SCORE 100 Relocate (9) existing sprinkler heads on 17th floor. Date: December 12, 2012 Contractor: A And S Sprinkler Co Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: April 1, 2013 | Permit id: 443032 | |||||
SCORE 100 Adding new corridor doorways, renovating reception area, new base paint & ceiling work. Date: August 20, 2010 Contractor: Structure Tone,Inc Client: Hub Properties Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: March 29, 2011 | Permit id: 296374 | |||||
SCORE 100 Ez interior demolition-selective demolition relocations 15th & 18th floor unoccupied tenant suites. For the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: April 19, 2017 Contractor: Commercial Construction Inc Client: Hub Properties Trust | Permit type: Demolition permit | Permit status: Completed | Completion date: May 30, 2017 | Permit id: 770683 | |||||
SCORE 100 Relocation of sprinkler heads Date: November 22, 2010 Contractor: Independence Fire Sprinkler Co Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: December 20, 2010 | Permit id: 312984 | |||||
SCORE 100 Furnish and install 147 new cat6 plenum rated data cables with a longest run of 255ft,all cabling will be as per articles 300. 21, 300. 22 & 8 of the 2008 nec. Date: March 18, 2015 Contractor: Bluestone Communications Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: March 20, 2017 | Permit id: 592074 | |||||
SCORE 100 Remove existing down light (12) and replace with new remove existing 2x2s (20) and replace with 5-linear, add 4-motion sensors and relocate (15) 2x2s, remove old furniture power and connect 10-new duplex as per 2008 nec (cc district) Date: September 27, 2017 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: October 19, 2017 | Permit id: 808327 | |||||
SCORE 100 Fixture installation Date: November 14, 2008 Contractor: John Uebele Jr Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 21, 2009 | Permit id: 187397 | |||||
SCORE 100 Relocate 14 sprinkler heads on the 18th floor Date: December 3, 2008 Contractor: Fire Protection Industries Inc Client: Hub Properties Trust | Permit type: Suppression permit | Permit status: Completed | Completion date: January 8, 2009 | Permit id: 190922 | |||||
SCORE 95 Installation of plenum rated cat 5e cable for (23)telecommunications outlets - the installation will comply with the 2008 nec Date: May 15, 2015 Contractor: Tangent Cable Systems Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Expired | Completion date: May 15, 2015 | Permit id: 610482 | |||||
SCORE 100 Installation of (1)ada water closet and (1) ada lavatory Date: September 17, 2013 Contractor: Lormar Mechanical Services Client: Hub Properties Trust | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 5, 2013 | Permit id: 494943 | |||||
SCORE 100 Amend building permit # 494182 for minor interior alterations to the 3rd, 11th, & 29th floor as per approved plans. Date: December 4, 2013 Contractor: Dlauro And Rodgers Inc Client: Hub Properties Trust | Permit type: Administrative permit | Permit status: Completed | Completion date: August 14, 2014 | Permit id: 505348 | |||||
SCORE 100 Installation of a 1 amp 120 208 volt service to feed clearwire cabinet only as per 2005 nec (cc district) Date: January 8, 2010 Contractor: Mjk Electrical Corporation Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: August 3, 2010 | Permit id: 256459 | |||||
SCORE 100 Replace existing corridor lights in mens and ladies rooms with new leds and reconnect to existing circuits,furnish and install 1-new switch and light in ada bathroom as per 2008 nec (cc district) Date: December 8, 2017 Contractor: New Light Electric Inc Client: Hub Properties Trust | Permit type: Electrical permit | Permit status: Active | Completion date: December 8, 2017 | Permit id: 828671 |