Mechanical permit Date: April 20, 2010 Client: Ramesh Reddi | Permit status: Completed | Permit id: 273918 | |||||
Plumbing permit Date: April 21, 2010 Client: Ramesh Reddi | Permit status: Completed | Permit id: 274152 | |||||
Zoning/use permit Date: January 26, 2010 Client: Ramesh Reddi | Permit status: Completed | Permit id: 247864 | |||||
Plumbing permit Date: January 10, 2008 Client: Ramesh Reddi | Permit status: Completed | Permit id: 125619 | |||||
New construction permit Date: March 4, 2010 Client: Ramesh Reddi | Permit status: Completed | Permit id: 261896 | |||||
Electrical permit Date: June 22, 2010 Client: Ramesh Reddi | Permit status: Completed | Permit id: 286888 | |||||
Permit for the erection of a three (3) story detached structure not to exceed 35 high with cellar, bay at 2nd and 3rd floor front and side (completely outside the property line) for use as a single family dwelling. Date: December 11, 2009 Client: Ramesh Reddi | Applicant: Hercules Grigos, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: January 28, 2010 | Permit id: 10651 | |||||
Plumbing permit Date: January 10, 2008 Client: Ramesh Reddi | Permit status: Completed | Permit id: 125619 | |||||
New construction permit Date: March 4, 2010 Client: Ramesh Reddi | Permit status: Completed | Permit id: 261896 | |||||
Plumbing permit Date: April 21, 2010 Client: Ramesh Reddi | Permit status: Completed | Permit id: 274152 | |||||
Zoning use permit Date: January 26, 2010 Client: Ramesh Reddi | Permit status: Completed | Permit id: 247864 | |||||
Mechanical permit Date: April 20, 2010 Client: Ramesh Reddi | Permit status: Completed | Permit id: 273918 | |||||
Electrical permit Date: June 22, 2010 Client: Ramesh Reddi | Permit status: Completed | Permit id: 286888 | |||||
Permit for the erection of a three (3) story detached structure not to exceed 35 high with cellar, bay at 2nd and 3rd floor front and side (completely outside the property line) for use as a single family dwelling. Date: December 11, 2009 Client: Ramesh Reddi | Applicant: Hercules Grigos, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: January 28, 2010 | Permit id: 10651 | |||||
New construction of 3 story structure, associated site work, excavation to be assessed by engineer as per attached letter. No underpinning of adjacent structures proposed or approved by this office. Date: March 4, 2010 Client: Ramesh Reddi | Permit type: New construction permit | Permit status: Completed | Completion date: October 20, 2010 | Permit id: 261896 | |||||
SCORE 100 Replace existing fixtures, no piping. (3) bathrooms & (3) kitchens. New yard drain Date: January 10, 2008 Contractor: Alfred Rossi Sr Client: Ramesh Reddi | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 14, 2008 | Permit id: 125619 | |||||
SCORE 99 Sewer water,service Date: April 13, 2010 Contractor: Keith Klein Client: Ramesh Reddi | Permit type: Plumbing permit | Permit status: Completed | Completion date: April 16, 2010 | Permit id: 272361 | |||||
SCORE 100 Install 200a service install 25 circuits total, install 45 outlets install switches, install 15 lights install 8 120v smoke detectors, install 2 phone cable jacks as per 2008 nec (south dist) Date: June 22, 2010 Contractor: Sean Kearns Client: Ramesh Reddi | Permit type: Electrical permit | Permit status: Completed | Completion date: October 27, 2010 | Permit id: 286888 | |||||
SCORE 100 To install house drain waste line, 2 toilets, 2 lav, 2 tub,1 laundry tub, 1 kitchen sink,shower, hwh Date: April 21, 2010 Contractor: Garry Dabney Client: Ramesh Reddi | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 2, 2013 | Permit id: 274152 | |||||
SCORE 100 Install 1 hvac unit (sfd) Date: April 20, 2010 Contractor: Talgar Inc Client: Ramesh Reddi | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 20, 2010 | Permit id: 273918 |