Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Electrical Date: April 5, 2013 Client: Hightower Apartments Lp | Applicant: Dieter G Linder | Permit status: Completed | Permit id: E1304314 | |||||
SCORE 82 Electrical Date: April 5, 2013 Contractor: Dieter G Linder Client: Hightower Apartments Lp | Permit status: Completed | Permit id: E1304314 | |||||
SCORE 82 Electrical Date: April 5, 2013 Contractor: Dieter G Linder Client: Hightower Apartments Lp | Permit status: Completed | Permit id: E1304314 | |||||
SCORE 82 Electrical Date: April 5, 2013 Contractor: Dieter G Linder Client: Hightower Apartments Lp | Permit status: Completed | Permit id: E1304314 | |||||
SCORE 56 Level 1 alteration to include removal and replacement of the existing fire alarm panel and associated field devices with a new fire lite alarm panel and field devices. Existing strobes and audible devices will be reused in their existing locations. Existing conduit and wiring will be reused. Power for the new fire alarm control panel shall be provided from the existing 120vac connection. Date: January 25, 2012 Contractor: Hightowers Llc; Sam Hollen Ramco Of Dc Inc Client: Hightowers, Llc | Permit type: Alteration and repair | Permit status: Completed | Permit id: B1202293 | |||||
SCORE 92 Electrical Date: January 30, 2012 Contractor: Wayne O Reep Client: Hightower Apartments Lp | Permit status: Completed | Permit id: E1203059 | |||||
SCORE 93 Plumbing and gas Date: March 12, 2013 Contractor: Donald E. Decarr Client: Hightower Apartments Lp | Permit status: Completed | Permit id: P1303418 | |||||
SCORE 56 Sprint will be adding three antennas, three remote radio units and new three cables. Existing equipment cabinets will be altered. Date: May 13, 2015 Contractor: Hightowers Llc Client: Hightower Apartments Lp | Permit type: Miscellaneous | Permit status: Completed | Permit id: An1400174 | |||||
SCORE 100 Electrical Date: June 15, 2016 Contractor: Ralph Threatt Client: Foundry United Methodist Church | Permit status: Completed | Permit id: E1607266 | |||||
SCORE 96 Mechanical Date: March 11, 2016 Contractor: Christos T Sakkos Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: M1601405 | |||||
SCORE 96 Plumbing and gas Date: March 11, 2016 Contractor: Christos T. Sakkos Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: P1604459 | |||||
SCORE 96 Electrical Date: March 16, 2016 Contractor: Laurence O Humble Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: E1604675 | |||||
SCORE 96 Electrical Date: April 1, 2016 Contractor: Guy Eubanks Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: E1605083 | |||||
SCORE 93 Plumbing and gas Date: May 23, 2016 Contractor: Matt Losignor Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: P1606416 | |||||
SCORE 56 Remove existing 3 panel antennas / install 6 new panel antennas install 1 new equipment cabinet Date: January 26, 2012 Contractor: Hightowers Llc Tim Aco Property Advisors Client: Hightowers Llc | Permit type: Miscellaneous | Permit status: Completed | Permit id: An1200024 | |||||
SCORE 56 The purpose of this application is to revise the previously pulled antenna permit # an1200024. Sprint proposes to install a fiber optic run from the fiber box in the telco room to the wireless facility on the roof. Date: June 21, 2012 Contractor: Hightower Apart C O Peabody Corp William Stone Client: Hightower Apartments Lp Co Peabody Corp | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: An1200226 | |||||
SCORE 93 Plumbing and gas Date: March 12, 2013 Contractor: Donald E. Decarr Client: Hightower Apartments Lp | Permit status: Completed | Permit id: P1303418 | |||||
SCORE 56 Level 1 alteration to include removal and replacement of the existing fire alarm panel and associated field devices with a new fire lite alarm panel and field devices. Existing strobes and audible devices will be reused in their existing locations. Existing conduit and wiring will be reused. Power for the new fire alarm control panel shall be provided from the existing 120vac connection. Date: January 25, 2012 Contractor: Hightowers Llc Sam Hollen Ramco Of Dc Inc Client: Hightowers, Llc | Permit type: Alteration and repair | Permit status: Completed | Permit id: B1202293 | |||||
SCORE 92 Electrical Date: January 30, 2012 Contractor: Wayne O Reep Client: Hightower Apartments Lp | Permit status: Completed | Permit id: E1203059 | |||||
SCORE 100 Electrical Date: June 15, 2016 Contractor: Ralph Threatt Client: Foundry United Methodist Church | Permit status: Completed | Permit id: E1607266 | |||||
SCORE 96 Mechanical Date: March 11, 2016 Contractor: Christos T Sakkos Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: M1601405 | |||||
SCORE 96 Plumbing and gas Date: March 11, 2016 Contractor: Christos T. Sakkos Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: P1604459 | |||||
SCORE 93 Plumbing and gas Date: May 23, 2016 Contractor: Matt Losignor Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: P1606416 | |||||
SCORE 86 This building permit is to revise the existing building permit number b1212844, which should reflect the total number of purposed dwelling units as per the dcra approved plans as 86. The correct total number of dwelling units is 89, three of which were converted at basement level. Date: February 10, 2014 Contractor: Amanda Barley Client: Hightowns Llc | Permit type: Alteration and repair | Permit status: Completed | Permit id: B1404148 | |||||
SCORE 56 The purpose of this application is to revise the previously pulled antenna permit # an1200024. Sprint proposes to install a fiber optic run from the fiber box in the telco room to the wireless facility on the roof. Date: June 21, 2012 Contractor: Hightower Apart C O Peabody Corp; William Stone Client: Hightower Apartments Lp C O Peabody Corp | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: An1200226 | |||||
SCORE 56 Level 1 alteration to include removal and replacement of the existing fire alarm panel and associated field devices with a new fire lite alarm panel and field devices. Existing strobes and audible devices will be reused in their existing locations. Existing conduit and wiring will be reused. Power for the new fire alarm control panel shall be provided from the existing 120vac connection. Date: January 25, 2012 Contractor: Hightowers, Llc; Sam Hollen Ramco Of Dc, Inc Client: Hightowers, Llc | Permit type: Alteration and repair | Permit status: Completed | Permit id: B1202293 | |||||
SCORE 56 Converting existing space into three additional dwelling units. Date: December 27, 2012 Contractor: Elise Shinagawa Client: John Theoharis | Permit type: Alteration and repair | Permit status: Completed | Permit id: B1212844 | |||||
SCORE 56 Replacement in kind of interior wall coverings. Replacement in kind, when applied to architectural features, means replacement with a feature of like material that replicates the existing feature in proportion, appearance, texture, design, detail and dimensions. Date: October 26, 2012 Contractor: Jonathan Boocock Permit type: Building | Permit status: Permit issued | Permit id: Pc97015793 | |||||
SCORE 92 Electrical Date: January 30, 2012 Contractor: Wayne O Reep Client: Hightower Apartments Lp | Permit status: Completed | Permit id: E1203059 | |||||
SCORE 93 Plumbing and gas Date: March 12, 2013 Contractor: Donald E. Decarr Client: Hightower Apartments Lp | Permit status: Completed | Permit id: P1303418 | |||||
SCORE 82 Al hammer foundry united methodist church interior demolition on the lower level and main level as per plans. Date: October 6, 2015 Contractor: Americode Client: Al Hammer Foundry United Methodist Church | Permit type: Demolition | Permit status: Permit issued | Permit id: D1600015 | |||||
SCORE 76 Install 20. 5kw pv system -82panels x 250w- on the roof. Date: November 6, 2015 Contractor: Armen Mkhoyan Greenbrilliance Client: Foundry Church Foundry Church | Permit type: Addition | Permit status: Completed | Permit id: B1513120 | |||||
SCORE 56 Erect access tower scaffold on private property at west elevation of flat roof. Remove existing flat roof membrane and metal flashing on flat roof of addition south of church. Haul debris from premises. Install new flat roof membrane and all new metal flashing where needed. Any structural rafter work to be done by others. All work to remain in kind. No work on pitched roofs visible from the ground. Date: November 16, 2015 Contractor: Alan Zabel With Foundry United Methodist Church Client: Alan Zabel With Foundry United Methodist Church | Permit type: Alteration and repair | Permit status: Permit issued | Permit id: B1601840 | |||||
SCORE 56 Sprint will be adding three antennas, three remote radio units and new three cables. Existing equipment cabinets will be altered. Date: May 13, 2015 Contractor: Hightowers, Llc Client: Hightower Apartments Lp | Permit type: Miscellaneous | Permit status: Completed | Permit id: An1400174 | |||||
SCORE 82 Alteration level two of 9,211 sf of existing church. Reconfiguration and consolidation of spaces in a limited area of the main level including structural, electrical, plumbing, mechanical, av, waterproofing, one new ada compliant 3-stop elevator, new ada toilet rooms and pantry kitchen equipment. Foundry umc renovation Date: March 9, 2016 Contractor: Americode Client: Al Hammer Foundry United Methodist Church | Permit type: Alteration and repair | Permit status: Permit issued | Permit id: B1512446 | |||||
SCORE 56 Foundry umc - permit revision to b-1512446. Lower level kitchen - new double oven, range, hood, refrigerator & freezer to replace the same existing, outdated equipment. New dropped ceiling grid with scrubable ceiling tile and new kitchen-rated 2x4 light fixtures. New hood has new grease exhaust ductwork that travels up through an existing shaft, through the attic and through the roof with an exhaust fan. Make up air is also provided in the kitchen to bring it up to code, also via ductwork through existing shaft and inlet on roof. Gear room l36 due to major piping and ductwork conflicts, door -l24b no longer fit and had to be removed, leaving l24a and the existing door direct to the outside. Upper level elevator shaft and vestibule u new ventilation shaft with fire damper above ceiling with 2 new linear diffusers to provide ventilation to the elevator shaft. Also, structural beam in elevator shaft changed to imbedded angle to provide additional clearance above elevator. Attic & roof ind Date: May 19, 2016 Client: Al Hammer Foundry United Methodist Church. | Permit type: Alteration and repair | Permit status: Permit issued | Permit id: B1606415 | |||||
SCORE 96 Electrical Date: April 1, 2016 Contractor: Guy Eubanks Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: E1605083 | |||||
SCORE 96 Electrical Date: March 16, 2016 Contractor: Laurence O Humble Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: E1604675 | |||||
SCORE 100 Electrical Date: June 15, 2016 Contractor: Ralph Threatt Client: Foundry United Methodist Church | Permit status: Completed | Permit id: E1607266 | |||||
SCORE 93 Plumbing and gas Date: May 23, 2016 Contractor: Matt Losignor Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: P1606416 | |||||
SCORE 96 Plumbing and gas Date: March 11, 2016 Contractor: Christos T. Sakkos Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: P1604459 | |||||
SCORE 96 Mechanical Date: March 11, 2016 Contractor: Christos T Sakkos Client: Foundry United Methodist Church | Permit status: Permit issued | Permit id: M1601405 | |||||
SCORE 56 Remove existing 3 panel antennas / install 6 new panel antennas install 1 new equipment cabinet Date: January 26, 2012 Contractor: Hightowers Llc; Tim Aco Property Advisors Client: Hightowers Llc | Permit type: Miscellaneous | Permit status: Completed | Permit id: An1200024 | |||||
SCORE 82 Foundry methodist church - demo and shoring permit. Work is the structural demolition required to accommodate -1- new/expanded openings in masonry walls, -2- new elevator shaft opening, and -3- shoring of upper level floor and removal of existing columns and beams below. The following departments are going to be involved lower level, main level and upper level, as per plans. Date: January 14, 2016 Contractor: Americode Client: Foundry United Methodist Church. | Permit type: Alteration and repair | Permit status: Permit issued | Permit id: B1603668 | |||||
SCORE 56 This supplemental permit was issued online. Use the online permit view application on dcra intranet to view the details and print a copy of the permit. Alternatively, you can copy and paste the following url into an internet browser. Https:/eservices. Dcra. Dc. Gov/ospi/printpermit. Aspx? Param=zi8iggjeilelubdtrwdlwcdaicwtrgzr Date: October 18, 2016 Client: Foundry United Methodist Church | Permit type: Boiler | Permit status: Permit issued | Permit id: Fb71988348 | |||||
SCORE 95 Type of elevator : one (1) traction/ steel/centrally/vertical transportation(3rd floor) condition : (application for modification of construction code requirements (or variance of flood hazard rules) mvq1600161 /mvq16000162 Date: July 20, 2016 Contractor: Otis Elevator Company Client: Foundry United Methodist Church | Permit type: Elevator - new | Permit status: Permit issued | Permit id: En1602780 | |||||
SCORE 96 Expedited Date: June 28, 2016 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1690776 | |||||
SCORE 96 Expedited Date: June 28, 2016 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1690776 | |||||
SCORE 96 Expedited Date: June 28, 2016 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1690776 |