Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 95 Phase 1 - pcs skids for arrays 24 & 25 Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1210040062 | |||||
SCORE 95 Phase 1 - structural support for modules of arrays 24 & 25 Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1301160064 | |||||
SCORE 77 Perimeter fence Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1306190020 | |||||
SCORE 95 Array 23 - structural suport for modules Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1402060066 | |||||
SCORE 95 Array 22-1 - structural support for modules Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1402060068 | |||||
SCORE 95 Array 22-2 - structural support for modules Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1402060069 | |||||
SCORE 95 Array 26 - structural support for modules Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1402060070 | |||||
SCORE 95 Array 23 - concrete pad for pcs Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1402060071 | |||||
SCORE 95 Array 22-1 - concrete pad for pcs Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1402060072 | |||||
SCORE 95 Array 22-2 - concrete pad for pcs Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1402060073 | |||||
SCORE 95 Array 26 - concrete pad for pcs Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1402060074 | |||||
SCORE 70 Underground duct bank at 3 locations Applicant: Acevedo Andres | Permit status: Finaled | Completion date: June 23, 2015 | Permit id: 1402260064 | |||||
SCORE 95 Phase 1 - arrays 24 & 25 Date: February 24, 2014 Contractor: Rosendin Electric Inc Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1210040067 | |||||
SCORE 95 El for array 26 Date: April 15, 2014 Contractor: Rosendin Electric Inc Applicant: Acevedo Andres | Permit status: Finaled | Completion date: June 23, 2015 | Permit id: 1402060041 | |||||
SCORE 95 El for array 22-2 Date: April 15, 2014 Contractor: Rosendin Electric Inc Applicant: Acevedo Andres | Permit status: Finaled | Completion date: June 23, 2015 | Permit id: 1402060042 | |||||
SCORE 95 El for array 22-1 Date: April 15, 2014 Contractor: Rosendin Electric Inc Applicant: Acevedo Andres | Permit status: Finaled | Completion date: June 23, 2015 | Permit id: 1402060043 | |||||
SCORE 95 El for array 23 Date: April 15, 2014 Contractor: Rosendin Electric Inc Applicant: Acevedo Andres | Permit status: Finaled | Completion date: June 23, 2014 | Permit id: 1402060044 | |||||
SCORE 77 Grading for solar project all phases Date: January 31, 2014 Contractor: M A Mortenson Co Applicant: Acevedo Andres | Permit status: Finaled | Completion date: March 30, 2015 | Permit id: 1401210004 |