SCORE 99 Close sidewalk along 14th (west side of church) during re-roofing project. Date: January 18, 2005 Contractor: Arapahoe Roofing And Sheet Metal Inc Client: Johns St | Applicant: Arapahoe Roofing & Sheet Metal, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Re-roof st. Johns episcopal church with replacement of clay tile on 2:12 pitch (74 squares) and replacement of shake shingles with asphalt on 4:12 pitch (36 squares) and slate on 14:12 pitch (22 squares) Date: December 27, 2004 Contractor: Arapahoe Roofing And Sheet Metal Client: Johns St | Applicant: Arapahoe Roofing & Sheet Metal | Permit type: Roofing | Permit status: Cmp | Completion date: October 10, 2005 | Current use: Religious assem | |||||
SCORE 64 Replacement of a low-pressure boiler (1,832k btu) at st. Johns episcopal church. Date: February 4, 2003 Contractor: Western Steel And Boiler Co Client: Johns St | Applicant: Western Steel & Boiler Co. | Permit type: Mechanical | Permit status: N&v | Current use: Religious assem | |||||
SCORE 73 Fire sprinkler system - existing area Date: November 5, 2002 Contractor: Alliance Fire Systems Inc Client: St Johns Episcopal Church | Applicant: Alliance Fire Systems, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: May 22, 2008 | Current use: Religious assem | |||||
SCORE 100 Crane Date: September 25, 2002 Contractor: Schroeder Roofing Inc Client: Johns St | Applicant: Schroeder Roofing, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 60 Reroof 77 squares of tile roof material on a 12 12 pitch roof, tear off 9 squares of shakes and replace with dimensional shingles on 5 12 pitch roof and coat squares of the bell tower with epoxy fllex. Work to be completed in accordance with the landmark alteration certificate dated 9 24 2002. Client: Johns St | Applicant: Johns St | Permit type: Roofing | Permit status: N&v | Current use: Religious assem | |||||
SCORE 95 Install new transformer Date: September 20, 2002 Contractor: Xcel Client: Johns St | Applicant: Xcel | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Remove & replace existing wall, install structural steel support for new organ pipes to be installed by separate permit. Client: St Johns Episcopal Church | Applicant: Fischer Construction Inc | Permit type: Building, electrical | Permit status: N&v | Current use: Religious assem | |||||
SCORE 97 Fire alarm system Date: August 15, 2002 Contractor: Rose Electric Llc Client: Johns St | Applicant: Rose Electric, Llc | Permit type: Fire | Permit status: Cmp | Completion date: February 3, 2003 | Current use: Religious assem | |||||
SCORE 95 New three stop oildraulic passenger elevator. Date: July 10, 2002 Contractor: Thyssenkrupp Elevator Client: St Johns Episcopal Church | Applicant: Thyssenkrupp Elevator | Permit type: Elevator | Permit status: Cmp | Completion date: March 25, 2003 | Current use: Religious assem | |||||
SCORE 97 Fire alarm system Date: June 10, 2002 Contractor: Rose Electric Llc Client: Johns St | Applicant: Rose Electric, Llc | Permit type: Fire | Permit status: N&v | Current use: Religious assem | |||||
SCORE 73 Fire sprinkler system - st. Johns epsiscopal Date: June 6, 2002 Contractor: Alliance Fire Systems Inc Client: Johns St | Applicant: Alliance Fire Systems, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: January 13, 2003 | Current use: Religious assem | |||||
SCORE 95 Site utilities, curb & gutter, sidewalk Date: May 22, 2002 Contractor: Fischer Construction Inc Client: Johns St | Applicant: Fischer Construction Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Apprx 8,0 sq ft addition and 3,4 sq ft remodel to st. Johns episcopal church. Client: St Johns Episcopal Church | Applicant: Fischer Construction Inc | Permit type: Building, electrical | Permit status: N&v | Current use: Religious assem | |||||
SCORE 97 Kitchen remodel and upgrade existing conference room. (subvaluations added 6 11 2008) Client: Johns St | Applicant: George Weber | Permit type: Building, electrical | Permit status: Cmp | Completion date: November 13, 2008 | Current use: Religious assem | |||||
SCORE 95 Scope of work letter for saint john episcopalian church Date: July 14, 2008 Contractor: Firetrol Protection Systems Client: Johns St | Applicant: Firetrol Protection Systems | Permit type: Fire | Permit status: Iss | Current use: Religious assem | |||||
SCORE 95 Scope of work letter Date: July 18, 2008 Contractor: Firetrol Protection Systems Client: Johns St | Applicant: Firetrol Protection Systems | Permit type: Fire | Permit status: N&v | Current use: Religious assem | |||||
SCORE 59 After-the fact installation of a type i grease hood. Portions of a field review have been done by sd. Date: September 3, 2008 Contractor: Dbm Hvac Client: Johns St | Applicant: Dbm Hvac | Permit type: Mechanical | Permit status: Iss | Current use: Religious assem | |||||
SCORE 71 Restoration of church tower. Need to take parking on pine & on 14th for 3 weeks. Permit extended through july with addfootl crane work on aug. 6 Date: June 4, 2009 Contractor: Building Restoration Specialties Client: Johns St | Applicant: Building Restoration Specialties | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Isolate overhead line for construction need traffic control in alley for 2 days Date: July 7, 2009 Contractor: Xcel Energy Client: Johns St | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 99 Connect roof drains to strom manhole on 14th st. Also will have man lift in row for brick repair. Date: July 6, 2012 Contractor: Ccm Construction Management Inc Client: Johns St | Applicant: Ccm Construction Management Inc | Permit type: Wastewater, right-of | Permit status: Iss | Current use: Religious assem | |||||
SCORE 95 Four new split systems (two 3-ton units ; one 2-ton unit ; one 5-ton unit). 13seer Date: April 12, 2013 Contractor: Control Service Center Inc Client: Johns St | Applicant: Control Service Center Inc | Permit type: Mechanical | Permit status: Cmp | Completion date: February 28, 2014 | Current use: Religious assem | |||||
SCORE 95 Boiler replacement. No exterior work required. Date: August 8, 2013 Contractor: Control Service Center Inc Client: Johns St | Applicant: Control Service Center Inc | Permit type: Mechanical | Permit status: Cmp | Completion date: October 4, 2013 | Current use: Religious assem | |||||
SCORE 56 Occupy row with traffic control devices and lift to repair damaged mortor & joints Date: September 29, 2014 Contractor: Olde English Masonry Inc Client: Johns St | Applicant: Olde English Masonry, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 84 Rewire and replace15 fixtures (9 exterior and 6 interior). See his2014-00372 approval Date: December 10, 2014 Contractor: Diversified Electric And Controls Client: Johns St | Applicant: Diversified Electric & Controls | Permit type: Electrical | Permit status: Cmp | Completion date: March 19, 2015 | Current use: Religious assem | |||||
SCORE 95 Installation of 25. 29 kw, rooftop, grid-tied, photovoltaic, solar energy system on st johnfoots episcopal church. Flush mounted arrays on northeastern portion of building, ballast mounted, low pitch arrays to be installed in southeastern central portion s of non-historic portions of building. Client: Johns St | Permit type: Photovoltaic | Permit status: Cmp | Completion date: February 16, 2016 | Current use: Religious assembly, existing | Permit id: Pmt2016-00141 | |||||
Isolate overhead line for construction need traffic control in alley for 2 days Date: July 7, 2009 Client: Johns St | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2009-02442 | |||||
SCORE 95 Four new split systems (two 3-ton units ; one 2-ton unit ; one 5-ton unit). 13seer Client: Johns St | Permit type: Mechanical | Permit status: Cmp | Completion date: February 28, 2014 | Current use: Religious assembly, existing | Permit id: Pmt2013-01559 | |||||
SCORE 95 Boiler replacement. No exterior work required. Client: Johns St | Permit type: Mechanical | Permit status: Cmp | Completion date: October 4, 2013 | Current use: Religious assembly, existing | Permit id: Pmt2013-03843 | |||||
SCORE 95 Apprx 8,0 sq ft addition and 3,4 sq ft remodel to st. Johnfoots episcopal church. Client: St Johns Episcopal Church | Permit type: Building, electrical, mechanical, plumbing, water, wastewater, sitework | Permit status: N&v | Current use: Religious assembly, addition and remodel | Permit id: Pmt2001-04719 | |||||
SCORE 60 Occupy row with traffic control devices and lift to repair damaged mortor & joints Date: September 29, 2014 Contractor: Olde English Masonry, Inc Client: Johns St | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2014-04425 | |||||
SCORE 84 Rewire and replace15 fixtures (9 exterior and 6 interior). See his2014-00372 approval Client: Johns St | Permit type: Electrical | Permit status: Cmp | Completion date: March 19, 2015 | Current use: Religious assembly, existing | Permit id: Pmt2014-05500 | |||||
SCORE 99 Close sidewalk along 14th (west side of church) during re-roofing project. Date: January 18, 2005 Contractor: Arapahoe Roofing And Sheet Metal, Inc Client: Johns St | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2005-00170 | |||||
SCORE 95 Scope of work letter for saint john episcopalian church Client: Johns St | Permit type: Fire | Permit status: Iss | Current use: Religious assembly, existing | Permit id: Pmt2008-02941 | |||||
SCORE 100 Crane Date: September 25, 2002 Contractor: Schroeder Roofing, Inc Client: Johns St | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2002-04208 | |||||
SCORE 84 Electrical permit to replace existing lighting and mounting rack at north alter window adjacent to the alley. See adr2015-00261 for lighting variance. Client: Johns St | Permit type: Electrical | Permit status: Iss | Current use: Religious assembly, existing | Permit id: Pmt2015-04854 | |||||
SCORE 73 Fire sprinkler system - st. Johns epsiscopal Client: Johns St | Permit type: Fire | Permit status: Cmp | Completion date: January 13, 2003 | Current use: Religious assembly, existing | Permit id: Pmt2002-02308 | |||||
SCORE 95 Fire alarm system Value: $8,000 Contractor: Rose Electric, Llc Client: Johns St | Permit type: Fire | Permit status: N&v | Current use: Religious assembly, existing | Permit id: Pmt2002-02404 | |||||
SCORE 95 New three stop oildraulic passenger elevator. Client: St Johns Episcopal Church | Permit type: Elevator | Permit status: Cmp | Completion date: March 25, 2003 | Current use: Religious assembly, existing | Permit id: Pmt2002-02844 | |||||
SCORE 95 Fire alarm system Client: Johns St | Permit type: Fire | Permit status: Cmp | Completion date: February 3, 2003 | Current use: Religious assembly, existing | Permit id: Pmt2002-03504 | |||||
SCORE 95 Remove & replace existing wall, install structural steel support for new organ pipes to be installed by separate permit. Client: St Johns Episcopal Church | Permit type: Building, electrical | Permit status: N&v | Current use: Religious assembly, remodel | Permit id: Pmt2002-03571 | |||||
SCORE 100 Reroof 77 squares of tile roof material on a 12 12 pitch roof, tear off 9 squares of shakes and replace with dimensional shingles on 5 12 pitch roof and coat squares of the bell tower with epoxy fllex. Work to be completed in accordance with the landmark alteration certificate dated 9 24 2002. Client: Johns St | Permit type: Roofing | Permit status: N&v | Current use: Religious assembly, existing | Permit id: Pmt2002-04199 | |||||
SCORE 73 Fire sprinkler system - existing area Client: St Johns Episcopal Church | Permit type: Fire | Permit status: Cmp | Completion date: May 22, 2008 | Current use: Religious assembly, existing | Permit id: Pmt2002-04808 | |||||
SCORE 64 Replacement of a low-pressure boiler (1,832k btu) at st. Johnfoots episcopal church. Client: Johns St | Permit type: Mechanical | Permit status: N&v | Current use: Religious assembly, existing | Permit id: Pmt2003-00389 | |||||
SCORE 100 Re-roof st. Johnfoots episcopal church with replacement of clay tile on 2:12 pitch (74 squares) and replacement of shake shingles with asphalt on 4:12 pitch (36 squares) and slate on 14:12 pitch (22 squares) Client: Johns St | Permit type: Roofing | Permit status: Cmp | Completion date: October 10, 2005 | Current use: Religious assembly, existing | Permit id: Pmt2004-04861 | |||||
SCORE 100 Kitchen remodel and upgrade existing conference room. (subvaluations added 6 11 2008) Client: Johns St | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: November 13, 2008 | Current use: Religious assembly, remodel | Permit id: Pmt2008-01956 | |||||
SCORE 95 Scope of work letter Value: $600 Contractor: Firetrol Protection Systems Client: Johns St | Permit type: Fire | Permit status: N&v | Current use: Religious assembly, existing | Permit id: Pmt2008-03063 | |||||
SCORE 59 After-the fact installation of a type i grease hood. Portions of a field review have been done by sd. Client: Johns St | Permit type: Mechanical | Permit status: Iss | Current use: Religious assembly, existing | Permit id: Pmt2008-03843 |