New construction permit Date: January 27, 2012 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 382275 | |||||
Electrical permit Date: April 12, 2012 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 398934 | |||||
Mechanical permit Date: March 16, 2012 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 394035 | |||||
Plumbing permit Date: March 20, 2012 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 394604 | |||||
Suppression permit Date: May 23, 2012 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 398452 | |||||
Zoning/use permit Date: December 1, 2011 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 349816 | |||||
Permit for the erection of a three story detached structure not to exceed 35 high with cellar, roof deck on the second floor rear roof with a 42" high protective railing, a roof deck on the third floor roof, setback 8 from the front property line with a 42" high protective railing and a pilot house (48 sq. Ft. And 86" high), and one accessory open air parking space 9x18. Date: August 3, 2011 Client: Hoffman Virginia A Rainey Robert W Iii | Applicant: Eli Gabay, Esquire | Permit type: Appeal | Permit status: Granted/prov | Completion date: October 21, 2011 | Permit id: 15803 | |||||
Electrical permit Date: April 12, 2012 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 398934 | |||||
New construction permit Date: January 27, 2012 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 382275 | |||||
Zoning use permit Date: December 1, 2016 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 737714 | |||||
Zoning use permit Date: December 1, 2011 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 349816 | |||||
Addition permit Date: January 3, 2017 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Active | Permit id: 743218 | |||||
Suppression permit Date: May 23, 2012 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 398452 | |||||
Mechanical permit Date: March 16, 2012 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 394035 | |||||
Alteration permit Date: November 17, 2016 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Active | Permit id: 737648 | |||||
Plumbing permit Date: March 20, 2012 Client: Hoffman Virginia A Rainey Robert W Iii | Permit status: Completed | Permit id: 394604 | |||||
Permit for the erection of a three story detached structure not to exceed 35 high with cellar, roof deck on the second floor rear roof with a 42" high protective railing, a roof deck on the third floor roof, setback 8 from the front property line with a 42" high protective railing and a pilot house (48 sq. Ft. And 86" high), and one accessory open air parking space 9x18. Date: August 3, 2011 Client: Hoffman Virginia A Rainey Robert W Iii | Applicant: Eli Gabay, Esquire | Permit type: Appeal | Permit status: Granted/prov | Completion date: October 21, 2011 | Permit id: 15803 | |||||
SCORE 100 Install new 90% gas fired furnace, install new a c coil and condenser,and related ductwork supply and returns ducts Date: March 16, 2012 Contractor: Christopher G. Long Client: Stablefish Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: July 31, 2012 | Permit id: 394035 | |||||
SCORE 100 Install 2-3 piece bathrooms, 1 kit, 1 waswher, 2 sinks, 2 tubs, 2 wc, 1 ks, 1 washer, and 1 floor drain(sfd) Date: March 20, 2012 Contractor: Jp Builder And Management Llc Client: Stablefish Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 31, 2012 | Permit id: 394604 | |||||
SCORE 100 Installation of a nfpa 13d (rfss) fire suppression system in a 1 family dwelling - 1" feed main, 1" rise, 1" cross main, 1" branch lines. Date: May 23, 2012 Contractor: Elite Fire Protection Client: Stablefish Llc | Permit type: Suppression permit | Permit status: Completed | Completion date: July 31, 2012 | Permit id: 398452 | |||||
SCORE 72 Addition: interior plumbing; roof deck;3 story structure; mixed use commercial use of first floor & 2 residential units above; drain and water supply lines for 3 toilets,3 vanities,2 tubs,2 kitchens,2 washer and water heaters - the installation will comply with the philadephia plubming code 2004 Date: November 7, 2017 Contractor: Dela Cruz Construction Client: Stablefish Llc | Permit type: Plumbing permit | Permit status: Active | Completion date: November 21, 2017 | Permit id: 826640 | |||||
SCORE 100 Install 4 ton air handler with 4 ton heat pump in basement with related duct workt Date: October 20, 2017 Contractor: Milmar Hvac Client: Stablefish Llc | Permit type: Mechanical permit | Permit status: Active | Completion date: November 21, 2017 | Permit id: 824319 | |||||
SCORE 100 Install 500amp service w grounding,install (1)2 amp panel in commercial and (2)150amp panels,(1)1 amp house panel and wire w recepts,switches,lights,fixtures,smokes and co detectors as per 2008 nec (east district) install complete fire alarm system with pullstations,horns,strobes,horn strobes,panel and lights as per nfpa72 Date: October 26, 2017 Contractor: L Moore Electric Inc Client: Stablefish Llc | Permit type: Electrical permit | Permit status: Active | Completion date: October 26, 2017 | Permit id: 815554 | |||||
SCORE 100 For the installation of a nfpa 13 (first floor) and nfpa 13r (throughout) system serviced by a two inch fire service line with a back flow preventer assembly. Fire suppression system to be installed for a commercial space on the basement first floor level and residential above. All work to be done per approved plans. If field conditions vary contact design engineer prior to the start of any work. Fire supression system to be installed in accordance with a nfpa 13 & 13r standard. Separate permits required for all other work. Date: September 11, 2017 Contractor: B. M. Consulting Services Inc Client: Stablefish Llc | Permit type: Suppression permit | Permit status: Active | Completion date: November 21, 2017 | Permit id: 804598 | |||||
SCORE 87 Interior demolition of non load bearing walls and flooring, installation of interior partition walls, repair replacement of stucco, and roof repairs-ez permit stadard alterations- for alterations to an existing one family dwelling as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: November 17, 2016 Contractor: Urban Core Inc Client: Stablefish Llc | Permit type: Alteration permit | Permit status: Active | Completion date: August 9, 2017 | Permit id: 737648 | |||||
SCORE 87 Foundation only for new front addition as part of renovation addition to an existing building as per approved plans. Separate permit required for alterations and addition work Date: January 3, 2017 Contractor: Urban Core Inc Client: Stablefish Llc | Permit type: Addition permit | Permit status: Completed | Completion date: November 24, 2017 | Permit id: 743218 | |||||
For the erection of an addition, roof deck access structure, roof deck, interior alterations, and all other work as per approved plans. Entire bulding to be fully sprinklered. Separate permit required for any mep work and fire suppression work. Date: July 18, 2017 Client: Stablefish Llc | Permit type: Addition permit | Permit status: Active | Completion date: November 22, 2017 | Permit id: 784625 | |||||
Renovation addition to existing sfd to convert into mixed use building with commercial use of first floor and basement and 2 residential units above. The addition includes he construction of a 3 story to match the existing floor levels in the front out to the sidewalk an addition at the rear of the 3rd floor to match the rear wall at the second and 1st floor. Date: December 1, 2016 Client: Stablefish Llc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: December 1, 2016 | Permit id: 737714 | |||||
SCORE 100 6 21 12 payment mailed in; recd 6 13 12(ams) erection of a 3 story detached fully sprinkled 13d single family dwelling with cellar and deck on 2nd floor rear roof, deck on third floor roof with pilot house per submitted plan. No parking. No garage. Separate permits required for electric; plumbing; mechanical and sprinkler system. Date: January 27, 2012 Contractor: Lawndale Construction Mgmt Llc Client: Stablefish Llc | Permit type: New construction permit | Permit status: Completed | Completion date: July 31, 2012 | Permit id: 382275 | |||||
SCORE 100 New construction of a new 3 story dwelling with cellar with 3rd floor roof deck and optional roof deck with pilot house; lots on either side, new driveway and curb cut to be sfd. Elimination of an alley on the south side of property Date: December 1, 2011 Contractor: Lawndale Construction Mgmt Llc Client: Stablefish Llc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: December 1, 2011 | Permit id: 349816 | |||||
SCORE 98 Install 2 amp service and wiring throughout as per 2008 nec Date: April 12, 2012 Contractor: David Bell Client: Stablefish Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: August 10, 2012 | Permit id: 398934 |