Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Alteration permit Date: July 3, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 407177 | |||||
Mechanical permit Date: October 23, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 428959 | |||||
Administrative permit Date: February 25, 2013 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 454053 | |||||
Administrative permit Date: March 25, 2015 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 598287 | |||||
Suppression permit Date: March 13, 2013 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 438405 | |||||
Administrative permit Date: November 30, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 439616 | |||||
Zoning permit Date: May 24, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 351437 | |||||
Electrical permit Date: November 9, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 431977 | |||||
Electrical permit Date: August 20, 2013 Client: Ranlud Associates Llc | Permit status: Expired | Permit id: 468484 | |||||
Alteration permit Date: March 27, 2013 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 449294 | |||||
Plumbing permit Date: October 31, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 434013 | |||||
Electrical permit Date: August 20, 2013 Client: Ranlud Associates Llc | Permit status: Expired | Permit id: 468484 | |||||
Mechanical permit Date: October 23, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 428959 | |||||
Administrative permit Date: March 25, 2015 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 598287 | |||||
Alteration permit Date: March 27, 2013 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 449294 | |||||
Administrative permit Date: February 25, 2013 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 454053 | |||||
Electrical permit Date: November 9, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 431977 | |||||
Zoning permit Date: May 24, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 351437 | |||||
Administrative permit Date: November 30, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 439616 | |||||
Suppression permit Date: March 13, 2013 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 438405 | |||||
Alteration permit Date: July 3, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 407177 | |||||
Plumbing permit Date: October 31, 2012 Client: Ranlud Associates Llc | Permit status: Completed | Permit id: 434013 | |||||
SCORE 89 Install recepts, switches, outlets and 5 hvac units. All work done in accordance with 2008 nec. No fa, communication or electrical service on this permit. Installation to comply with article 210. 8(b)(2). Date: November 9, 2012 Contractor: Del Val Structures Client: Ranlud Associates Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: December 4, 2014 | Permit id: 431977 | |||||
SCORE 100 Install 6 ceremonial hs,9 floor drains,3 ms,1 hs,1-3 compartment,6 lav,6 wc,1 urinal,1 water heater(water to fixtures) (comm ctr office bldg) Date: October 31, 2012 Contractor: James Mc Dermott Client: Ranlud Associates Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 27, 2015 | Permit id: 434013 | |||||
SCORE 100 Installation of new fire pump, backflow assembly, standpipe to roof and tie into existing standpipe. Installation of new sprinkler system for basement, 1st and 2nd floors assembly fire area. Nfpa 13, 6" fire service line. Partial building sprinklered. Date: March 13, 2013 Contractor: Mac Sprinkler Inc Client: Ranlud Associates Llc | Permit type: Suppression permit | Permit status: Completed | Completion date: August 13, 2015 | Permit id: 438405 | |||||
SCORE 89 Amend permit #407177 for reconfiguration of plans for basement-community center as per sealed submiteed revised plans. Call the inspector prior to making changes. Date: November 30, 2012 Contractor: Del Val Structures Client: Ranlud Associates Llc | Permit type: Administrative permit | Permit status: Completed | Completion date: November 4, 2014 | Permit id: 439616 | |||||
SCORE 89 Level existing floor and create new bearing for existing beam by installing beam header and new joists and reinforce existing masonry wall as per plans. Date: March 27, 2013 Contractor: Del Val Structures Client: Ranlud Associates Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: January 2, 2014 | Permit id: 449294 | |||||
SCORE 89 Revise amend prior permit ap407177. Show new fire barrier separation of 2nd floor to upper floors creating 2 separate fire areas as per plan and performance testing submittal, revise basement layout. Building partially sprinklered only basement, 1st and 2nd floors(see sprinker permit ap438405. Amend to change contractor. New co and lo, also indicating sprinkler locations. Additional permits req: electrical, plumbing, hvac, sprinklers. Date: February 25, 2013 Contractor: Del Val Structures Client: Ranlud Associates Llc | Permit type: Administrative permit | Permit status: Completed | Completion date: November 4, 2014 | Permit id: 454053 | |||||
SCORE 96 Revise permit number 428959 to include basement system. Date: May 21, 2013 Contractor: Dzo Mechanical Inc Client: Ranlud Associates Llc | Permit type: Administrative permit | Permit status: Completed | Completion date: October 23, 2014 | Permit id: 462134 | |||||
SCORE 89 Provide electrical distrib and fixtures in bsmt area for storage bathrooms kitchens fire pump lights and power. Install components for new 3 phase power svc to bldg as per 2008 nec (community ctr) Date: August 20, 2013 Contractor: Del Val Structures Client: Ranlud Associates Llc | Permit type: Electrical permit | Permit status: Expired | Completion date: August 20, 2013 | Permit id: 468484 | |||||
SCORE 89 Day t. C. O. For 2nd floor Date: March 25, 2015 Contractor: Del Val Structures Client: Ranlud Associates Llc | Permit type: Administrative permit | Permit status: Completed | Completion date: March 26, 2015 | Permit id: 598287 | |||||
SCORE 96 Install multiple ductwork system, mechanicals, registers diffusers Date: October 23, 2012 Contractor: Dzo Mechanical Inc Client: Ranlud Associates Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 6, 2014 | Permit id: 428959 | |||||
SCORE 89 Rennovations to an existing office building to create a new community center as per submitted sealed plans. Fire rated assemblies are required to be maintained at all times. Plumbing, electrical, mechanical, and fire suppression work requires additional permits. Call the inspector prior to starting work. Date: July 3, 2012 Contractor: Del Val Structures Client: Ranlud Associates Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: August 7, 2015 | Permit id: 407177 | |||||
Consolidating 2 lots into one (1), changing use from office space to community center and adding 1st floor entrance, vestibule, pergola & decorative fencing along 20th street houseline. Date: May 24, 2012 Client: Ranlud Associates Llc | Permit type: Zoning permit | Permit status: Completed | Completion date: May 24, 2012 | Permit id: 351437 |