SCORE 86 New conduit run approximately 429 - going east on the north side of lee hill Date: June 6, 2003 Contractor: Utilx Corporation Client: Authority Housing | Applicant: Utilx Corporation | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Construction of a new 12,414 sf mixed use building, 5486 sf group residential, 4354 sf administrative offices and remainder sf storage area. New offices and transitional housing for boulder housing partners. See adr2006-00053 for minor mod to increase floor area of east building. Client: Authority Housing | Applicant: C C M Construction Management | Permit type: Building, electrical | Permit status: Co | Current use: Motel/hotel/bed | |||||
SCORE 95 New wall fence. Concrete masonry steel. 2 linear feet Date: August 22, 2007 Contractor: C C M Construction Management Client: Authority Housing | Applicant: C C M Construction Management | Permit type: Fence | Permit status: Cmp | Completion date: April 15, 2008 | Current use: Government uses | |||||
SCORE 95 Install 11 2" meter pit, 3 4" irrigation meter pit, 5 type r inlet & 65 of 12" pvc Date: July 18, 2007 Contractor: Valley Excavating Inc Client: Authority Housing | Applicant: Valley Excavating Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 320ft bore along the north side of lee hill rd plus 35ft of backhoe located at the sw corner of the intersection of lee hill rd and broadway. Traffic control 5 days. Job no. 10984833 Date: August 8, 2007 Contractor: Xcel Energy Client: Authority Housing | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Sprinkler system boulder housing partners Date: August 10, 2007 Contractor: Freedom Fire Protection. Llc Client: Authority Housing | Applicant: Freedom Fire Protection. Llc | Permit type: Fire | Permit status: Cls | Current use: Single family a | |||||
SCORE 100 Install gas service to serve new office building- bore across lee hill rd., pothole existing utilities and 6x4 bell hole at gas main location Date: September 11, 2007 Contractor: Xcel Energy Client: Authority Housing | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Tennan finish fire alarm boulder housing project Date: October 22, 2007 Contractor: Safe Systems Inc Client: Authority Housing | Applicant: Safe Systems, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: May 15, 2008 | Current use: Single family a | |||||
SCORE 95 Hood suppression system Date: December 3, 2007 Contractor: Sentry Fire And Safety Client: Authority Housing | Applicant: Sentry Fire And Safety | Permit type: Fire | Permit status: N&v | Current use: Multifamily dwe | |||||
SCORE 96 Installation of a tilt-up grid-tie photovoltaic array, 4 kw. Date: February 20, 2008 Contractor: Ben Jamin Electric Inc Client: Authority Housing | Applicant: Ben Jamin Electric Inc. | Permit type: Photovoltaic | Permit status: Cmp | Completion date: May 2, 2008 | Current use: Multifamily dwe | |||||
SCORE 95 Class i hood -- plan review done & fees already paid under pmt2006-04452 Date: March 6, 2008 Contractor: Meyers Heating And A C Client: Authority Housing | Applicant: Meyers Heating And A/c | Permit type: Mechanical | Permit status: Cmp | Completion date: June 12, 2008 | Current use: Government uses | |||||
SCORE 100 Remove replace damaged curb, drivepan and ada ramp Date: April 25, 2008 Contractor: Willmark Enterprises Inc Client: Authority Housing | Applicant: Willmark Enterprises, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
Place new hh at ped 48 trench 4foot to intercept duct going to ped on broadway. Place new hh at ped 1325 trench 4foot to intercept cbo. Pull fiber from 48 to address. Job 140512 Date: October 28, 2016 Client: Authority Housing | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2016-04975 | |||||
SCORE 95 Remove replace damaged curb, drivepan and ada ramp Date: April 25, 2008 Contractor: Willmark Enterprises, Inc Client: Authority Housing | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2008-01585 | |||||
320ft bore along the north side of lee hill rd plus 35ft of backhoe located at the sw corner of the intersection of lee hill rd and broadway. Traffic control 5 days. Job no. 10984833 Date: August 8, 2007 Client: Authority Housing | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2007-03232 | |||||
Install gas service to serve new office building- bore across lee hill rd., pothole existing utilities and 6x4 bell hole at gas main location Date: September 11, 2007 Client: Authority Housing | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2007-03815 | |||||
SCORE 86 New conduit run approximately 429foot - going east on the north side of lee hill Date: June 6, 2003 Contractor: Utilx Corporation Client: Authority Housing | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2003-01995 | |||||
SCORE 95 Construction of a new 12,414 sf mixed use building, 5486 sf group residential, 4354 sf administrative offices and remainder sf storage area. New offices and transitional housing for boulder housing partners. See adr2006-00053 for minor mod to increase floor area of east building. Client: Authority Housing | Permit type: Building, electrical, mechanical, plumbing, elevator, water, wastewater | Permit status: Co | Current use: Motel/hotel/bed & breakfast, new | Permit id: Pmt2006-04452 | |||||
SCORE 95 New wall fence. Concrete masonry steel. 2 linear feet Client: Authority Housing | Permit type: Fence | Permit status: Cmp | Completion date: April 15, 2008 | Current use: Government uses, existing | Permit id: Pmt2007-01428 | |||||
SCORE 95 Install 11 2inch meter pit, 3 4inch irrigation meter pit, 5foot type r inlet & 65foot of 12inch pvc Date: July 18, 2007 Contractor: Valley Excavating Inc Client: Authority Housing | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2007-02995 | |||||
SCORE 95 Sprinkler system boulder housing partners Client: Authority Housing | Permit type: Fire | Permit status: Cls | Current use: Single family attached dwelling, existin | Permit id: Pmt2007-03411 | |||||
Install gas service to serve new office building- bore across lee hill rd., pothole existing utilities and 6footx4foot bell hole at gas main location Date: September 11, 2007 Client: Authority Housing | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2007-03815 | |||||
SCORE 95 Tennan finish fire alarm boulder housing project Client: Authority Housing | Permit type: Fire | Permit status: Cmp | Completion date: May 15, 2008 | Current use: Single family attached dwelling, existin | Permit id: Pmt2007-04638 | |||||
SCORE 95 Hood suppression system Value: $1,660 Contractor: Sentry Fire And Safety Client: Authority Housing | Permit type: Fire | Permit status: N&v | Current use: Multifamily dwellings, existing | Permit id: Pmt2007-05347 | |||||
SCORE 96 Installation of a tilt-up grid-tie photovoltaic array, 4 kw. Client: Authority Housing | Permit type: Photovoltaic | Permit status: Cmp | Completion date: May 2, 2008 | Current use: Multifamily dwellings | Permit id: Pmt2008-00611 |