SCORE 89 Us cellular data center - restroom Permit type: Plans required - commercial remodel existing space | Permit status: Issued | Permit id: Bld-15-10701 | |||||
Add light fixture, switch and gfi receptacle. Date: December 14, 2015 Permit type: Commercial electrical | Permit status: Issued | Permit id: Elc-15-10990 | |||||
SCORE 95 Date: September 12, 2006 Contractor: Patrick Killeen Permit status: Issued | Permit id: Elc-06-23857 | |||||
Install new urinal Date: November 20, 2015 Permit type: Commercial plumbing | Permit status: Issued | Permit id: Plb-15-07750 | |||||
Job #20745 cm - 10343 military replace rtu Date: June 27, 2016 Permit type: Commercial electrical | Permit status: Issued | Permit id: Elc-16-05477 | |||||