Mechanical permit Date: May 31, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 408051 | |||||
Electrical permit Date: October 5, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 431284 | |||||
Plumbing permit Date: September 17, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 427688 | |||||
Zoning/use permit Date: April 30, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 398504 | |||||
New construction permit Date: May 31, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 405697 | |||||
Suppression permit Date: September 13, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 425796 | |||||
Zoning/use permit Date: August 1, 2008 Client: Golhar Abhay M | Permit status: Completed | Permit id: 165550 | |||||
Plumbing permit Date: September 24, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 428833 | |||||
Suppression permit Date: September 13, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 425796 | |||||
Mechanical permit Date: May 31, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 408051 | |||||
Electrical permit Date: October 5, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 431284 | |||||
New construction permit Date: May 31, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 405697 | |||||
Zoning use permit Date: April 30, 2012 Client: Golhar Abhay M | Permit status: Completed | Permit id: 398504 | |||||
Zoning use permit Date: August 1, 2008 Client: Golhar Abhay M | Permit status: Completed | Permit id: 165550 | |||||
SCORE 99 Install 1 hvac unit (sfd) Date: May 31, 2012 Contractor: David Mercado Client: Golhar Abhay M | Permit type: Mechanical permit | Permit status: Completed | Completion date: March 4, 2013 | Permit id: 408051 | |||||
SCORE 100 Install new fire suppression system in accordance with nfpa 13d throughout the entire building. All work shall comply with the approved plans. All work shall be performed by a fire suppression contractor licensed by the city of philadelphia. Date: September 13, 2012 Contractor: Brothers Mechanical Client: Golhar Abhay M | Permit type: Suppression permit | Permit status: Completed | Completion date: March 4, 2013 | Permit id: 425796 | |||||
Vacant to 3 story sfd with cellar Date: August 1, 2008 Client: Golhar Abhay M | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 1, 2008 | Permit id: 165550 | |||||
New construction of a 3 story wood framed sfd with flat roof and full cellar with rooftop deck with access from 3rd floor. Date: April 30, 2012 Client: Golhar Abhay M | Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 30, 2012 | Permit id: 398504 | |||||
New construction of a 3 story wood framed sfd with flat roof, full cellar and roof deck with access from 3rd floor. Date: May 31, 2012 Client: Golhar Abhay M | Permit type: New construction permit | Permit status: Completed | Completion date: February 12, 2013 | Permit id: 405697 | |||||
SCORE 98 200amp svc of eqiuptment. Wiring throughout,wiring sfd as per 2008 nec Date: October 5, 2012 Contractor: David Bell Client: Golhar Abhay M | Permit type: Electrical permit | Permit status: Completed | Completion date: December 13, 2012 | Permit id: 431284 | |||||
SCORE 96 Installing new 1" dual copper service, new sewer line & main drain (sfd) pa1 call#2012 261 0210 Date: September 17, 2012 Contractor: Frankie D And Benny G Plumbing And Client: Golhar Abhay M | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 3, 2013 | Permit id: 427688 | |||||
SCORE 96 3 toilets, 2 showers, 3 lavs, 1 ks, 1 washer box(sfd) Date: September 24, 2012 Contractor: Frankie D And Benny G Plumbing And Client: Golhar Abhay M | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 7, 2013 | Permit id: 428833 |